{"schemaVersion":1,"updated":"2026-11-22","total":23,"records":[{"id":"wolf-creek","title":"Wolf Creek Dam — karst-foundation cutoff wall","summary":"A deep concrete barrier and associated grouting addressed seepage through the dam’s karst foundation. USACE documents completion and project scope.","topics":["dams-levees","seepage","rock","ground-improvement","delivery"],"country":"United States","region":"Jamestown, Kentucky","owner":"US Army Corps of Engineers","year":2013,"yearLabel":"Case reference year","projectType":"Rehabilitation","methods":["Cutoff wall","Karst grouting","Dam seepage control"],"documentationLevel":"project-summary","design":{"availability":"partial","summary":"The completion account describes approximately 1,197 overlapping piles forming a 4,000-foot barrier. It does not provide a complete issued-for-construction package.","sourceIds":["s1"]},"cost":{"availability":"partial","summary":"The March 2013 USACE account identifies a $594 million rehabilitation project; this is programme scope, not the wall’s final unit-price account.","sourceIds":["s1"]},"schedule":{"availability":"partial","summary":"Last pile placement was reported on 6 March 2013, nine months ahead of the then-planned December completion.","sourceIds":["s1"]},"records":{"availability":"partial","summary":"USACE records barrier completion and the subsequent reservoir review.","sourceIds":["s1"]},"capstone":{"label":"Suggested capstone study","scope":"An original teaching brief based on the documented project. Study assumptions and student designs are separate from the built project.","brief":"Compare a cutoff wall and grouting strategy for an operating dam over soluble rock, including continuity verification and reservoir constraints.","inputs":["Extract the documented barrier dimensions and geological problem.","Define an explicitly sourced or assumed permeability model for the study seepage calculation."],"deliverables":["Develop a seepage/uplift comparison and a wall-continuity QA plan.","Prepare a construction platform section and a reservoir/instrumentation hold-point sequence.","A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.","A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points."],"questions":["Which site data control the decision, and what additional investigation would reduce uncertainty?","How would the proposed solution change under the stated sensitivity cases, construction constraints and performance limits?"],"output":"Design report, calculation workbook, concept drawings, quantity schedule and construction programme."},"sources":[{"id":"s1","title":"Nashville District completes Wolf Creek Dam barrier wall","url":"https://www.dvidshub.net/news/103103/nashville-district-completes-wolf-creek-dam-barrier-wall","publisher":"USACE / DVIDS","year":2013,"access":"public-link","license":"US government public information; original credits retained","notes":"","checked":"2026-11-22"},{"id":"s2","title":"Wolf Creek Dam barrier-wall construction — published image and source","url":"https://www.dvidshub.net/image/1965076/nashville-district-highlights-its-notable-projects-leading-into-national-dam-safety-awareness-day","publisher":"DVIDS / U.S. Army Corps of Engineers","year":2012,"access":"public-link","license":"Public domain — U.S. federal government work","notes":"Project image source. Unmodified bytes from the publisher’s 1000-pixel image; responsive display only.","checked":"2026-11-22","localAssetIds":["project-image"]}],"assets":[{"id":"schematic","title":"Conceptual study schematic","kind":"figure","fileName":"wolf-creek.svg","mimeType":"image/svg+xml","bytes":985,"sha256":"ee95ff57b022b53ff13f55beb263a60b849d824c45c609ed976e0810f3961f8b","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/wolf-creek/download/schematic"},{"id":"project-image","title":"Wolf Creek Dam barrier-wall construction","kind":"project-image","fileName":"wolf-creek.jpg","mimeType":"image/jpeg","bytes":360915,"sha256":"3b361e7407fd987273b67296a8243d56d96b8acaacef0a11a35bbbf016ef58cc","sourceId":"s2","license":"Public domain — U.S. federal government work","width":1000,"height":664,"credit":"Leon Roberts / U.S. Army Corps of Engineers","sourceUrl":"https://www.dvidshub.net/image/1965076/nashville-district-highlights-its-notable-projects-leading-into-national-dam-safety-awareness-day","licenseUrl":"https://www.dvidshub.net/about/copyright","imageDate":"2012-05-02","evidenceFile":"image-provenance/wolf-creek-source.json","evidenceSha256":"7c60540ea61fdb963e680eb0e27ef54375564f419bba957c0086c51479fca3e5","transformations":"Unmodified bytes from the publisher’s 1000-pixel image; responsive display only.","rightsBasis":"See the per-image provenance record and linked license; source hosting alone is not the rights basis.","downloadUrl":"/cases/wolf-creek/download/project-image"},{"id":"capstone-brief","title":"Capstone brief (Markdown)","kind":"brief","fileName":"wolf-creek-capstone.md","mimeType":"text/markdown","bytes":3149,"sha256":"a6a8f5863cc2de9de547b3be3d54e50e32e3a1475422a83b73f24b26ce485245","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/wolf-creek/download/capstone-brief"}],"figure":{"assetId":"project-image","kind":"photograph","alt":"Concrete barrier-wall construction in the Wolf Creek Dam embankment on May 2, 2012.","caption":"Concrete barrier-wall construction in the Wolf Creek Dam embankment on May 2, 2012. U.S. Army Corps of Engineers photograph by Leon Roberts.","credit":"Leon Roberts / U.S. Army Corps of Engineers","sourceUrl":"https://www.dvidshub.net/image/1965076/nashville-district-highlights-its-notable-projects-leading-into-national-dam-safety-awareness-day","license":"Public domain — U.S. federal government work","licenseUrl":"https://www.dvidshub.net/about/copyright","width":1000,"height":664,"imageDate":"2012-05-02"},"figureCaption":"Concrete barrier-wall construction in the Wolf Creek Dam embankment on May 2, 2012. U.S. Army Corps of Engineers photograph by Leon Roberts.","qualityNotes":[],"checked":"2026-11-22","curatedOrder":20,"referenceValues":[],"teachingFigureCaption":"Conceptual study schematic; not an as-built project drawing.","imageEvidence":{"status":"acquired","identityVerified":true,"evidenceFile":"image-provenance/wolf-creek-source.json","evidenceSha256":"7c60540ea61fdb963e680eb0e27ef54375564f419bba957c0086c51479fca3e5","visualReview":"Original image inspected at card scale and against its caption/source; no AI-created replacement.","checked":"2026-11-22"},"localReportCount":0,"downloadBytes":365049,"sourceCount":2,"url":"/cases/wolf-creek"},{"id":"center-hill","title":"Center Hill Dam — grouting, cutoff wall and stabilizing berm","summary":"A staged rehabilitation treated foundation seepage and auxiliary-dam risks using grouting, a deep cutoff wall and a roller-compacted-concrete berm.","topics":["dams-levees","seepage","rock","ground-improvement","delivery"],"country":"United States","region":"DeKalb County, Tennessee","owner":"US Army Corps of Engineers","year":2020,"yearLabel":"Case reference year","projectType":"Rehabilitation","methods":["Foundation grouting","Cutoff wall","Stabilizing berm"],"documentationLevel":"project-summary","design":{"availability":"partial","summary":"USACE describes three major repair phases and their completed components; detailed construction plans are not attached to the completion release.","sourceIds":["s1"]},"cost":{"availability":"partial","summary":"The completion release reports $353 million overall, with $107 million grouting, $122 million cutoff and $50 million berm contracts; scopes differ from the programme total.","sourceIds":["s1"]},"schedule":{"availability":"partial","summary":"Reported phases were grouting in 2008–2010, cutoff in 2012–2015 and final berm completion celebrated in July 2020.","sourceIds":["s1"]},"records":{"availability":"partial","summary":"The USACE release documents the final repair phase and constructed features.","sourceIds":["s1"]},"capstone":{"label":"Suggested capstone study","scope":"An original teaching brief based on the documented project. Study assumptions and student designs are separate from the built project.","brief":"Develop a risk-based sequence of dam repairs in which initial grouting also informs the later cutoff design.","inputs":["Extract phase scope, wall depth and published contract-period information.","Identify the piezometric and geological evidence needed to assess each repaired failure mode."],"deliverables":["Prepare a seepage/stability failure-mode map and an investigation-to-construction decision process.","Compare a single-stage programme with the documented phased strategy.","A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.","A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points."],"questions":["Which site data control the decision, and what additional investigation would reduce uncertainty?","How would the proposed solution change under the stated sensitivity cases, construction constraints and performance limits?"],"output":"Design report, calculation workbook, concept drawings, quantity schedule and construction programme."},"sources":[{"id":"s1","title":"Berm construction completes last repair phase for dam rehabilitation","url":"https://www.usace.army.mil/Media/News-Releases/News-Release-Article-View/Article/2261687/berm-construction-completes-last-repair-phase-for-dam-rehabilitation/","publisher":"USACE","year":2020,"access":"public-link","license":"USACE public information; original credits retained","notes":"","checked":"2026-11-22"},{"id":"s2","title":"Center Hill auxiliary-dam RCC berm — published image and source","url":"https://www.dvidshub.net/image/6260111/berm-construction-completes-last-repair-phase-dam-rehabilitation","publisher":"DVIDS / U.S. Army Corps of Engineers","year":2020,"access":"public-link","license":"Public domain — U.S. federal government work","notes":"Project image source. Unmodified bytes from the publisher’s 1000-pixel image; responsive display only.","checked":"2026-11-22","localAssetIds":["project-image"]}],"assets":[{"id":"schematic","title":"Conceptual study schematic","kind":"figure","fileName":"center-hill.svg","mimeType":"image/svg+xml","bytes":985,"sha256":"ee95ff57b022b53ff13f55beb263a60b849d824c45c609ed976e0810f3961f8b","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/center-hill/download/schematic"},{"id":"project-image","title":"Center Hill auxiliary-dam RCC berm","kind":"project-image","fileName":"center-hill.jpg","mimeType":"image/jpeg","bytes":293503,"sha256":"a0d33fc9f80d78aecd1af015fbcb8573ffccfdd3639abf05c4993f77dfefa73c","sourceId":"s2","license":"Public domain — U.S. federal government work","width":1000,"height":667,"credit":"Leon Roberts / U.S. Army Corps of Engineers","sourceUrl":"https://www.dvidshub.net/image/6260111/berm-construction-completes-last-repair-phase-dam-rehabilitation","licenseUrl":"https://www.dvidshub.net/about/copyright","imageDate":"2020","evidenceFile":"image-provenance/center-hill-source.json","evidenceSha256":"7491f54c4d276ee87d196bb5ab594f571734776ba54d95bb86336014027cecf1","transformations":"Unmodified bytes from the publisher’s 1000-pixel image; responsive display only.","rightsBasis":"See the per-image provenance record and linked license; source hosting alone is not the rights basis.","downloadUrl":"/cases/center-hill/download/project-image"},{"id":"capstone-brief","title":"Capstone brief (Markdown)","kind":"brief","fileName":"center-hill-capstone.md","mimeType":"text/markdown","bytes":3178,"sha256":"fd3962a5077f1d6636c34b684c2ab4f19da43c9623771422cb63d524eb0013d6","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/center-hill/download/capstone-brief"}],"figure":{"assetId":"project-image","kind":"photograph","alt":"The roller-compacted-concrete berm at the Center Hill auxiliary dam, shown in the USACE project-completion image collection published in July 2020..","caption":"The roller-compacted-concrete berm at the Center Hill auxiliary dam, shown in the USACE project-completion image collection published in July 2020.","credit":"Leon Roberts / U.S. Army Corps of Engineers","sourceUrl":"https://www.dvidshub.net/image/6260111/berm-construction-completes-last-repair-phase-dam-rehabilitation","license":"Public domain — U.S. federal government work","licenseUrl":"https://www.dvidshub.net/about/copyright","width":1000,"height":667,"imageDate":"2020"},"figureCaption":"The roller-compacted-concrete berm at the Center Hill auxiliary dam, shown in the USACE project-completion image collection published in July 2020.","qualityNotes":[],"checked":"2026-11-22","curatedOrder":21,"referenceValues":[],"teachingFigureCaption":"Conceptual study schematic; not an as-built project drawing.","imageEvidence":{"status":"acquired","identityVerified":true,"evidenceFile":"image-provenance/center-hill-source.json","evidenceSha256":"7491f54c4d276ee87d196bb5ab594f571734776ba54d95bb86336014027cecf1","visualReview":"Original image inspected at card scale and against its caption/source; no AI-created replacement.","checked":"2026-11-22"},"localReportCount":0,"downloadBytes":297666,"sourceCount":2,"url":"/cases/center-hill"},{"id":"herbert-hoover","title":"Herbert Hoover Dike — seepage barriers and structure replacement","summary":"The rehabilitation combined cutoff walls, culvert replacements and embankment armoring around Lake Okeechobee. USACE provides a completion summary and project update.","topics":["dams-levees","seepage","ground-improvement","monitoring","delivery"],"country":"United States","region":"Lake Okeechobee, Florida","owner":"US Army Corps of Engineers","year":2023,"yearLabel":"Case reference year","projectType":"Rehabilitation","methods":["Cutoff walls","Internal erosion","Embankment armoring"],"documentationLevel":"technical-case","design":{"availability":"partial","summary":"USACE documents more than 56 miles of cutoff wall and replacement of 28 water-control structures, alongside other risk-reduction work.","sourceIds":["s1","s2"]},"cost":{"availability":"partial","summary":"The January 2023 announcement reports $1.5 billion invested; the later Fall 2023 update reports over $1.6 billion since 2001. Preserve the different dates and scopes.","sourceIds":["s1","s2"]},"schedule":{"availability":"partial","summary":"USACE celebrated construction completion in January 2023 after a programme begun in 2005.","sourceIds":["s1","s2"]},"records":{"availability":"partial","summary":"The completion release and later update describe completed risk-reduction features.","sourceIds":["s1","s2"]},"capstone":{"label":"Suggested capstone study","scope":"An original teaching brief based on the documented project. Study assumptions and student designs are separate from the built project.","brief":"Develop a reach-prioritization and treatment plan for a long embankment system with penetrations and heterogeneous seepage risk.","inputs":["Extract the completed work types and distinguish dike length from treated cutoff length.","Select one study reach and record what local borings, heads and structure details remain necessary."],"deliverables":["Compare seepage-control alternatives at a typical reach and at a culvert penetration.","Build a work-package schedule and QA plan for interfaces between walls and structures.","A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.","A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points."],"questions":["Which site data control the decision, and what additional investigation would reduce uncertainty?","How would the proposed solution change under the stated sensitivity cases, construction constraints and performance limits?"],"output":"Design report, calculation workbook, concept drawings, quantity schedule and construction programme."