# Bolivar Dam — seepage barriers in outwash and fractured abutment rock

Case reference year: 2017 | Location: Tuscarawas County, Ohio, United States

Rehabilitation combined a partial-depth barrier, blanket improvements, relief wells and an abutment grout curtain. The project authors explain construction problems in thin limestone units with open flow paths.

## Suggested capstone study

An original teaching brief based on the documented project. Study assumptions and student designs are separate from the built project.

Compare seepage-control combinations for an embankment on permeable outwash beside fractured rock.

### Inputs to assemble

- Separate foundation flow, rock-contact erosion and gate-system issues in the owner record.
- Extract the grout-curtain arrangement and treatment response to circulation losses.

### Deliverables

- Draw a seepage model with wall, blanket and relief-well alternatives.
- Specify drilling/grouting decisions and post-treatment piezometric performance criteria.
- A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.
- A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points.

### Review questions

- How can a partial-depth barrier still reduce internal-erosion risk?
- Where could seepage concentrate if the wall-to-rock transition is poorly treated?

## Published project information

### Design — partial

The USACE completion account identifies the combined risk-reduction measures. A technical paper details the abutment grouting and downstage treatment decisions.

### Cost information — not-found

A project-specific estimate, bid schedule or final account was not found in the reviewed sources.

### Schedule information — partial

The owner reports rehabilitation completion in October 2017.

### Completion and records — partial

The completion account describes post-implementation evaluation and the resulting dam-safety classification.

## Project image

Upstream view of Bolivar Dam in Ohio. The actual embankment is shown; the later seepage barrier and grout curtain are largely below ground.

Credit: Roseohioresident
Image source: https://commons.wikimedia.org/wiki/File:Bolivar_Dam_(Ohio)_upstream.jpg
Image rights: Public domain — https://commons.wikimedia.org/wiki/File:Bolivar_Dam_(Ohio)_upstream.jpg#Licensing

## Sources

- Completion and post-implementation review (US Army / USACE; date not stated): https://www.army.mil/article/200670/bolivar_receives_best_dam_safety_rating
- Grout-curtain construction at Bolivar Dam (USACE project authors / Environmental & Engineering Geoscience; date not stated): https://pubs.geoscienceworld.org/aeg/eeg/article-abstract/24/1/121/522957/Grout-Curtain-Construction-At-Bolivar-Dam-Ohio
- Bolivar Dam (Ohio) upstream.jpg — image and reuse license (Wikimedia Commons / Roseohioresident; date not stated): https://commons.wikimedia.org/wiki/File:Bolivar_Dam_(Ohio)_upstream.jpg

Sources checked: 2026-11-22. This brief is an original teaching aid. Source rights remain with their respective holders.