# Bluestone Dam — rock anchors and spillway-foundation protection

Case reference year: 2026 | Location: Hinton, West Virginia, United States

The safety programme combines anchoring, drainage and armor over the bedrock stilling basin. Construction must be staged while the spillway remains an active river-release route.

## Suggested capstone study

An original teaching brief based on the documented project. Study assumptions and student designs are separate from the built project.

Stage foundation anchoring and armor placement in half of an operating stilling basin.

### Inputs to assemble

- Extract the owner’s phase boundaries, diversion concept and uplift-control components.
- Define a study flood window and rock discontinuity model for temporary and permanent checks.

### Deliverables

- Check anchor demand and drain effectiveness for intact and blocked-drain scenarios.
- Prepare a cofferdam sequence and flood-response plan with excavation hold points.
- A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.
- A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points.

### Review questions

- How does temporary river diversion alter uplift beneath the work area?
- Which inspection or proof-test result should delay concreting over an anchor zone?

## Published project information

### Design — partial

USACE describes completed earlier phases and the ongoing stilling-basin work. The project is not labeled fully complete; the owner’s 2026 programme forecasts completion in 2030.

### Cost information — partial

The 2020 notice identifies a $319.6 million Phase 5 contract. It is not a final cost for all phases.

### Schedule information — partial

The 2026 owner update reports one half complete and forecasts overall completion in 2030; this supersedes the older 2020 contract forecast.

### Completion and records — not-found

Complete as-built drawings and acceptance records were not found in the reviewed sources.

## Project image

Bluestone Dam in 2022, showing work in the spillway area. The photograph corresponds to the ongoing dam-safety programme.

Credit: Antony-22
Image source: https://commons.wikimedia.org/wiki/File:Bluestone_Dam_2022a.jpg
Image rights: CC BY-SA 4.0 — https://creativecommons.org/licenses/by-sa/4.0

## Sources

- Safety assurance project and 2026 progress (USACE Great Lakes and Ohio River Division; date not stated): https://www.lrd.usace.army.mil/Missions/Projects/Article/3631104/bluestone-dam-dam-safety-assurance-mega-project/
- Phase 5 contract milestone (USACE; date not stated): https://www.usace.army.mil/Media/News/Article/2126116/bluestone-pdt-achieves-milestone/
- Bluestone Dam 2022a.jpg — image and reuse license (Wikimedia Commons / Antony-22; 2022): https://commons.wikimedia.org/wiki/File:Bluestone_Dam_2022a.jpg

Sources checked: 2026-11-22. This brief is an original teaching aid. Source rights remain with their respective holders.