},"sources":[{"id":"s1","title":"Herbert Hoover Dike rehabilitation completion","url":"https://www.saj.usace.army.mil/Media/News-Releases/Article/3276863/usace-marks-herbert-hoover-dike-rehabilitation-project-completion-with-ribbon-c/","publisher":"USACE","year":2023,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s2","title":"Herbert Hoover Dike — Fall 2023 project update","url":"https://usace.contentdm.oclc.org/digital/api/collection/p16021coll11/id/6735/download","publisher":"USACE","year":2023,"access":"public-link","license":"USACE public information; original credits retained","notes":"","checked":"2026-11-22","localAssetIds":["herbert-hoover-update","project-image"]}],"assets":[{"id":"schematic","title":"Conceptual study schematic","kind":"figure","fileName":"herbert-hoover.svg","mimeType":"image/svg+xml","bytes":985,"sha256":"ee95ff57b022b53ff13f55beb263a60b849d824c45c609ed976e0810f3961f8b","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/herbert-hoover/download/schematic"},{"id":"herbert-hoover-update","title":"Herbert Hoover Dike project update, Fall 2023","kind":"report","fileName":"herbert-hoover-update.pdf","mimeType":"application/pdf","bytes":1823491,"sha256":"01202f04ff137dff3893984e220dba8cc131287ee65070944b1b0c4dea9d6e69","sourceId":"s2","license":"USACE public information; original credits retained","rightsUrl":"https://www.usace.army.mil/Privacy-and-Security/","rightsBasis":"USACE public-information policy permits copying and distribution unless otherwise indicated.","rightsEvidenceUrl":"https://www.usace.army.mil/Privacy-and-Security/","pages":2,"downloadUrl":"/cases/herbert-hoover/download/herbert-hoover-update"},{"id":"reference-values","title":"Published reference values (CSV)","kind":"table","fileName":"herbert-hoover-reference-values.csv","mimeType":"text/csv","bytes":767,"sha256":"03152f87e5ef980f6f0c4ca7440c17766655c72932e645aa4edb92b3a26c9f9e","sourceId":null,"license":"Factual values transcribed with source attribution; original selection and descriptions by Foundation Design","downloadUrl":"/cases/herbert-hoover/download/reference-values"},{"id":"project-image","title":"Herbert Hoover Dike cutoff-wall construction","kind":"project-image","fileName":"herbert-hoover.jpeg","mimeType":"image/jpeg","bytes":1250146,"sha256":"901a3bac7b402ad688e24f2fe77941a34e7cd9d3602d4edc5ac331ccd350cf6a","sourceId":"s2","license":"Public domain — U.S. federal government work","width":1200,"height":800,"credit":"U.S. Army Corps of Engineers, Jacksonville District","sourceUrl":"https://usace.contentdm.oclc.org/digital/api/collection/p16021coll11/id/6735/download","licenseUrl":"https://www.usace.army.mil/Privacy-and-Security/","imageDate":null,"evidenceFile":"image-provenance/herbert-hoover-source.json","evidenceSha256":"0bf437e163401247f8725180dba9abdf6f6aa5a4234808386c3f48ac5f91252e","transformations":"Unchanged original embedded image extracted from the identified PDF; no new marks, labels, retouching, or crop.","rightsBasis":"See the per-image provenance record and linked license; source hosting alone is not the rights basis.","downloadUrl":"/cases/herbert-hoover/download/project-image"},{"id":"capstone-brief","title":"Capstone brief (Markdown)","kind":"brief","fileName":"herbert-hoover-capstone.md","mimeType":"text/markdown","bytes":4026,"sha256":"ee6a2a35f3d9cab06c07dbb0f25fb69ea7cc757392cba4fbaaf9563b9c91d87d","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/herbert-hoover/download/capstone-brief"}],"figure":{"assetId":"project-image","kind":"photograph","alt":"Construction equipment working along the Herbert Hoover Dike at Lake Okeechobee.","caption":"Construction equipment working along the Herbert Hoover Dike at Lake Okeechobee. Original USACE photograph from the Fall 2023 project update.","credit":"U.S. Army Corps of Engineers, Jacksonville District","sourceUrl":"https://usace.contentdm.oclc.org/digital/api/collection/p16021coll11/id/6735/download","license":"Public domain — U.S. federal government work","licenseUrl":"https://www.usace.army.mil/Privacy-and-Security/","width":1200,"height":800,"imageDate":null},"figureCaption":"Construction equipment working along the Herbert Hoover Dike at Lake Okeechobee. Original USACE photograph from the Fall 2023 project update.","qualityNotes":[],"checked":"2026-11-22","curatedOrder":22,"referenceValues":[{"label":"Completed cutoff-wall length","value":56.2,"unit":"mile","scope":"Partial-penetration wall described in the Fall 2023 update.","sourceId":"s2","locator":"Embankment cutoff wall","basis":"Reported completed length."},{"label":"Replaced water-control structures","value":28,"unit":"count","scope":"Replacement work within the rehabilitation programme.","sourceId":"s2","locator":"Water control structures","basis":"Reported completed quantity."},{"label":"Removed or abandoned structures","value":4,"unit":"count","scope":"Structures no longer required.","sourceId":"s2","locator":"Water control structures","basis":"Reported completed quantity."}],"teachingFigureCaption":"Conceptual study schematic; not an as-built project drawing.","imageEvidence":{"status":"acquired","identityVerified":true,"evidenceFile":"image-provenance/herbert-hoover-source.json","evidenceSha256":"0bf437e163401247f8725180dba9abdf6f6aa5a4234808386c3f48ac5f91252e","visualReview":"Original image inspected at card scale and against its caption/source; no AI-created replacement.","checked":"2026-11-22"},"localReportCount":1,"downloadBytes":3079415,"sourceCount":2,"url":"/cases/herbert-hoover"},{"id":"folsom-spillway","title":"Folsom auxiliary spillway — rock excavation and foundation preparation","summary":"The auxiliary spillway required major rock excavation and preparation of the control-structure foundation before concrete placement.","topics":["rock","dams-levees","excavation","delivery"],"country":"United States","region":"Folsom, California","owner":"USACE / Bureau of Reclamation","year":2017,"yearLabel":"Case reference year","projectType":"Design and construction","methods":["Rock excavation","Foundation preparation","Controlled blasting"],"documentationLevel":"project-summary","design":{"availability":"partial","summary":"USACE construction accounts describe blasting completion, foundation cleaning and the subsequent control structure and chute.","sourceIds":["s1","s2"]},"cost":{"availability":"partial","summary":"USACE describes a $900 million cooperative effort, a programme total rather than a rock-excavation unit-rate schedule.","sourceIds":["s2"]},"schedule":{"availability":"partial","summary":"The source records initial excavation in 2008, final concrete stages in 2016 and the October 2017 completion ceremony.","sourceIds":["s2"]},"records":{"availability":"partial","summary":"The owner’s completion release identifies the constructed auxiliary spillway.","sourceIds":["s2"]},"capstone":{"label":"Suggested capstone study","scope":"An original teaching brief based on the documented project. Study assumptions and student designs are separate from the built project.","brief":"Plan a rock-foundation excavation and acceptance programme beside an operating dam and public transport route.","inputs":["Extract published construction stages and final structure dimensions.","Establish study discontinuity, groundwater and blast-vibration parameters explicitly."],"deliverables":["Prepare a temporary rock-slope/bench concept and foundation mapping checklist.","Design sequencing between blasting, cleaning, drainage, acceptance and concrete placement.","A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.","A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points."],"questions":["Which site data control the decision, and what additional investigation would reduce uncertainty?","How would the proposed solution change under the stated sensitivity cases, construction constraints and performance limits?"],"output":"Design report, calculation workbook, concept drawings, quantity schedule and construction programme."},"sources":[{"id":"s1","title":"Corps completes blasting for Folsom Dam spillway","url":"https://www.spk.usace.army.mil/Media/News-Stories/Article/479150/corps-completes-blasting-for-folsom-dam-spillway/","publisher":"USACE","year":2012,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s2","title":"Folsom auxiliary spillway completion ceremony","url":"https://www.spk.usace.army.mil/Media/News-Releases/Article/1347967/folsom-auxiliary-spillway-completion-ceremony-marks-conclusion-of-historic-proj/","publisher":"USACE","year":2017,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s3","title":"Corps completes final rock blasting for Folsom Dam spillway (7074960195).jpg — image and reuse license","url":"https://commons.wikimedia.org/wiki/File:Corps_completes_final_rock_blasting_for_Folsom_Dam_spillway_(7074960195).jpg","publisher":"Wikimedia Commons / U.S. Army Corps of Engineers Sacramento District","year":2012,"access":"public-link","license":"Public domain","notes":"Project image source. Unmodified image bytes from the publisher’s selected-size file; only responsive display sizing is applied by the website.","checked":"2026-11-22","localAssetIds":["project-image"]}],"assets":[{"id":"schematic","title":"Conceptual study schematic","kind":"figure","fileName":"folsom-spillway.svg","mimeType":"image/svg+xml","bytes":1017,"sha256":"ab086e9b878d71ca75443d4083022bf013c864b1ad5c4bbfbedf783b1ffc7360","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/folsom-spillway/download/schematic"},{"id":"project-image","title":"Corps completes final rock blasting for Folsom Dam spillway (7074960195).jpg","kind":"project-image","fileName":"folsom-spillway.jpg","mimeType":"image/jpeg","bytes":464701,"sha256":"7a19a74d7b3b5a33de9a62801a125a79786fab6e5e3741f2489f8163752e394c","sourceId":"s3","license":"Public domain","width":1280,"height":853,"credit":"U.S. Army Corps of Engineers Sacramento District","sourceUrl":"https://commons.wikimedia.org/wiki/File:Corps_completes_final_rock_blasting_for_Folsom_Dam_spillway_(7074960195).jpg","licenseUrl":"https://commons.wikimedia.org/wiki/File:Corps_completes_final_rock_blasting_for_Folsom_Dam_spillway_(7074960195).jpg#Licensing","imageDate":"2012-04-09 13:07","evidenceFile":"image-provenance/folsom-spillway-commons.json","evidenceSha256":"f8c58b1165831e3d43c019c6198f439b3999d2ca0dd921846e86483602a54411","transformations":"Unmodified image bytes from the publisher’s selected-size file; only responsive display sizing is applied by the website.","originalUrl":"https://upload.wikimedia.org/wikipedia/commons/a/a9/Corps_completes_final_rock_blasting_for_Folsom_Dam_spillway_%287074960195%29.jpg","downloadUrl":"/cases/folsom-spillway/download/project-image","rightsBasis":"See the per-image provenance record and linked license; source hosting alone is not the rights basis."},{"id":"capstone-brief","title":"Capstone brief (Markdown)","kind":"brief","fileName":"folsom-spillway-capstone.md","mimeType":"text/markdown","bytes":3360,"sha256":"9db574128d7dfcb79de13e692011843039bad04940c148f1a0128a63dc749079","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/folsom-spillway/download/capstone-brief"}],"figure":{"assetId":"project-image","kind":"photograph","alt":"Rock excavation for the Folsom Dam auxiliary spillway, April 2012.","caption":"Rock excavation for the Folsom Dam auxiliary spillway, April 2012. U.S. Army Corps of Engineers construction photograph.","credit":"U.S. Army Corps of Engineers Sacramento District","sourceUrl":"https://commons.wikimedia.org/wiki/File:Corps_completes_final_rock_blasting_for_Folsom_Dam_spillway_(7074960195).jpg","license":"Public domain","licenseUrl":"https://commons.wikimedia.org/wiki/File:Corps_completes_final_rock_blasting_for_Folsom_Dam_spillway_(7074960195).jpg#Licensing","width":1280,"height":853,"imageDate":"2012-04-09 13:07"},"figureCaption":"Rock excavation for the Folsom Dam auxiliary spillway, April 2012. U.S. Army Corps of Engineers construction photograph.","qualityNotes":[],"checked":"2026-11-22","curatedOrder":23,"referenceValues":[],"teachingFigureCaption":"Conceptual study schematic; not an as-built project drawing.","imageEvidence":{"status":"acquired","identityVerified":true,"evidenceFile":"image-provenance/folsom-spillway-commons.json","evidenceSha256":"f8c58b1165831e3d43c019c6198f439b3999d2ca0dd921846e86483602a54411","visualReview":"Original image inspected at card scale and against its caption/source; no AI-created replacement.","checked":"2026-11-22"},"localReportCount":0,"downloadBytes":469078,"sourceCount":3,"url":"/cases/folsom-spillway"},{"id":"oroville-spillways","title":"Oroville spillway recovery — erosion-resistant foundation reconstruction","summary":"Recovery rebuilt the main spillway and added a secant pile wall, splashpad and buttress at the emergency spillway after the 2017 incident.","topics":["rock","scour-erosion","dams-levees","seepage","delivery"],"country":"United States","region":"Oroville, California","owner":"California Department of Water Resources","year":2018,"yearLabel":"Case reference year","projectType":"Rehabilitation","methods":["Erosion control","Secant pile wall","Rock foundation drainage"],"documentationLevel":"technical-report","design":{"availability":"partial","summary":"DWR’s recovery page links investigations and describes the final-design reconstruction; the project update distinguishes initial mobilization from the completed design.","sourceIds":["s1","s2"]},"cost":{"availability":"partial","summary":"The September 2018 update estimated $940 million recovery through 2019, plus $160 million emergency response; these are dated estimates, not a final account.","sourceIds":["s2"]},"schedule":{"availability":"partial","summary":"Temporary main-spillway readiness was targeted for November 2017; final-design reconstruction was completed in 2018.","sourceIds":["s1","s2"]},"records":{"availability":"partial","summary":"DWR links consultant, inspection and forensic records from the recovery page.","sourceIds":["s1","s2"]},"capstone":{"label":"Suggested capstone study","scope":"An original teaching brief based on the documented project. Study assumptions and student designs are separate from the built project.","brief":"Develop an emergency-to-permanent reconstruction plan that addresses erosion, uplift and uncertain rock quality.","inputs":["Review the forensic findings and identify the selected failure mechanisms.","Extract the repair cross sections and distinguish temporary from permanent work."],"deliverables":["Prepare a foundation-drainage and erosion-protection concept with construction hold points.","Reconcile changing estimate scopes and show how geological uncertainty enters contingency.","A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.","A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points."],"questions":["Which site data control the decision, and what additional investigation would reduce uncertainty?","How would the proposed solution change under the stated sensitivity cases, construction constraints and performance limits?"],"output":"Design report, calculation workbook, concept drawings, quantity schedule and construction programme."