# Berkeley Pit — mine flooding and hydraulic containment

Case reference year: 2025 | Location: Butte, Montana, United States

The flooded open pit and connected underground mine workings require water-level management and treatment. Public monitoring records link hydraulic containment with an ongoing remediation operation.

## Suggested capstone study

An original teaching brief based on the documented project. Study assumptions and student designs are separate from the built project.

Develop a water-balance and containment assessment for the flooded mine, with sensitivity to uncertain inflow and temporary treatment interruption.

### Inputs to assemble

- Use a dated monthly monitoring report for observed discharge and compliance data.
- Identify pit and mine-water levels, the relevant control elevation and its datum, and unmeasured groundwater exchanges.

### Deliverables

- Build a time-dependent storage/pumping model that distinguishes observations, calibrated flows and conservative assumptions.
- Develop outage scenarios, monitoring triggers and a recovery pumping strategy with treatment-capacity constraints.
- A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.
- A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points.

### Review questions

- How would a stable pit level conceal a change in groundwater capture or treatment demand?
- What evidence is needed before comparing a reported control elevation with survey data recorded in a different vertical datum?

## Published project information

### Design — partial

EPA identifies the Butte Mine Flooding operable unit and continuing treatment. The official monitoring archive provides dated discharge reports; pit water, connected mine water and surrounding aquifers must be represented as a connected system.

### Cost information — not-found

A project-specific estimate, bid schedule or final account was not found in the reviewed sources.

### Schedule information — not-found

A dated project programme was not found in the reviewed sources; develop a study schedule from the documented method.

### Completion and records — partial

Public discharge reports and EPA status material document continuing treatment and monitoring. They are dated operational records, not evidence that treatment can be discontinued.

## Project image

The Berkeley Pit in Butte, Montana, photographed in 2013. The image shows the actual flooded pit; water-level controls and treatment performance should be read from the dated monitoring records.

Credit: Chris06 / Wikimedia Commons
Image source: https://commons.wikimedia.org/wiki/File:2013_Berkeley_Pit,_Butte,_Montana_(1).jpg
Image rights: CC BY-SA 4.0 — https://creativecommons.org/licenses/by-sa/4.0

## Sources

- Current site status — Butte Mine Flooding OU3 (U.S. Environmental Protection Agency; date not stated): https://www.epa.gov/butte/current-site-status
- January 2025 monthly discharge monitoring report (Thompson and Griffis / Montana Technological University archive; date not stated): https://digitalcommons.mtech.edu/superfund_silverbowbutte/1282/
- Berkeley Pit water-treatment explanation (PitWatch / Butte Mine Flooding information programme; date not stated): https://pitwatch.org/learn/water-treatment/
- 2013 Berkeley Pit, Butte, Montana (1).jpg (Chris06; 2013): https://commons.wikimedia.org/wiki/File:2013_Berkeley_Pit,_Butte,_Montana_(1).jpg

Sources checked: 2026-11-22. This brief is an original teaching aid. Source rights remain with their respective holders.