# Calaveras Dam replacement — seismic foundations and unexpected landslides

Case reference year: 2019 | Location: Sunol Valley, California, United States

Replacement of a seismically vulnerable dam encountered an additional ancient landslide during abutment excavation. Public environmental and budget records document supplemental investigation, design revisions and delivery consequences.

## Suggested capstone study

An original teaching brief based on the documented project. Study assumptions and student designs are separate from the built project.

Revise a dam-abutment excavation after construction exposes an unrecognized landslide mass.

### Inputs to assemble

- Extract the mapped hazard, supplemental investigation and treatment objective from the addendum.
- Separate original design assumptions, newly observed conditions and later access-road damage.

### Deliverables

- Compare removal and retained-remnant stabilization with groundwater sensitivities.
- Develop a revised excavation sequence, material handling plan and change-control estimate.
- A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.
- A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points.

### Review questions

- What observations would distinguish an ancient shear surface from ordinary weathered rock?
- How should uncertainty in the residual landslide geometry affect contingency quantities?

## Published project information

### Design — partial

The environmental addendum explains the left-abutment investigation and revised slope treatment. The consultant describes final-design responsibilities, while city oversight records track budget changes.

### Cost information — partial

The 2019 city analysis traces a budget change from $416 million to $823 million across successive revisions. These are programme budgets with multiple causes, not a foundation-only final account.

### Schedule information — not-found

A dated project programme was not found in the reviewed sources; develop a study schedule from the documented method.

### Completion and records — not-found

Complete as-built drawings and acceptance records were not found in the reviewed sources.

## Project image

Aerial view of Calaveras Reservoir during reconstruction of the dam. The image shows the actual replacement-project work area.

Credit: Kyle Hawton
Image source: https://commons.wikimedia.org/wiki/File:Aerial_view_of_Calaveras_Reservoir_showing_the_reconstruction_of_the_dam_wall.JPG
Image rights: CC BY-SA 4.0 — https://creativecommons.org/licenses/by-sa/4.0

## Sources

- Environmental addendum after left-abutment discoveries (San Francisco Planning / SFPUC; date not stated): https://sfplanning.s3.amazonaws.com/sfmea/2005.0161E_Adm1.pdf
- Final design and geotechnical investigations (AECOM; date not stated): https://aecom.com/projects/calaveras-dam-replacement-project/
- 2019 budget and legislative analysis (San Francisco Budget and Legislative Analyst; date not stated): https://sfgov.legistar.com/View.ashx?GUID=E44CE420-A2F2-4DE8-BA38-A16B402F5B23&ID=7102715&M=F
- Aerial view of Calaveras Reservoir showing the reconstruction of the dam wall.JPG — image and reuse license (Wikimedia Commons / Kyle Hawton; 2015): https://commons.wikimedia.org/wiki/File:Aerial_view_of_Calaveras_Reservoir_showing_the_reconstruction_of_the_dam_wall.JPG

Sources checked: 2026-11-22. This brief is an original teaching aid. Source rights remain with their respective holders.