},"sources":[{"id":"s1","title":"Oroville Spillways Recovery","url":"https://water.ca.gov/Programs/State-Water-Project/SWP-Facilities/Oroville/Oroville-Spillways","publisher":"California DWR","year":2018,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s2","title":"September 2018 construction and cost estimate update","url":"https://water.ca.gov/News/News-Releases/2018/Sept-18/Oroville-Spillways-Construction-and-Cost-Estimate-Update","publisher":"California DWR","year":2018,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s3","title":"Oroville Dam weir and emergency spillway erosion.jpg — image and reuse license","url":"https://commons.wikimedia.org/wiki/File:Oroville_Dam_weir_and_emergency_spillway_erosion.jpg","publisher":"Wikimedia Commons / California Department of Water Resources","year":2017,"access":"public-link","license":"Public domain","notes":"Project image source. Unmodified image bytes from the publisher’s selected-size file; only responsive display sizing is applied by the website.","checked":"2026-11-22","localAssetIds":["project-image"]}],"assets":[{"id":"schematic","title":"Conceptual study schematic","kind":"figure","fileName":"oroville-spillways.svg","mimeType":"image/svg+xml","bytes":1017,"sha256":"ab086e9b878d71ca75443d4083022bf013c864b1ad5c4bbfbedf783b1ffc7360","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/oroville-spillways/download/schematic"},{"id":"project-image","title":"Oroville Dam weir and emergency spillway erosion.jpg","kind":"project-image","fileName":"oroville-spillways.jpg","mimeType":"image/jpeg","bytes":320332,"sha256":"f4bd13af9ead3b5be6c9e4a05f99af18dd1c77f2fec0b5b3abc0cde34b401542","sourceId":"s3","license":"Public domain","width":1200,"height":900,"credit":"California Department of Water Resources","sourceUrl":"https://commons.wikimedia.org/wiki/File:Oroville_Dam_weir_and_emergency_spillway_erosion.jpg","licenseUrl":"https://commons.wikimedia.org/wiki/File:Oroville_Dam_weir_and_emergency_spillway_erosion.jpg#Licensing","imageDate":"2017-02-13","evidenceFile":"image-provenance/oroville-spillways-commons.json","evidenceSha256":"e0d98727520124a4f3f46bcb4cef896752cbd9e8edd6e0aa990b908411566689","transformations":"Unmodified image bytes from the publisher’s selected-size file; only responsive display sizing is applied by the website.","originalUrl":"https://upload.wikimedia.org/wikipedia/commons/b/bc/Oroville_Dam_weir_and_emergency_spillway_erosion.jpg","downloadUrl":"/cases/oroville-spillways/download/project-image","rightsBasis":"See the per-image provenance record and linked license; source hosting alone is not the rights basis."},{"id":"capstone-brief","title":"Capstone brief (Markdown)","kind":"brief","fileName":"oroville-spillways-capstone.md","mimeType":"text/markdown","bytes":3348,"sha256":"56fa6675b828b6b1cd30cec6dd7461afa664e2b2ba051586c8e6dce28299e59a","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/oroville-spillways/download/capstone-brief"}],"figure":{"assetId":"project-image","kind":"photograph","alt":"Oroville Dam’s emergency spillway and the erosion below its weir during the February 2017 spillway incident.","caption":"Oroville Dam’s emergency spillway and the erosion below its weir during the February 2017 spillway incident. California Department of Water Resources project photograph.","credit":"California Department of Water Resources","sourceUrl":"https://commons.wikimedia.org/wiki/File:Oroville_Dam_weir_and_emergency_spillway_erosion.jpg","license":"Public domain","licenseUrl":"https://commons.wikimedia.org/wiki/File:Oroville_Dam_weir_and_emergency_spillway_erosion.jpg#Licensing","width":1200,"height":900,"imageDate":"2017-02-13"},"figureCaption":"Oroville Dam’s emergency spillway and the erosion below its weir during the February 2017 spillway incident. California Department of Water Resources project photograph.","qualityNotes":[],"checked":"2026-11-22","curatedOrder":24,"referenceValues":[],"teachingFigureCaption":"Conceptual study schematic; not an as-built project drawing.","imageEvidence":{"status":"acquired","identityVerified":true,"evidenceFile":"image-provenance/oroville-spillways-commons.json","evidenceSha256":"e0d98727520124a4f3f46bcb4cef896752cbd9e8edd6e0aa990b908411566689","visualReview":"Original image inspected at card scale and against its caption/source; no AI-created replacement.","checked":"2026-11-22"},"localReportCount":0,"downloadBytes":324697,"sourceCount":3,"url":"/cases/oroville-spillways"},{"id":"teton-dam","title":"Teton Dam — internal erosion and first-filling investigation","summary":"The first-filling failure is documented through the Bureau of Reclamation’s history and the independent investigation report.","topics":["dams-levees","seepage","rock","site-investigation"],"country":"United States","region":"Eastern Idaho","owner":"US Bureau of Reclamation","year":1976,"yearLabel":"Case reference year","projectType":"Forensic investigation","methods":["Internal erosion","Filters and contacts","First-filling surveillance"],"documentationLevel":"investigation-report","design":{"availability":"partial","summary":"The official archive provides the original design/foundation investigation context and the 1976 failure report; the dam was not rebuilt.","sourceIds":["s1"]},"cost":{"availability":"not-found","summary":"A project-specific estimate, bid schedule or final account was not found in the reviewed sources.","sourceIds":[]},"schedule":{"availability":"partial","summary":"Failure occurred on 5 June 1976; the independent panel report was submitted in December 1976.","sourceIds":["s1"]},"records":{"availability":"partial","summary":"The official archive links the investigation and contemporary photographs; there is no completed replacement-dam record.","sourceIds":["s1"]},"capstone":{"label":"Suggested capstone study","scope":"An original teaching brief based on the documented project. Study assumptions and student designs are separate from the built project.","brief":"Evaluate alternative core/filter and foundation-treatment concepts using the investigation as a forensic reference, without treating a classroom redesign as an approved remedy.","inputs":["Extract foundation geology, core/filter arrangement and reservoir-filling observations.","Separate contemporary records from later interpretations of the failure mechanism."],"deliverables":["Prepare a potential-failure-mode analysis and a filtered-contact concept.","Design a first-filling monitoring and escalation plan.","A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.","A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points."],"questions":["Which site data control the decision, and what additional investigation would reduce uncertainty?","How would the proposed solution change under the stated sensitivity cases, construction constraints and performance limits?"],"output":"Design report, calculation workbook, concept drawings, quantity schedule and construction programme."},"sources":[{"id":"s1","title":"Teton Dam history and investigation archive","url":"https://www.usbr.gov/pn/snakeriver/dams/uppersnake/teton/","publisher":"Bureau of Reclamation","year":1976,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s2","title":"Breach of Teton Dam - DPLA - 657b673aa7b01ea982116a68bef069b4.jpg — image and reuse license","url":"https://commons.wikimedia.org/wiki/File:Breach_of_Teton_Dam_-_DPLA_-_657b673aa7b01ea982116a68bef069b4.jpg","publisher":"Wikimedia Commons / Department of the Interior. Bureau of Reclamation. Denver Office. 3/4/1988","year":1976,"access":"public-link","license":"Public domain","notes":"Project image source. Unmodified image bytes from the publisher’s selected-size file; only responsive display sizing is applied by the website.","checked":"2026-11-22","localAssetIds":["project-image"]}],"assets":[{"id":"schematic","title":"Conceptual study schematic","kind":"figure","fileName":"teton-dam.svg","mimeType":"image/svg+xml","bytes":985,"sha256":"ee95ff57b022b53ff13f55beb263a60b849d824c45c609ed976e0810f3961f8b","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/teton-dam/download/schematic"},{"id":"project-image","title":"Breach of Teton Dam - DPLA - 657b673aa7b01ea982116a68bef069b4.jpg","kind":"project-image","fileName":"teton-dam.jpg","mimeType":"image/jpeg","bytes":343519,"sha256":"ee45a14882d8e40ef7cdb8d2ece02d9b5374b2d05f99d4b1b102ea2a0eeda844","sourceId":"s2","license":"Public domain","width":1280,"height":1343,"credit":"U.S. Bureau of Reclamation / U.S. National Archives at Denver","sourceUrl":"https://commons.wikimedia.org/wiki/File:Breach_of_Teton_Dam_-_DPLA_-_657b673aa7b01ea982116a68bef069b4.jpg","licenseUrl":"https://commons.wikimedia.org/wiki/File:Breach_of_Teton_Dam_-_DPLA_-_657b673aa7b01ea982116a68bef069b4.jpg#Licensing","imageDate":"1976-06-05","evidenceFile":"image-provenance/teton-dam-commons.json","evidenceSha256":"37ed6c24f2101c2bca27da33b67333e9b1d6149cc3a7f12fc66d13eb389b47b9","transformations":"Unmodified image bytes from the publisher’s selected-size file; only responsive display sizing is applied by the website.","originalUrl":"https://upload.wikimedia.org/wikipedia/commons/0/0c/Breach_of_Teton_Dam_-_DPLA_-_657b673aa7b01ea982116a68bef069b4.jpg","downloadUrl":"/cases/teton-dam/download/project-image","rightsBasis":"See the per-image provenance record and linked license; source hosting alone is not the rights basis."},{"id":"capstone-brief","title":"Capstone brief (Markdown)","kind":"brief","fileName":"teton-dam-capstone.md","mimeType":"text/markdown","bytes":3122,"sha256":"b5d2ac5ede4ca9a488bd21b78156a925a2c65879cecce063d5ca5c2181a91114","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/teton-dam/download/capstone-brief"}],"figure":{"assetId":"project-image","kind":"photograph","alt":"The breach of Teton Dam, June 5, 1976.","caption":"The breach of Teton Dam, June 5, 1976. Historical project photograph from the U.S. Bureau of Reclamation collection.","credit":"U.S. Bureau of Reclamation / U.S. National Archives at Denver","sourceUrl":"https://commons.wikimedia.org/wiki/File:Breach_of_Teton_Dam_-_DPLA_-_657b673aa7b01ea982116a68bef069b4.jpg","license":"Public domain","licenseUrl":"https://commons.wikimedia.org/wiki/File:Breach_of_Teton_Dam_-_DPLA_-_657b673aa7b01ea982116a68bef069b4.jpg#Licensing","width":1280,"height":1343,"imageDate":"1976-06-05"},"figureCaption":"The breach of Teton Dam, June 5, 1976. Historical project photograph from the U.S. Bureau of Reclamation collection.","qualityNotes":["This is a failure-analysis case, not a successfully completed design example."],"checked":"2026-11-22","curatedOrder":25,"referenceValues":[],"teachingFigureCaption":"Conceptual study schematic; not an as-built project drawing.","imageEvidence":{"status":"acquired","identityVerified":true,"evidenceFile":"image-provenance/teton-dam-commons.json","evidenceSha256":"37ed6c24f2101c2bca27da33b67333e9b1d6149cc3a7f12fc66d13eb389b47b9","visualReview":"Original image inspected at card scale and against its caption/source; no AI-created replacement.","checked":"2026-11-22"},"localReportCount":0,"downloadBytes":347626,"sourceCount":2,"url":"/cases/teton-dam"},{"id":"olmsted-locks","title":"Olmsted Locks and Dam — marine construction and project controls","summary":"The navigation replacement became operational in 2018 after a long construction programme. USACE publishes project-control updates and completion material.","topics":["dams-levees","deep-foundations","coastal-offshore","delivery"],"country":"United States","region":"Ohio River, Illinois–Kentucky","owner":"US Army Corps of Engineers","year":2018,"yearLabel":"Case reference year","projectType":"Design and construction","methods":["Marine foundation construction","Construction staging","Earned-value comparison"],"documentationLevel":"technical-report","design":{"availability":"partial","summary":"The public project material supports marine construction and sequencing studies; detailed foundation design must be obtained from project-specific technical records.","sourceIds":["s1","s2"]},"cost":{"availability":"partial","summary":"The August 2018 scorecard distinguishes planned, earned and actual expenditure at its reporting date; it is not the final closeout account.","sourceIds":["s1","s2"]},"schedule":{"availability":"partial","summary":"The 2018 update gives planned versus current completion/operational milestones; the ribbon-cutting release records the August 2018 event.","sourceIds":["s1","s2"]},"records":{"availability":"partial","summary":"Owner completion and award accounts are available; a full geotechnical completion report was not located.","sourceIds":["s1","s2"]},"capstone":{"label":"Suggested capstone study","scope":"An original teaching brief based on the documented project. Study assumptions and student designs are separate from the built project.","brief":"Compare construction sequencing and foundation-installation risks for a major river structure while maintaining navigation.","inputs":["Extract the published work packages, dated cost scorecard and operational milestone.","Identify missing geotechnical design and production-rate information before pricing a study alternative."],"deliverables":["Develop a river-access, foundation-installation and closure sequence.","Reconcile planned, earned and actual cost terminology without treating budgeted quantities as final expenditures.","A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.","A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points."],"questions":["Which site data control the decision, and what additional investigation would reduce uncertainty?","How would the proposed solution change under the stated sensitivity cases, construction constraints and performance limits?"],"output":"Design report, calculation workbook, concept drawings, quantity schedule and construction programme."},"sources":[{"id":"s1","title":"Olmsted Locks and Dam — August 2018 update","url":"https://www.iwr.usace.army.mil/Portals/70/docs/IWUB/board_meetings/meeting88/UB88_01_Olmsted_Locks_and_Dam_Update_Rissler_28Aug18.pdf","publisher":"USACE","year":2018,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s2","title":"Corps cuts ribbon on Olmsted project","url":"https://www.lrd.usace.army.mil/News/News-Releases/Article/1617621/corps-cuts-ribbon-on-olmsted-locks-and-dam-project/","publisher":"USACE","year":2018,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s3","title":"Olmsted Locks and Dam aerial view.jpg — image and reuse license","url":"https://commons.wikimedia.org/wiki/File:Olmsted_Locks_and_Dam_aerial_view.jpg","publisher":"Wikimedia Commons / LouisvilleUSACE","year":2013,"access":"public-link","license":"Public domain","notes":"Project image source. Unmodified image bytes from the publisher’s selected-size file; only responsive display sizing is applied by the website.","checked":"2026-11-22","localAssetIds":["project-image"]}],"assets":[{"id":"schematic","title":"Conceptual study schematic","kind":"figure","fileName":"olmsted-locks.svg","mimeType":"image/svg+xml","bytes":985,"sha256":"ee95ff57b022b53ff13f55beb263a60b849d824c45c609ed976e0810f3961f8b","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/olmsted-locks/download/schematic"},{"id":"project-image","title":"Olmsted Locks and Dam aerial view.jpg","kind":"project-image","fileName":"olmsted-locks.jpg","mimeType":"image/jpeg","bytes":337003,"sha256":"25c89d760530e1e3eca24c97144ecde5f02a5b58c8e74840e0b040e9d1a01086","sourceId":"s3","license":"Public domain","width":1280,"height":989,"credit":"LouisvilleUSACE","sourceUrl":"https://commons.wikimedia.org/wiki/File:Olmsted_Locks_and_Dam_aerial_view.jpg","licenseUrl":"https://commons.wikimedia.org/wiki/File:Olmsted_Locks_and_Dam_aerial_view.jpg#Licensing","imageDate":"2013-08-21 11:35","evidenceFile":"image-provenance/olmsted-locks-commons.json","evidenceSha256":"b6891b8530650f83a47ef38a15779f5a5821a64128e800d64de25c6d704f68a6","transformations":"Unmodified image bytes from the publisher’s selected-size file; only responsive display sizing is applied by the website.","originalUrl":"https://upload.wikimedia.org/wikipedia/commons/c/ca/Olmsted_Locks_and_Dam_aerial_view.jpg","downloadUrl":"/cases/olmsted-locks/download/project-image","rightsBasis":"See the per-image provenance record and linked license; source hosting alone is not the rights basis."},{"id":"capstone-brief","title":"Capstone brief (Markdown)","kind":"brief","fileName":"olmsted-locks-capstone.md","mimeType":"text/markdown","bytes":3361,"sha256":"4315f61fa271ea7990fca5219e1d9baf260650bd49dba05b560e1fe1f1807ed9","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/olmsted-locks/download/capstone-brief"}],"figure":{"assetId":"project-image","kind":"photograph","alt":"Aerial view of the Olmsted Locks and Dam construction site, with lower pier shells being prepared for concrete placement.","caption":"Aerial view of the Olmsted Locks and Dam construction site, with lower pier shells being prepared for concrete placement. U.S. Army Corps of Engineers project photograph.","credit":"LouisvilleUSACE","sourceUrl":"https://commons.wikimedia.org/wiki/File:Olmsted_Locks_and_Dam_aerial_view.jpg","license":"Public domain","licenseUrl":"https://commons.wikimedia.org/wiki/File:Olmsted_Locks_and_Dam_aerial_view.jpg#Licensing","width":1280,"height":989,"imageDate":"2013-08-21 11:35"},"figureCaption":"Aerial view of the Olmsted Locks and Dam construction site, with lower pier shells being prepared for concrete placement. U.S. Army Corps of Engineers project photograph.","qualityNotes":[],"checked":"2026-11-22","curatedOrder":26,"referenceValues":[],"teachingFigureCaption":"Conceptual study schematic; not an as-built project drawing.","imageEvidence":{"status":"acquired","identityVerified":true,"evidenceFile":"image-provenance/olmsted-locks-commons.json","evidenceSha256":"b6891b8530650f83a47ef38a15779f5a5821a64128e800d64de25c6d704f68a6","visualReview":"Original image inspected at card scale and against its caption/source; no AI-created replacement.","checked":"2026-11-22"},"localReportCount":0,"downloadBytes":341349,"sourceCount":3,"url":"/cases/olmsted-locks"},{"id":"17th-street-canal","title":"17th Street Canal — floodwall failure and reevaluation","summary":"Post-Katrina investigations and reevaluation examine the canal floodwall/levee system, including the soil profile and interaction between the wall and foundation.","topics":["dams-levees","seepage","retaining-walls","laboratory-testing","site-investigation"],"country":"United States","region":"New Orleans, Louisiana","owner":"US Army Corps of Engineers","year":2005,"yearLabel":"Case reference year","projectType":"Forensic investigation","methods":["Floodwall stability","Undrained strength","Water-filled gap","Seepage"],"documentationLevel":"investigation-report","design":{"availability":"partial","summary":"USACE publishes reevaluation material and later remediation decisions. The record distinguishes the original I-wall problem from subsequent protection measures.","sourceIds":["s1","s2"]},"cost":{"availability":"not-found","summary":"A project-specific estimate, bid schedule or final account was not found in the reviewed sources.","sourceIds":[]},"schedule":{"availability":"not-found","summary":"A dated project programme was not found in the reviewed sources; develop a study schedule from the documented method.","sourceIds":[]},"records":{"availability":"partial","summary":"The reevaluation and remediation decisions are linked; complete as-built records for all later works are not included.","sourceIds":["s1","s2"]},"capstone":{"label":"Suggested capstone study","scope":"An original teaching brief based on the documented project. Study assumptions and student designs are separate from the built project.","brief":"Reconcile competing ground-model and wall-loading assumptions, then propose a monitored remediation concept.","inputs":["Extract a published cross section and the laboratory/field-test evidence for foundation strength.","Identify canal water levels, wall embedment and alternative assumptions for a water-filled gap."],"deliverables":["Compare effective-stress/undrained equilibrium cases and sensitivity to weak layers.","Develop a remediation alternatives assessment and a verification investigation.","A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.","A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points."],"questions":["Which site data control the decision, and what additional investigation would reduce uncertainty?","How would the proposed solution change under the stated sensitivity cases, construction constraints and performance limits?"],"output":"Design report, calculation workbook, concept drawings, quantity schedule and construction programme."},"sources":[{"id":"s1","title":"17th Street Canal reevaluation","url":"https://www.mvn.usace.army.mil/portals/56/docs/hsdrrs/MOWL-17th-St-Canal.pdf","publisher":"USACE","year":null,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s2","title":"Decision record for outfall-canal remediation","url":"https://www.mvn.usace.army.mil/Media/News-Releases/Article/474147/district-commander-signs-decision-record-for-remediation-work-at-outfall-canals/","publisher":"USACE","year":2010,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s3","title":"NOAA Katrina NOLA 17th Street breach Aug 31 2005.jpg — image and reuse license","url":"https://commons.wikimedia.org/wiki/File:NOAA_Katrina_NOLA_17th_Street_breach_Aug_31_2005.jpg","publisher":"Wikimedia Commons / NOAA","year":2005,"access":"public-link","license":"Public domain","notes":"Project image source. Unmodified image bytes from the publisher’s selected-size file; only responsive display sizing is applied by the website.","checked":"2026-11-22","localAssetIds":["project-image"]}],"assets":[{"id":"schematic","title":"Conceptual study schematic","kind":"figure","fileName":"17th-street-canal.svg","mimeType":"image/svg+xml","bytes":985,"sha256":"ee95ff57b022b53ff13f55beb263a60b849d824c45c609ed976e0810f3961f8b","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/17th-street-canal/download/schematic"},{"id":"project-image","title":"NOAA Katrina NOLA 17th Street breach Aug 31 2005.jpg","kind":"project-image","fileName":"17th-street-canal.jpg","mimeType":"image/jpeg","bytes":977324,"sha256":"4639a5baf2a1b834fae4f2b53ab79923419920b8f3b16a2e77e8ce7edb2cba2d","sourceId":"s3","license":"Public domain","width":1082,"height":1323,"credit":"NOAA","sourceUrl":"https://commons.wikimedia.org/wiki/File:NOAA_Katrina_NOLA_17th_Street_breach_Aug_31_2005.jpg","licenseUrl":"https://commons.wikimedia.org/wiki/File:NOAA_Katrina_NOLA_17th_Street_breach_Aug_31_2005.jpg#Licensing","imageDate":"2005-08","evidenceFile":"image-provenance/17th-street-canal-commons.json","evidenceSha256":"cab42e822a4adb6db090593124612f985014194d864bb832d291240d96c01aef","transformations":"Unmodified image bytes from the publisher’s selected-size file; only responsive display sizing is applied by the website.","originalUrl":"https://upload.wikimedia.org/wikipedia/commons/c/cb/NOAA_Katrina_NOLA_17th_Street_breach_Aug_31_2005.jpg","downloadUrl":"/cases/17th-street-canal/download/project-image","rightsBasis":"See the per-image provenance record and linked license; source hosting alone is not the rights basis."},{"id":"capstone-brief","title":"Capstone brief (Markdown)","kind":"brief","fileName":"17th-street-canal-capstone.md","mimeType":"text/markdown","bytes":3240,"sha256":"f25f19a3fb10fabdc8a6c29c1359ee75db4fa42a4cef7977c4f8ec0b967ef236","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/17th-street-canal/download/capstone-brief"}],"figure":{"assetId":"project-image","kind":"photograph","alt":"Aerial view of the 17th Street Canal breach and surrounding flooding after Hurricane Katrina.","caption":"Aerial view of the 17th Street Canal breach and surrounding flooding after Hurricane Katrina in August 2005. NOAA photograph.","credit":"NOAA","sourceUrl":"https://commons.wikimedia.org/wiki/File:NOAA_Katrina_NOLA_17th_Street_breach_Aug_31_2005.jpg","license":"Public domain","licenseUrl":"https://commons.wikimedia.org/wiki/File:NOAA_Katrina_NOLA_17th_Street_breach_Aug_31_2005.jpg#Licensing","width":1082,"height":1323,"imageDate":"2005-08"},"figureCaption":"Aerial view of the 17th Street Canal breach and surrounding flooding after Hurricane Katrina in August 2005. NOAA photograph.","qualityNotes":[],"checked":"2026-11-22","curatedOrder":31,"referenceValues":[],"teachingFigureCaption":"Conceptual study schematic; not an as-built project drawing.","imageEvidence":{"status":"acquired","identityVerified":true,"evidenceFile":"image-provenance/17th-street-canal-commons.json","evidenceSha256":"cab42e822a4adb6db090593124612f985014194d864bb832d291240d96c01aef","visualReview":"Original image inspected at card scale and against its caption/source; no AI-created replacement.","checked":"2026-11-22"},"localReportCount":0,"downloadBytes":981549,"sourceCount":3,"url":"/cases/17th-street-canal"},{"id":"lower-san-fernando","title":"Lower San Fernando Dam — liquefaction and post-earthquake stability","summary":"The upstream embankment slide during the 1971 earthquake became a major case for evaluating liquefaction, residual strength and post-shaking stability.","topics":["seismic","dams-levees","laboratory-testing","slopes"],"country":"United States","region":"Los Angeles, California","owner":"Los Angeles Department of Water and Power; USACE/USGS investigations","year":1971,"yearLabel":"Case reference year","projectType":"Forensic investigation","methods":["Liquefaction","Residual strength","Post-earthquake stability"],"documentationLevel":"investigation-report","design":{"availability":"partial","summary":"USACE reevaluation reports address the slide mechanism; a USGS fact sheet describes the later Los Angeles dam system.","sourceIds":["s1","s2"]},"cost":{"availability":"not-found","summary":"A project-specific estimate, bid schedule or final account was not found in the reviewed sources.","sourceIds":[]},"schedule":{"availability":"partial","summary":"The earthquake occurred on 9 February 1971; later reports reassess the mechanism.","sourceIds":["s1","s2"]},"records":{"availability":"partial","summary":"The linked reports contain forensic sections and investigations, rather than a completed replacement-design package.","sourceIds":["s1","s2"]},"capstone":{"label":"Suggested capstone study","scope":"An original teaching brief based on the documented project. Study assumptions and student designs are separate from the built project.","brief":"Assess how laboratory interpretation and residual-strength selection affect a back-analysis of an earthquake-induced embankment slide.","inputs":["Extract the historical cross section, hydraulic fill zones and identified liquefied region.","Keep triggering, residual-strength and deformation analyses as separate steps."],"deliverables":["Develop a sensitivity matrix for post-shaking stability and water level.","Compare redesign/operational mitigation concepts without presenting a single correlation as a full seismic assessment.","A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.","A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points."],"questions":["Which site data control the decision, and what additional investigation would reduce uncertainty?","How would the proposed solution change under the stated sensitivity cases, construction constraints and performance limits?"],"output":"Design report, calculation workbook, concept drawings, quantity schedule and construction programme."},"sources":[{"id":"s1","title":"Reevaluation of Lower San Fernando Dam — Report 2","url":"https://erdc-library.erdc.dren.mil/handle/11681/6154","publisher":"USACE ERDC","year":null,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s2","title":"USGS Fact Sheet 096-95 — The Los Angeles Dam Story","url":"https://pubs.usgs.gov/fs/1995/0096/","publisher":"USGS","year":1995,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s3","title":"Lower San Fernando Dam — USGS photograph reproduced as Figure 24 in Bilodeau et al. (2007)","url":"https://www.aegweb.org/assets/docs/la.pdf","publisher":"USGS photograph reproduced by Environmental & Engineering Geoscience / AEG","year":1971,"access":"public-link","license":"Public domain — original USGS photograph","notes":"Project image source. Unchanged original embedded USGS photograph extracted from the identified publication; no retouching, crop, or added marks.","checked":"2026-11-22","localAssetIds":["project-image"]}],"assets":[{"id":"schematic","title":"Conceptual study schematic","kind":"figure","fileName":"lower-san-fernando.svg","mimeType":"image/svg+xml","bytes":989,"sha256":"7ed6562b41c1ef6286cc62d81928348d9f071653ee41e073ab8e6a4e68cf4e34","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/lower-san-fernando/download/schematic"},{"id":"project-image","title":"Lower San Fernando Dam after the 1971 earthquake — USGS photograph","kind":"project-image","fileName":"lower-san-fernando.jpeg","mimeType":"image/jpeg","bytes":407005,"sha256":"c385b44176f35dfef0983c6b9b069e3a493d84ba49be5124237a720e006e41cf","sourceId":"s3","license":"Public domain — original USGS photograph","width":1395,"height":1462,"credit":"R. E. Wallace / U.S. Geological Survey (1971), reproduced as Figure 24 in Bilodeau et al. (2007)","sourceUrl":"https://www.aegweb.org/assets/docs/la.pdf","licenseUrl":"https://www.usgs.gov/information-policies-and-instructions/copyrights-and-credits","imageDate":"1971","evidenceFile":"image-provenance/lower-san-fernando-source.json","evidenceSha256":"f421ee2fe177e9d384a58b0fd4d11b069af4d3736b5c1bc51e4f02e90795bc67","transformations":"Unchanged original embedded USGS photograph extracted from the identified publication; no retouching, crop, or added marks.","rightsBasis":"See the per-image provenance record and linked license; source hosting alone is not the rights basis.","downloadUrl":"/cases/lower-san-fernando/download/project-image"},{"id":"capstone-brief","title":"Capstone brief (Markdown)","kind":"brief","fileName":"lower-san-fernando-capstone.md","mimeType":"text/markdown","bytes":3230,"sha256":"fb3470eadfc523033b41b83129c705c9dd321f576f1ad3f61ac5719596ed4b54","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/lower-san-fernando/download/capstone-brief"}],"figure":{"assetId":"project-image","kind":"photograph","alt":"Liquefaction damage and slumped concrete lining at Lower San Fernando Dam after the 1971 earthquake.","caption":"Lower San Fernando Dam and Lower Van Norman Reservoir after the 1971 San Fernando earthquake. The slumped concrete lining follows liquefaction of the hydraulic fill. Original USGS photograph by R. E. Wallace.","credit":"R. E. Wallace / U.S. Geological Survey (1971), reproduced as Figure 24 in Bilodeau et al. (2007)","sourceUrl":"https://www.aegweb.org/assets/docs/la.pdf","license":"Public domain — original USGS photograph","licenseUrl":"https://www.usgs.gov/information-policies-and-instructions/copyrights-and-credits","width":1395,"height":1462,"imageDate":"1971"},"figureCaption":"Lower San Fernando Dam and Lower Van Norman Reservoir after the 1971 San Fernando earthquake. The slumped concrete lining follows liquefaction of the hydraulic fill. Original USGS photograph by R. E. Wallace.","qualityNotes":[],"checked":"2026-11-22","curatedOrder":32,"referenceValues":[],"teachingFigureCaption":"Conceptual study schematic; not an as-built project drawing.","imageEvidence":{"status":"acquired","identityVerified":true,"evidenceFile":"image-provenance/lower-san-fernando-source.json","evidenceSha256":"f421ee2fe177e9d384a58b0fd4d11b069af4d3736b5c1bc51e4f02e90795bc67","visualReview":"Original image inspected at card scale and against its caption/source; no AI-created replacement.","checked":"2026-11-22"},"localReportCount":0,"downloadBytes":411224,"sourceCount":3,"url":"/cases/lower-san-fernando"},{"id":"milltown-dam-removal","title":"Milltown Reservoir — dam removal and contaminated sediment remediation","summary":"Reservoir drawdown, dam removal and sediment excavation/capping were coordinated with river restoration and replacement of affected water-supply wells.","topics":["geoenvironmental","dewatering","earthworks","dams-levees","monitoring"],"country":"United States","region":"Missoula County, Montana","owner":"US EPA / Montana and responsible-party partners","year":2009,"yearLabel":"Case reference year","projectType":"Remediation and restoration","methods":["Sediment dewatering","Excavation and capping","Groundwater response"],"documentationLevel":"technical-report","design":{"availability":"partial","summary":"EPA’s five-year review describes the implemented remedy and site components. Different operable units have different completion status.","sourceIds":["s1","s2"]},"cost":{"availability":"not-found","summary":"A project-specific estimate, bid schedule or final account was not found in the reviewed sources.","sourceIds":[]},"schedule":{"availability":"partial","summary":"The 2021 review records remedial work beginning in 2006 and final dam removal in March 2009; later site restoration and monitoring followed.","sourceIds":["s1","s2"]},"records":{"availability":"partial","summary":"The five-year review evaluates remedy performance; it does not state that every Clark Fork operable unit is complete.","sourceIds":["s1","s2"]},"capstone":{"label":"Suggested capstone study","scope":"An original teaching brief based on the documented project. Study assumptions and student designs are separate from the built project.","brief":"Develop a phased contaminated-sediment removal plan while maintaining downstream water quality and protecting nearby wells.","inputs":["Extract the remedy scope for the reservoir operable unit, not the entire Clark Fork site.","Identify sediment handling, groundwater and restored-channel monitoring information."],"deliverables":["Prepare a dewatering/well-impact assessment and sediment handling sequence.","Compare excavation, onsite containment and capping with monitoring/closure criteria.","A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.","A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points."],"questions":["Which site data control the decision, and what additional investigation would reduce uncertainty?","How would the proposed solution change under the stated sensitivity cases, construction constraints and performance limits?"],"output":"Design report, calculation workbook, concept drawings, quantity schedule and construction programme."},"sources":[{"id":"s1","title":"Third five-year review — Milltown Reservoir/Clark Fork","url":"https://nepis.epa.gov/Exe/ZyPURL.cgi?Dockey=P101GPHY.TXT","publisher":"US EPA","year":2021,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s2","title":"Milltown Reservoir Sediments cleanup profile","url":"https://cumulis.epa.gov/supercpad/SiteProfiles/index.cfm?fuseaction=second.cleanup&id=0800445","publisher":"US EPA","year":null,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s3","title":"Excavation.jpg — image and reuse license","url":"https://commons.wikimedia.org/wiki/File:Excavation.jpg","publisher":"Wikimedia Commons / M Kustudia","year":2008,"access":"public-link","license":"CC BY-SA 3.0","notes":"Project image source. Unmodified image bytes from the publisher’s selected-size file; only responsive display sizing is applied by the website.","checked":"2026-11-22","localAssetIds":["project-image"]}],"assets":[{"id":"schematic","title":"Conceptual study schematic","kind":"figure","fileName":"milltown-dam-removal.svg","mimeType":"image/svg+xml","bytes":991,"sha256":"26222485f74844ee89b3f605791d3913e3b1100909062100b32642ad290c3b48","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/milltown-dam-removal/download/schematic"},{"id":"project-image","title":"Excavation.jpg","kind":"project-image","fileName":"milltown-dam-removal.jpg","mimeType":"image/jpeg","bytes":92446,"sha256":"c89444bbdf35eaa35ede26e64248eef43c17962bdb52b85aa8b7ea6a94ab395b","sourceId":"s3","license":"CC BY-SA 3.0","width":640,"height":473,"credit":"M Kustudia","sourceUrl":"https://commons.wikimedia.org/wiki/File:Excavation.jpg","licenseUrl":"https://creativecommons.org/licenses/by-sa/3.0","imageDate":"2008-10-14","evidenceFile":"image-provenance/milltown-dam-removal-commons.json","evidenceSha256":"b542555b3a16fa6c34d99f848043d15ea64dc6789961e70910b6bfc421dd6895","transformations":"Unmodified image bytes from the publisher’s selected-size file; only responsive display sizing is applied by the website.","originalUrl":"https://upload.wikimedia.org/wikipedia/commons/8/8f/Excavation.jpg","downloadUrl":"/cases/milltown-dam-removal/download/project-image","rightsBasis":"See the per-image provenance record and linked license; source hosting alone is not the rights basis."},{"id":"capstone-brief","title":"Capstone brief (Markdown)","kind":"brief","fileName":"milltown-dam-removal-capstone.md","mimeType":"text/markdown","bytes":3054,"sha256":"7aee3520ebde422ce33cc80a110f0ed5313bdaa02a3ba95536fc18e40182447a","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/milltown-dam-removal/download/capstone-brief"}],"figure":{"assetId":"project-image","kind":"photograph","alt":"Remediation work at the Milltown Reservoir Superfund site in Montana.","caption":"Remediation work at the Milltown Reservoir Superfund site in Montana. The photograph shows excavation at the actual cleanup and dam-removal project.","credit":"M Kustudia","sourceUrl":"https://commons.wikimedia.org/wiki/File:Excavation.jpg","license":"CC BY-SA 3.0","licenseUrl":"https://creativecommons.org/licenses/by-sa/3.0","width":640,"height":473,"imageDate":"2008-10-14"},"figureCaption":"Remediation work at the Milltown Reservoir Superfund site in Montana. The photograph shows excavation at the actual cleanup and dam-removal project.","qualityNotes":[],"checked":"2026-11-22","curatedOrder":34,"referenceValues":[],"teachingFigureCaption":"Conceptual study schematic; not an as-built project drawing.","imageEvidence":{"status":"acquired","identityVerified":true,"evidenceFile":"image-provenance/milltown-dam-removal-commons.json","evidenceSha256":"b542555b3a16fa6c34d99f848043d15ea64dc6789961e70910b6bfc421dd6895","visualReview":"Original image inspected at card scale and against its caption/source; no AI-created replacement.","checked":"2026-11-22"},"localReportCount":0,"downloadBytes":96491,"sourceCount":3,"url":"/cases/milltown-dam-removal"},{"id":"san-vicente-dam","title":"San Vicente Dam raise — rock preparation and RCC interface","summary":"The existing concrete dam was raised using roller-compacted concrete. Owner documents connect excavation to competent rock, treatment of localized poor material and seepage control with the enlarged structure.","topics":["rock","dams-levees","seepage","excavation","delivery"],"country":"United States","region":"San Diego County, California","owner":"San Diego County Water Authority","year":2014,"yearLabel":"Case reference year","projectType":"Design, construction and performance","methods":["Rock excavation","Dental concrete","Consolidation grouting","RCC"],"documentationLevel":"technical-case","design":{"availability":"partial","summary":"The environmental design commitments describe proposed foundation measures; the completion account establishes the constructed dam raise. Detailed final foundation treatment records are not included.","sourceIds":["s1","s2"]},"cost":{"availability":"not-found","summary":"A project-specific estimate, bid schedule or final account was not found in the reviewed sources.","sourceIds":[]},"schedule":{"availability":"partial","summary":"The owner reports foundation preparation beginning in June 2009 and construction ending in June 2014.","sourceIds":["s1","s2"]},"records":{"availability":"not-found","summary":"Complete as-built drawings and acceptance records were not found in the reviewed sources.","sourceIds":[]},"capstone":{"label":"Suggested capstone study","scope":"An original teaching brief based on the documented project. Study assumptions and student designs are separate from the built project.","brief":"Plan foundation preparation and construction of an RCC enlargement beside an existing gravity dam.","inputs":["Extract the owner’s foundation-treatment commitments and construction milestones.","Identify rock defects, existing-dam support and old/new concrete interfaces needing detailed verification."],"deliverables":["Prepare excavation acceptance criteria, dental-concrete details and grout/drain layouts.","Check a representative enlarged section for sliding and uplift, with treatment effectiveness sensitivities.","A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.","A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points."],"questions":["How does excavating beside the original dam change temporary stability requirements?","Which field observations should decide whether a weak rock pocket is removed or treated?"],"output":"Design report, calculation workbook, concept drawings, quantity schedule and construction programme."},"sources":[{"id":"s1","title":"Geology and soils design commitments","url":"https://www.sdcwa.org/sites/default/files/files/environmental-docs/csp/Section%2003_08%2C%20Alt%201%20Geology%20%2008%2024%2007.pdf","publisher":"San Diego County Water Authority","year":null,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s2","title":"Completion of the dam raise","url":"https://www.sdcwa.org/historic-san-vicente-dam-raise-project-completed/","publisher":"San Diego County Water Authority","year":null,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s3","title":"Drone Photography San Vicente Reservoir and Dam San Diego.jpg — image and reuse license","url":"https://commons.wikimedia.org/wiki/File:Drone_Photography_San_Vicente_Reservoir_and_Dam_San_Diego.jpg","publisher":"Wikimedia Commons / Redideo","year":2024,"access":"public-link","license":"CC BY-SA 4.0","notes":"Project image source. Unmodified publisher-generated display-size file; the original source URL and publisher metadata are retained. No AI-generated replacement or content alteration.","checked":"2026-11-22","localAssetIds":["project-image"]}],"assets":[{"id":"schematic","title":"Conceptual study schematic","kind":"figure","fileName":"san-vicente-dam.svg","mimeType":"image/svg+xml","bytes":1017,"sha256":"ab086e9b878d71ca75443d4083022bf013c864b1ad5c4bbfbedf783b1ffc7360","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/san-vicente-dam/download/schematic"},{"id":"project-image","title":"Drone Photography San Vicente Reservoir and Dam San Diego.jpg","kind":"project-image","fileName":"san-vicente-dam.jpg","mimeType":"image/jpeg","bytes":169202,"sha256":"13b8f0c81856c9a03fefd07c981f6913f52c9e46eb2ba83a8706c2f6db0b55e2","sourceId":"s3","license":"CC BY-SA 4.0","width":1280,"height":715,"credit":"Redideo","sourceUrl":"https://commons.wikimedia.org/wiki/File:Drone_Photography_San_Vicente_Reservoir_and_Dam_San_Diego.jpg","licenseUrl":"https://creativecommons.org/licenses/by-sa/4.0","imageDate":"2024-04-21","evidenceFile":"image-provenance/san-vicente-dam-commons.json","evidenceSha256":"e1a6c813b0c557b0253bdb3b0e6764fe4402a1e58f2a6282e512b67dd9e29779","transformations":"Unmodified publisher-generated display-size file; the original source URL and publisher metadata are retained. No AI-generated replacement or content alteration.","originalUrl":"https://upload.wikimedia.org/wikipedia/commons/f/fd/Drone_Photography_San_Vicente_Reservoir_and_Dam_San_Diego.jpg","downloadUrl":"/cases/san-vicente-dam/download/project-image","originalSha1":"a17feb3503b42dbb142e24edfd3a3f2663af8f7b","imageDownloadAllowed":true,"rightsBasis":"See the per-image provenance record and linked license; source hosting alone is not the rights basis."},{"id":"capstone-brief","title":"Capstone brief (Markdown)","kind":"brief","fileName":"san-vicente-dam-capstone.md","mimeType":"text/markdown","bytes":3308,"sha256":"f5024109cac1cebbe29b76af2538e1c2ea9fba72955662e777a3a827ca7baefa","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/san-vicente-dam/download/capstone-brief"}],"figure":{"assetId":"project-image","kind":"photograph","alt":"Aerial view of the raised San Vicente Dam and reservoir in San Diego County.","caption":"Aerial view of the raised San Vicente Dam and reservoir in San Diego County. The photograph shows the actual completed dam, not a rendering of the proposed raise.","credit":"Redideo","sourceUrl":"https://commons.wikimedia.org/wiki/File:Drone_Photography_San_Vicente_Reservoir_and_Dam_San_Diego.jpg","license":"CC BY-SA 4.0","licenseUrl":"https://creativecommons.org/licenses/by-sa/4.0","width":1280,"height":715,"imageDate":"2024-04-21","imageDownloadAllowed":true},"figureCaption":"Aerial view of the raised San Vicente Dam and reservoir in San Diego County. The photograph shows the actual completed dam, not a rendering of the proposed raise.","qualityNotes":[],"checked":"2026-11-22","addedIn":"r13","curatedOrder":62,"referenceValues":[],"teachingFigureCaption":"Conceptual study schematic; not an as-built project drawing.","imageEvidence":{"status":"acquired","identityVerified":true,"evidenceFile":"image-provenance/san-vicente-dam-commons.json","evidenceSha256":"e1a6c813b0c557b0253bdb3b0e6764fe4402a1e58f2a6282e512b67dd9e29779","visualReview":"Viewed the complete publisher photograph in the final contact sheets or individually and compared it with the source identity, date, and caption. The caption distinguishes project context from the particular underground treatment or construction stage.","checked":"2026-11-22"},"localReportCount":0,"downloadBytes":173527,"sourceCount":3,"url":"/cases/san-vicente-dam"},{"id":"calaveras-dam","title":"Calaveras Dam replacement — seismic foundations and unexpected landslides","summary":"Replacement of a seismically vulnerable dam encountered an additional ancient landslide during abutment excavation. Public environmental and budget records document supplemental investigation, design revisions and delivery consequences.","topics":["dams-levees","seismic","slopes","rock","site-investigation","delivery"],"country":"United States","region":"Sunol Valley, California","owner":"San Francisco Public Utilities Commission","year":2019,"yearLabel":"Case reference year","projectType":"Design, construction and performance","methods":["Abutment excavation","Seismic embankment design","Landslide stabilization"],"documentationLevel":"technical-report","design":{"availability":"partial","summary":"The environmental addendum explains the left-abutment investigation and revised slope treatment. The consultant describes final-design responsibilities, while city oversight records track budget changes.","sourceIds":["s1","s2","s3"]},"cost":{"availability":"partial","summary":"The 2019 city analysis traces a budget change from $416 million to $823 million across successive revisions. These are programme budgets with multiple causes, not a foundation-only final account.","sourceIds":["s1","s2","s3"]},"schedule":{"availability":"not-found","summary":"A dated project programme was not found in the reviewed sources; develop a study schedule from the documented method.","sourceIds":[]},"records":{"availability":"not-found","summary":"Complete as-built drawings and acceptance records were not found in the reviewed sources.","sourceIds":[]},"capstone":{"label":"Suggested capstone study","scope":"An original teaching brief based on the documented project. Study assumptions and student designs are separate from the built project.","brief":"Revise a dam-abutment excavation after construction exposes an unrecognized landslide mass.","inputs":["Extract the mapped hazard, supplemental investigation and treatment objective from the addendum.","Separate original design assumptions, newly observed conditions and later access-road damage."],"deliverables":["Compare removal and retained-remnant stabilization with groundwater sensitivities.","Develop a revised excavation sequence, material handling plan and change-control estimate.","A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.","A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points."],"questions":["What observations would distinguish an ancient shear surface from ordinary weathered rock?","How should uncertainty in the residual landslide geometry affect contingency quantities?"],"output":"Design report, calculation workbook, concept drawings, quantity schedule and construction programme."},"sources":[{"id":"s1","title":"Environmental addendum after left-abutment discoveries","url":"https://sfplanning.s3.amazonaws.com/sfmea/2005.0161E_Adm1.pdf","publisher":"San Francisco Planning / SFPUC","year":null,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s2","title":"Final design and geotechnical investigations","url":"https://aecom.com/projects/calaveras-dam-replacement-project/","publisher":"AECOM","year":null,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s3","title":"2019 budget and legislative analysis","url":"https://sfgov.legistar.com/View.ashx?GUID=E44CE420-A2F2-4DE8-BA38-A16B402F5B23&ID=7102715&M=F","publisher":"San Francisco Budget and Legislative Analyst","year":null,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s4","title":"Aerial view of Calaveras Reservoir showing the reconstruction of the dam wall.JPG — image and reuse license","url":"https://commons.wikimedia.org/wiki/File:Aerial_view_of_Calaveras_Reservoir_showing_the_reconstruction_of_the_dam_wall.JPG","publisher":"Wikimedia Commons / Kyle Hawton","year":2015,"access":"public-link","license":"CC BY-SA 4.0","notes":"Project image source. Unmodified publisher-generated display-size file; the original source URL and publisher metadata are retained. No AI-generated replacement or content alteration.","checked":"2026-11-22","localAssetIds":["project-image"]}],"assets":[{"id":"schematic","title":"Conceptual study schematic","kind":"figure","fileName":"calaveras-dam.svg","mimeType":"image/svg+xml","bytes":985,"sha256":"ee95ff57b022b53ff13f55beb263a60b849d824c45c609ed976e0810f3961f8b","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/calaveras-dam/download/schematic"},{"id":"project-image","title":"Aerial view of Calaveras Reservoir showing the reconstruction of the dam wall.JPG","kind":"project-image","fileName":"calaveras-dam.jpg","mimeType":"image/jpeg","bytes":263048,"sha256":"4b2838d0f8faaf72aa29c476d993568f3533c88816ec281b3be550b2f7b06bba","sourceId":"s4","license":"CC BY-SA 4.0","width":1280,"height":720,"credit":"Kyle Hawton","sourceUrl":"https://commons.wikimedia.org/wiki/File:Aerial_view_of_Calaveras_Reservoir_showing_the_reconstruction_of_the_dam_wall.JPG","licenseUrl":"https://creativecommons.org/licenses/by-sa/4.0","imageDate":"2015-03-22 14:12:56","evidenceFile":"image-provenance/calaveras-dam-commons.json","evidenceSha256":"dfe8d170b97213af3fa3c4663da03310fe5fe662f0642aa16a8ccbb7d763b7b7","transformations":"Unmodified publisher-generated display-size file; the original source URL and publisher metadata are retained. No AI-generated replacement or content alteration.","originalUrl":"https://upload.wikimedia.org/wikipedia/commons/6/67/Aerial_view_of_Calaveras_Reservoir_showing_the_reconstruction_of_the_dam_wall.JPG","downloadUrl":"/cases/calaveras-dam/download/project-image","originalSha1":"3c6bd773968322a17452887f8c6e484af5dc8bf4","imageDownloadAllowed":true,"rightsBasis":"See the per-image provenance record and linked license; source hosting alone is not the rights basis."},{"id":"capstone-brief","title":"Capstone brief (Markdown)","kind":"brief","fileName":"calaveras-dam-capstone.md","mimeType":"text/markdown","bytes":3596,"sha256":"28570b7ef1084de40740abad204dfe5b3b1cf54b66164bb11fc8d3e016bd0939","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/calaveras-dam/download/capstone-brief"}],"figure":{"assetId":"project-image","kind":"photograph","alt":"Aerial view of Calaveras Reservoir during reconstruction of the dam.","caption":"Aerial view of Calaveras Reservoir during reconstruction of the dam. The image shows the actual replacement-project work area.","credit":"Kyle Hawton","sourceUrl":"https://commons.wikimedia.org/wiki/File:Aerial_view_of_Calaveras_Reservoir_showing_the_reconstruction_of_the_dam_wall.JPG","license":"CC BY-SA 4.0","licenseUrl":"https://creativecommons.org/licenses/by-sa/4.0","width":1280,"height":720,"imageDate":"2015-03-22 14:12:56","imageDownloadAllowed":true},"figureCaption":"Aerial view of Calaveras Reservoir during reconstruction of the dam. The image shows the actual replacement-project work area.","qualityNotes":[],"checked":"2026-11-22","addedIn":"r13","curatedOrder":63,"referenceValues":[],"teachingFigureCaption":"Conceptual study schematic; not an as-built project drawing.","imageEvidence":{"status":"acquired","identityVerified":true,"evidenceFile":"image-provenance/calaveras-dam-commons.json","evidenceSha256":"dfe8d170b97213af3fa3c4663da03310fe5fe662f0642aa16a8ccbb7d763b7b7","visualReview":"Viewed the complete publisher photograph in the final contact sheets or individually and compared it with the source identity, date, and caption. The caption distinguishes project context from the particular underground treatment or construction stage.","checked":"2026-11-22"},"localReportCount":0,"downloadBytes":267629,"sourceCount":4,"url":"/cases/calaveras-dam"},{"id":"isabella-dam","title":"Isabella Dam modifications — seismic, seepage and spillway risk","summary":"The main and auxiliary dams were modified to address combined seismic, seepage and flood-passage concerns. Owner records describe dam raises, downstream buttress work, filters, drainage and major spillway excavation.","topics":["dams-levees","seepage","seismic","rock","earthworks"],"country":"United States","region":"Kern County, California","owner":"US Army Corps of Engineers","year":2023,"yearLabel":"Case reference year","projectType":"Design, construction and performance","methods":["Embankment buttress","Filter compatibility","Rock excavation","Dam raise"],"documentationLevel":"technical-case","design":{"availability":"partial","summary":"USACE publishes the programme scope and completion milestones. A study should keep the different failure modes separate before combining their risk-reduction measures.","sourceIds":["s1","s2"]},"cost":{"availability":"partial","summary":"The owner identifies a $204 million Phase II construction contract awarded in 2017. This amount is contract scope, not the whole programme’s final cost.","sourceIds":["s1","s2"]},"schedule":{"availability":"partial","summary":"USACE reports substantial completion of the Phase II dam and spillway work in 2022; related facilities are separate phases.","sourceIds":["s1","s2"]},"records":{"availability":"partial","summary":"USACE documents a reduced dam-risk classification and lifting of operating restrictions in 2023.","sourceIds":["s1","s2"]},"capstone":{"label":"Suggested capstone study","scope":"An original teaching brief based on the documented project. Study assumptions and student designs are separate from the built project.","brief":"Develop a coordinated rehabilitation concept for an embankment dam with both seepage and seismic deficiencies.","inputs":["Extract the owner’s modification components and their targeted failure modes.","Build study sections for the embankment, filter/drain system and spillway excavation."],"deliverables":["Compare stability and seepage checks before and after buttressing and drainage improvements.","Sequence the work to preserve flood passage and define filter-placement quality controls.","A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.","A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points."],"questions":["Which risk remains if a dam raise is designed without checking seepage gradients?","How should rock excavation and embankment placement share temporary drainage and access?"],"output":"Design report, calculation workbook, concept drawings, quantity schedule and construction programme."},"sources":[{"id":"s1","title":"Isabella Dam safety modification project","url":"https://www.spk.usace.army.mil/Missions/Civil-Works/Isabella-Dam-Safety-Modification-Project/show/all/","publisher":"USACE Sacramento District","year":null,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s2","title":"Operating restrictions lifted after improvements","url":"https://www.spk.usace.army.mil/Media/News-Releases/Article/3465598/usace-lowers-isabella-dam-risk-rating-lifts-operating-restrictions/","publisher":"USACE Sacramento District","year":null,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s3","title":"Aerial view of the Isabella Dam Safety Modification Project.jpg — image and reuse license","url":"https://commons.wikimedia.org/wiki/File:Aerial_view_of_the_Isabella_Dam_Safety_Modification_Project.jpg","publisher":"Wikimedia Commons / U.S. Army Corps of Engineers, Sacramento District","year":2022,"access":"public-link","license":"Public domain","notes":"Project image source. Unmodified publisher-generated display-size file; the original source URL and publisher metadata are retained. No AI-generated replacement or content alteration.","checked":"2026-11-22","localAssetIds":["project-image"]}],"assets":[{"id":"schematic","title":"Conceptual study schematic","kind":"figure","fileName":"isabella-dam.svg","mimeType":"image/svg+xml","bytes":985,"sha256":"ee95ff57b022b53ff13f55beb263a60b849d824c45c609ed976e0810f3961f8b","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/isabella-dam/download/schematic"},{"id":"project-image","title":"Aerial view of the Isabella Dam Safety Modification Project.jpg","kind":"project-image","fileName":"isabella-dam.jpg","mimeType":"image/jpeg","bytes":575748,"sha256":"f66ddb737d1275d09742d361d46183bcf320b45382a1625ec3e4af5f0f9d5750","sourceId":"s3","license":"Public domain","width":1280,"height":960,"credit":"U.S. Army Corps of Engineers, Sacramento District","sourceUrl":"https://commons.wikimedia.org/wiki/File:Aerial_view_of_the_Isabella_Dam_Safety_Modification_Project.jpg","licenseUrl":"https://commons.wikimedia.org/wiki/File:Aerial_view_of_the_Isabella_Dam_Safety_Modification_Project.jpg#Licensing","imageDate":"2022-09-13 20:00:00","evidenceFile":"image-provenance/isabella-dam-commons.json","evidenceSha256":"585cadac20100e6a89c699ae881d201bb11fd0a8f347cfe93812aaa5a2d07c09","transformations":"Unmodified publisher-generated display-size file; the original source URL and publisher metadata are retained. No AI-generated replacement or content alteration.","originalUrl":"https://upload.wikimedia.org/wikipedia/commons/b/bd/Aerial_view_of_the_Isabella_Dam_Safety_Modification_Project.jpg","downloadUrl":"/cases/isabella-dam/download/project-image","originalSha1":"bb9ba911a669570736c2b7ca7f7f5b5e1079e431","imageDownloadAllowed":true,"rightsBasis":"See the per-image provenance record and linked license; source hosting alone is not the rights basis."},{"id":"capstone-brief","title":"Capstone brief (Markdown)","kind":"brief","fileName":"isabella-dam-capstone.md","mimeType":"text/markdown","bytes":3526,"sha256":"4abb6ee3c8ffc12bed66ea962c61321ddb882f4d54ec0ee44678422325316d28","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/isabella-dam/download/capstone-brief"}],"figure":{"assetId":"project-image","kind":"photograph","alt":"Aerial view of the Isabella Dam Safety Modification Project on 14 September 2022.","caption":"Aerial view of the Isabella Dam Safety Modification Project on 14 September 2022. USACE construction photograph of the actual dams and spillway works.","credit":"U.S. Army Corps of Engineers, Sacramento District","sourceUrl":"https://commons.wikimedia.org/wiki/File:Aerial_view_of_the_Isabella_Dam_Safety_Modification_Project.jpg","license":"Public domain","licenseUrl":"https://commons.wikimedia.org/wiki/File:Aerial_view_of_the_Isabella_Dam_Safety_Modification_Project.jpg#Licensing","width":1280,"height":960,"imageDate":"2022-09-13 20:00:00","imageDownloadAllowed":true},"figureCaption":"Aerial view of the Isabella Dam Safety Modification Project on 14 September 2022. USACE construction photograph of the actual dams and spillway works.","qualityNotes":[],"checked":"2026-11-22","addedIn":"r13","curatedOrder":64,"referenceValues":[],"teachingFigureCaption":"Conceptual study schematic; not an as-built project drawing.","imageEvidence":{"status":"acquired","identityVerified":true,"evidenceFile":"image-provenance/isabella-dam-commons.json","evidenceSha256":"585cadac20100e6a89c699ae881d201bb11fd0a8f347cfe93812aaa5a2d07c09","visualReview":"Viewed the complete publisher photograph in the final contact sheets or individually and compared it with the source identity, date, and caption. The caption distinguishes project context from the particular underground treatment or construction stage.","checked":"2026-11-22"},"localReportCount":0,"downloadBytes":580259,"sourceCount":3,"url":"/cases/isabella-dam"},{"id":"east-branch-dam","title":"East Branch Dam — cutoff-wall construction and verification","summary":"A dam-repair programme installed a cutoff wall to reduce foundation seepage. USACE reports the contract and return toward normal operations; the technical literature discusses wall verification drilling.","topics":["dams-levees","seepage","ground-improvement","monitoring"],"country":"United States","region":"Elk County, Pennsylvania","owner":"US Army Corps of Engineers","year":2020,"yearLabel":"Case reference year","projectType":"Design, construction and performance","methods":["Seepage cutoff","Wall continuity","Verification drilling"],"documentationLevel":"technical-case","design":{"availability":"partial","summary":"Owner releases establish the rehabilitation scope and outcome. The cited verification reference is an abstract, so complete verification datasets are not claimed locally.","sourceIds":["s1","s2","s3"]},"cost":{"availability":"partial","summary":"The owner reports a $132.5 million cutoff-wall rehabilitation contract awarded in 2014, not a certified final expenditure.","sourceIds":["s1","s2","s3"]},"schedule":{"availability":"not-found","summary":"A dated project programme was not found in the reviewed sources; develop a study schedule from the documented method.","sourceIds":[]},"records":{"availability":"partial","summary":"The owner’s 2020 releases describe repair completion and reservoir-operating changes.","sourceIds":["s1","s2","s3"]},"capstone":{"label":"Suggested capstone study","scope":"An original teaching brief based on the documented project. Study assumptions and student designs are separate from the built project.","brief":"Plan a cutoff-wall quality-assurance programme that can demonstrate continuity without damaging the finished barrier.","inputs":["Extract the owner’s treatment objective and the technical abstract’s verification problem.","Specify study foundation permeability zones and their uncertainty before comparing barrier options."],"deliverables":["Estimate seepage reduction for intact and defective wall scenarios.","Develop test-panel, drilling, permeability-testing and reservoir-response acceptance criteria.","A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.","A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points."],"questions":["Can a low-permeability test core establish continuity between adjacent panels?","What monitoring evidence is needed before relaxing an operating restriction?"],"output":"Design report, calculation workbook, concept drawings, quantity schedule and construction programme."},"sources":[{"id":"s1","title":"Repair-project conclusion","url":"https://www.usace.army.mil/Media/News/Article/2453263/thats-a-wrap-corps-concludes-east-branch-dam-repair-project/","publisher":"USACE Pittsburgh District","year":null,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s2","title":"Return to normal operations announcement","url":"https://www.usace.army.mil/Media/News-Releases/News-Release-Article-View/Article/2386554/east-branch-dam-safety-modification-project-returning-to-normal-operations-weat/","publisher":"USACE","year":null,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s3","title":"Lessons during cutoff-wall verification drilling","url":"https://damsafety.org/reference/east-branch-dam-lessons-learned-during-cutoff-wall-verification-drilling","publisher":"USACE authors / ASDSO","year":null,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s4","title":"USACE East Branch Clarion River Lake and Dam.jpg — image and reuse license","url":"https://commons.wikimedia.org/wiki/File:USACE_East_Branch_Clarion_River_Lake_and_Dam.jpg","publisher":"Wikimedia Commons / Margaret Luzier, U.S. Army Corps of Engineers","year":1985,"access":"public-link","license":"Public domain","notes":"Project image source. Unmodified publisher-generated display-size file; the original source URL and publisher metadata are retained. No AI-generated replacement or content alteration.","checked":"2026-11-22","localAssetIds":["project-image"]}],"assets":[{"id":"schematic","title":"Conceptual study schematic","kind":"figure","fileName":"east-branch-dam.svg","mimeType":"image/svg+xml","bytes":985,"sha256":"ee95ff57b022b53ff13f55beb263a60b849d824c45c609ed976e0810f3961f8b","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/east-branch-dam/download/schematic"},{"id":"project-image","title":"USACE East Branch Clarion River Lake and Dam.jpg","kind":"project-image","fileName":"east-branch-dam.jpg","mimeType":"image/jpeg","bytes":295707,"sha256":"3a7264103efa49f7a3c6af162e3c91518990dbc92b306642e9d07fe5b08de9d8","sourceId":"s4","license":"Public domain","width":1280,"height":854,"credit":"Margaret Luzier, U.S. Army Corps of Engineers","sourceUrl":"https://commons.wikimedia.org/wiki/File:USACE_East_Branch_Clarion_River_Lake_and_Dam.jpg","licenseUrl":"https://commons.wikimedia.org/wiki/File:USACE_East_Branch_Clarion_River_Lake_and_Dam.jpg#Licensing","imageDate":"1985-09-01","evidenceFile":"image-provenance/east-branch-dam-commons.json","evidenceSha256":"c1163c137e1710737ad46d4a734fa7fc01a733a7ca0c14b7a83b70471c24912a","transformations":"Unmodified publisher-generated display-size file; the original source URL and publisher metadata are retained. No AI-generated replacement or content alteration.","originalUrl":"https://upload.wikimedia.org/wikipedia/commons/b/b5/USACE_East_Branch_Clarion_River_Lake_and_Dam.jpg","downloadUrl":"/cases/east-branch-dam/download/project-image","originalSha1":"b4e50869d539b41ada751c645b44bb0bc14f6900","imageDownloadAllowed":true,"rightsBasis":"See the per-image provenance record and linked license; source hosting alone is not the rights basis."},{"id":"capstone-brief","title":"Capstone brief (Markdown)","kind":"brief","fileName":"east-branch-dam-capstone.md","mimeType":"text/markdown","bytes":3598,"sha256":"0424302e3006289b5f388519b956d139f36356bd9b7283fd3dc7b8a8a3076f4c","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/east-branch-dam/download/capstone-brief"}],"figure":{"assetId":"project-image","kind":"photograph","alt":"East Branch Clarion River Lake and Dam near Wilcox, Pennsylvania.","caption":"East Branch Clarion River Lake and Dam near Wilcox, Pennsylvania. USACE photograph of the dam treated by the later seepage-cutoff rehabilitation.","credit":"Margaret Luzier, U.S. Army Corps of Engineers","sourceUrl":"https://commons.wikimedia.org/wiki/File:USACE_East_Branch_Clarion_River_Lake_and_Dam.jpg","license":"Public domain","licenseUrl":"https://commons.wikimedia.org/wiki/File:USACE_East_Branch_Clarion_River_Lake_and_Dam.jpg#Licensing","width":1280,"height":854,"imageDate":"1985-09-01","imageDownloadAllowed":true},"figureCaption":"East Branch Clarion River Lake and Dam near Wilcox, Pennsylvania. USACE photograph of the dam treated by the later seepage-cutoff rehabilitation.","qualityNotes":[],"checked":"2026-11-22","addedIn":"r13","curatedOrder":65,"referenceValues":[],"teachingFigureCaption":"Conceptual study schematic; not an as-built project drawing.","imageEvidence":{"status":"acquired","identityVerified":true,"evidenceFile":"image-provenance/east-branch-dam-commons.json","evidenceSha256":"c1163c137e1710737ad46d4a734fa7fc01a733a7ca0c14b7a83b70471c24912a","visualReview":"Viewed the complete publisher photograph in the final contact sheets or individually and compared it with the source identity, date, and caption. The caption distinguishes project context from the particular underground treatment or construction stage.","checked":"2026-11-22"},"localReportCount":0,"downloadBytes":300290,"sourceCount":4,"url":"/cases/east-branch-dam"},{"id":"clearwater-dam","title":"Clearwater Dam — karst pretreatment and a hanging cutoff","summary":"A sinkhole prompted foundation exploration and grouting before construction of a deep seepage cutoff. The owner explains why treating solution-enlarged fractures was necessary for slurry-supported excavation.","topics":["dams-levees","seepage","rock","ground-improvement"],"country":"United States","region":"Wayne and Reynolds counties, Missouri","owner":"US Army Corps of Engineers","year":2011,"yearLabel":"Case reference year","projectType":"Design, construction and performance","methods":["Karst grouting","Hydromill cutoff","Slurry loss control"],"documentationLevel":"technical-case","design":{"availability":"partial","summary":"USACE’s rehabilitation account describes the grouting sequence, epikarst treatment and cutoff construction. Its forecast of later completion is retained as a forecast rather than a final-account statement.","sourceIds":["s1","s2"]},"cost":{"availability":"partial","summary":"The owner page forecast approximately $240 million for the overall rehabilitation. It is not presented here as a verified final account.","sourceIds":["s1","s2"]},"schedule":{"availability":"partial","summary":"USACE records placement of the final cutoff panel on 6 December 2011; the page’s remaining-work milestones were forecasts.","sourceIds":["s1","s2"]},"records":{"availability":"not-found","summary":"Complete as-built drawings and acceptance records were not found in the reviewed sources.","sourceIds":[]},"capstone":{"label":"Suggested capstone study","scope":"An original teaching brief based on the documented project. Study assumptions and student designs are separate from the built project.","brief":"Design a pretreatment and cutoff-wall sequence for a dam with connected karst features.","inputs":["Extract the reported seepage problem and the relationship between pretreatment and panel excavation.","Define a study range for rock permeability and connected-void sizes."],"deliverables":["Compare seepage paths around a hanging cutoff and through a locally defective panel.","Specify staged grouting, slurry-loss response and test-panel acceptance requirements.","A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.","A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points."],"questions":["Why can grouting be necessary even when a cutoff wall is the main permanent barrier?","How should treatment change when drilling loses circulation in a solution feature?"],"output":"Design report, calculation workbook, concept drawings, quantity schedule and construction programme."},"sources":[{"id":"s1","title":"Clearwater major rehabilitation","url":"https://www.swl.usace.army.mil/Missions/Civil-Works/Program-and-Project-Management/Clearwater-Major-Rehab/","publisher":"USACE Little Rock District","year":null,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s2","title":"Cutoff-wall construction account","url":"https://www.keller-na.com/projects/clearwater-lake-dam","publisher":"Keller","year":null,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22","localAssetIds":["project-image"]}],"assets":[{"id":"schematic","title":"Conceptual study schematic","kind":"figure","fileName":"clearwater-dam.svg","mimeType":"image/svg+xml","bytes":985,"sha256":"ee95ff57b022b53ff13f55beb263a60b849d824c45c609ed976e0810f3961f8b","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/clearwater-dam/download/schematic"},{"id":"project-image","title":"Clearwater Lake Dam — rehabilitation works in Missouri","kind":"project-image","fileName":"clearwater-dam-r13.jpg","mimeType":"image/jpeg","bytes":157363,"sha256":"6ba4f3f9f46427acca852befd6cbcf86ed02208a0029c7b3d592a2bc62707bea","sourceId":"s2","license":"No open reuse license verified; original copyright retained","width":900,"height":561,"credit":"Keller / Keller Management Services, LLC","sourceUrl":"https://www.keller-na.com/projects/clearwater-lake-dam","licenseUrl":"https://www.keller-na.com/projects/clearwater-lake-dam","imageDate":null,"evidenceFile":"image-provenance/clearwater-dam-r13-source.json","evidenceSha256":"c4e83124dafe5ca3ef277b3db6f7ac973e45d1e9d7dd7b6067175829993234e6","transformations":"Resized the full 2500 × 1559 source photograph proportionally to 900 × 561 pixels, JPEG quality 90; no cropping, added labels, or retouching.","originalUrl":"https://www.keller-na.com/sites/keller-na/files/2019-11/Clearwater-Lake-Dam-aerial.jpg","originalSha256":"a42680ec532691b4140cd8daf9878188de455cc941f6b4b7c9dd8eb695ee1575","imageDownloadAllowed":false,"rightsStatus":"editorial-reference","permissionStatus":"No open reuse permission verified","rightsNote":"Source-linked editorial reference; copyright remains with the original owner. The site does not offer this image as a reusable download.","imageUsage":"project-photograph","rightsBasis":"See the per-image provenance record and linked license; source hosting alone is not the rights basis.","previewUrl":"/cases/clearwater-dam/figure"},{"id":"capstone-brief","title":"Capstone brief (Markdown)","kind":"brief","fileName":"clearwater-dam-capstone.md","mimeType":"text/markdown","bytes":3059,"sha256":"784e54f18432f07f72ef06f300e14058dcca60705b6602c74041dc9056c09cb9","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/clearwater-dam/download/capstone-brief"}],"figure":{"assetId":"project-image","kind":"photograph","alt":"Aerial view of construction equipment along the crest of Clearwater Lake Dam in Missouri.","caption":"Aerial view of Clearwater Lake Dam in Missouri during the rehabilitation works, from Keller’s project account. The photograph shows construction along the dam crest.","credit":"Keller / Keller Management Services, LLC","sourceUrl":"https://www.keller-na.com/projects/clearwater-lake-dam","license":"No open reuse license verified; original copyright retained","licenseUrl":"https://www.keller-na.com/projects/clearwater-lake-dam","width":900,"height":561,"imageDate":null,"preserveWholeImage":true,"imageDownloadAllowed":false,"rightsStatus":"editorial-reference","permissionStatus":"No open reuse permission verified","rightsNote":"Source-linked editorial reference; copyright remains with the original owner. The site does not offer this image as a reusable download.","imageUsage":"project-photograph"},"figureCaption":"Aerial view of Clearwater Lake Dam in Missouri during the rehabilitation works, from Keller’s project account. The photograph shows construction along the dam crest.","qualityNotes":[],"checked":"2026-11-22","addedIn":"r13","curatedOrder":66,"referenceValues":[],"teachingFigureCaption":"Conceptual study schematic; not an as-built project drawing.","imageEvidence":{"status":"acquired","identityVerified":true,"evidenceFile":"image-provenance/clearwater-dam-r13-source.json","evidenceSha256":"c4e83124dafe5ca3ef277b3db6f7ac973e45d1e9d7dd7b6067175829993234e6","visualReview":"Inspected the full uncropped photograph and its 900 pixel derivative. It shows a reservoir, the Missouri dam embankment, and construction equipment on the crest. No embedded credit or other edge content was removed.","checked":"2026-11-22"},"localReportCount":0,"downloadBytes":4044,"sourceCount":2,"url":"/cases/clearwater-dam"},{"id":"bluestone-dam","title":"Bluestone Dam — rock anchors and spillway-foundation protection","summary":"The safety programme combines anchoring, drainage and armor over the bedrock stilling basin. Construction must be staged while the spillway remains an active river-release route.","topics":["dams-levees","rock","scour-erosion","dewatering","delivery"],"country":"United States","region":"Hinton, West Virginia","owner":"US Army Corps of Engineers","year":2026,"yearLabel":"Case reference year","projectType":"Design, construction and performance","methods":["Rock anchors","Uplift drainage","Stilling-basin armor","Cofferdams"],"documentationLevel":"technical-case","design":{"availability":"partial","summary":"USACE describes completed earlier phases and the ongoing stilling-basin work. The project is not labeled fully complete; the owner’s 2026 programme forecasts completion in 2030.","sourceIds":["s1","s2"]},"cost":{"availability":"partial","summary":"The 2020 notice identifies a $319.6 million Phase 5 contract. It is not a final cost for all phases.","sourceIds":["s1","s2"]},"schedule":{"availability":"partial","summary":"The 2026 owner update reports one half complete and forecasts overall completion in 2030; this supersedes the older 2020 contract forecast.","sourceIds":["s1","s2"]},"records":{"availability":"not-found","summary":"Complete as-built drawings and acceptance records were not found in the reviewed sources.","sourceIds":[]},"capstone":{"label":"Suggested capstone study","scope":"An original teaching brief based on the documented project. Study assumptions and student designs are separate from the built project.","brief":"Stage foundation anchoring and armor placement in half of an operating stilling basin.","inputs":["Extract the owner’s phase boundaries, diversion concept and uplift-control components.","Define a study flood window and rock discontinuity model for temporary and permanent checks."],"deliverables":["Check anchor demand and drain effectiveness for intact and blocked-drain scenarios.","Prepare a cofferdam sequence and flood-response plan with excavation hold points.","A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.","A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points."],"questions":["How does temporary river diversion alter uplift beneath the work area?","Which inspection or proof-test result should delay concreting over an anchor zone?"],"output":"Design report, calculation workbook, concept drawings, quantity schedule and construction programme."},"sources":[{"id":"s1","title":"Safety assurance project and 2026 progress","url":"https://www.lrd.usace.army.mil/Missions/Projects/Article/3631104/bluestone-dam-dam-safety-assurance-mega-project/","publisher":"USACE Great Lakes and Ohio River Division","year":null,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s2","title":"Phase 5 contract milestone","url":"https://www.usace.army.mil/Media/News/Article/2126116/bluestone-pdt-achieves-milestone/","publisher":"USACE","year":null,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s3","title":"Bluestone Dam 2022a.jpg — image and reuse license","url":"https://commons.wikimedia.org/wiki/File:Bluestone_Dam_2022a.jpg","publisher":"Wikimedia Commons / Antony-22","year":2022,"access":"public-link","license":"CC BY-SA 4.0","notes":"Project image source. Unmodified publisher-generated display-size file; the original source URL and publisher metadata are retained. No AI-generated replacement or content alteration.","checked":"2026-11-22","localAssetIds":["project-image"]}],"assets":[{"id":"schematic","title":"Conceptual study schematic","kind":"figure","fileName":"bluestone-dam.svg","mimeType":"image/svg+xml","bytes":985,"sha256":"ee95ff57b022b53ff13f55beb263a60b849d824c45c609ed976e0810f3961f8b","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/bluestone-dam/download/schematic"},{"id":"project-image","title":"Bluestone Dam 2022a.jpg","kind":"project-image","fileName":"bluestone-dam.jpg","mimeType":"image/jpeg","bytes":346957,"sha256":"1956f06dd42d585fa5868ce36388d01e769be3f4e1558d874872a4fa7143082e","sourceId":"s3","license":"CC BY-SA 4.0","width":1280,"height":853,"credit":"Antony-22","sourceUrl":"https://commons.wikimedia.org/wiki/File:Bluestone_Dam_2022a.jpg","licenseUrl":"https://creativecommons.org/licenses/by-sa/4.0","imageDate":"2022-04-02 13:13:58","evidenceFile":"image-provenance/bluestone-dam-commons.json","evidenceSha256":"55a381e13ba93c79b945faaf64fc9910ada6981407ff3b529abc3e1d4a12faa5","transformations":"Unmodified publisher-generated display-size file; the original source URL and publisher metadata are retained. No AI-generated replacement or content alteration.","originalUrl":"https://upload.wikimedia.org/wikipedia/commons/9/90/Bluestone_Dam_2022a.jpg","downloadUrl":"/cases/bluestone-dam/download/project-image","originalSha1":"7a54bc8e6d12bb134ada88de7744b4def9c86426","imageDownloadAllowed":true,"rightsBasis":"See the per-image provenance record and linked license; source hosting alone is not the rights basis."},{"id":"capstone-brief","title":"Capstone brief (Markdown)","kind":"brief","fileName":"bluestone-dam-capstone.md","mimeType":"text/markdown","bytes":3056,"sha256":"db4860c066a5468d0b6af254a88a791ef3657652ddccc228ec5e7352a5e98892","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/bluestone-dam/download/capstone-brief"}],"figure":{"assetId":"project-image","kind":"photograph","alt":"Bluestone Dam in 2022, showing work in the spillway area.","caption":"Bluestone Dam in 2022, showing work in the spillway area. The photograph corresponds to the ongoing dam-safety programme.","credit":"Antony-22","sourceUrl":"https://commons.wikimedia.org/wiki/File:Bluestone_Dam_2022a.jpg","license":"CC BY-SA 4.0","licenseUrl":"https://creativecommons.org/licenses/by-sa/4.0","width":1280,"height":853,"imageDate":"2022-04-02 13:13:58","imageDownloadAllowed":true},"figureCaption":"Bluestone Dam in 2022, showing work in the spillway area. The photograph corresponds to the ongoing dam-safety programme.","qualityNotes":[],"checked":"2026-11-22","addedIn":"r13","curatedOrder":67,"referenceValues":[],"teachingFigureCaption":"Conceptual study schematic; not an as-built project drawing.","imageEvidence":{"status":"acquired","identityVerified":true,"evidenceFile":"image-provenance/bluestone-dam-commons.json","evidenceSha256":"55a381e13ba93c79b945faaf64fc9910ada6981407ff3b529abc3e1d4a12faa5","visualReview":"Viewed the complete publisher photograph in the final contact sheets or individually and compared it with the source identity, date, and caption. The caption distinguishes project context from the particular underground treatment or construction stage.","checked":"2026-11-22"},"localReportCount":0,"downloadBytes":350998,"sourceCount":3,"url":"/cases/bluestone-dam"},{"id":"mosul-dam","title":"Mosul Dam — maintenance grouting in soluble foundations","summary":"The dam overlies soluble limestone and gypsum. A rehabilitation programme strengthened maintenance grouting, equipment and instrumentation; continuing operation depends on sustained foundation management.","topics":["dams-levees","seepage","rock","monitoring","delivery"],"country":"Iraq","region":"Tigris River, northern Iraq","owner":"Iraq Ministry of Water Resources","year":2019,"yearLabel":"Case reference year","projectType":"Design, construction and performance","methods":["Maintenance grouting","Karst dissolution","Instrumented surveillance"],"documentationLevel":"technical-case","design":{"availability":"partial","summary":"USACE’s project history explains the grouting-gallery purpose and the 2016–2019 rehabilitation. It does not portray dissolution as permanently eliminated.","sourceIds":["s1"]},"cost":{"availability":"not-found","summary":"A project-specific estimate, bid schedule or final account was not found in the reviewed sources.","sourceIds":[]},"schedule":{"availability":"partial","summary":"The history documents the 2016–2019 task force; operation and maintenance remained the responsibility of Iraq’s Ministry of Water Resources.","sourceIds":["s1"]},"records":{"availability":"partial","summary":"The source records equipment, workforce and instrumentation improvements, with continued grouting required.","sourceIds":["s1"]},"capstone":{"label":"Suggested capstone study","scope":"An original teaching brief based on the documented project. Study assumptions and student designs are separate from the built project.","brief":"Develop an operations-linked grouting and surveillance plan for a dam on a dissolving foundation.","inputs":["Identify the soluble strata, access-gallery function and monitoring system described by the project team.","Define study groundwater chemistry and hydraulic gradients, marking them as assumptions where unpublished."],"deliverables":["Compare targeted and blanket grouting using permeability and grout-take scenarios.","Create inspection, drilling, instrumentation and response schedules that remain workable during outages.","A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.","A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points."],"questions":["Why is completion of a rehabilitation contract different from ending maintenance grouting?","How can changing grout take indicate either successful closure or a new flow path?"],"output":"Design report, calculation workbook, concept drawings, quantity schedule and construction programme."},"sources":[{"id":"s1","title":"Mosul Dam Task Force project history","url":"https://www.tad.usace.army.mil/About/History/","publisher":"USACE Transatlantic Division","year":null,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s2","title":"Mosul Dam seepage.jpg — image and reuse license","url":"https://commons.wikimedia.org/wiki/File:Mosul_Dam_seepage.jpg","publisher":"Wikimedia Commons / This image or file is a work of a U.S. Army Corps of Engineers soldier or employee, taken or made as part of that person's official duties. As a work of the U.S. federal government , the image is in the public domain .","year":2007,"access":"public-link","license":"Public domain","notes":"Project image source. Unmodified publisher-generated display-size file; the original source URL and publisher metadata are retained. No AI-generated replacement or content alteration.","checked":"2026-11-22","localAssetIds":["project-image"]}],"assets":[{"id":"schematic","title":"Conceptual study schematic","kind":"figure","fileName":"mosul-dam.svg","mimeType":"image/svg+xml","bytes":985,"sha256":"ee95ff57b022b53ff13f55beb263a60b849d824c45c609ed976e0810f3961f8b","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/mosul-dam/download/schematic"},{"id":"project-image","title":"Mosul Dam seepage.jpg","kind":"project-image","fileName":"mosul-dam.jpg","mimeType":"image/jpeg","bytes":36400,"sha256":"5ed3cd442242ea44ce7714f6406861853e493e1e3c9f7ff7bfd283766ce3331c","sourceId":"s2","license":"Public domain","width":652,"height":390,"credit":"This image or file is a work of a U.S. Army Corps of Engineers soldier or employee, taken or made as part of that person's official duties. As a work of the U.S. federal government , the image is in the public domain .","sourceUrl":"https://commons.wikimedia.org/wiki/File:Mosul_Dam_seepage.jpg","licenseUrl":"https://commons.wikimedia.org/wiki/File:Mosul_Dam_seepage.jpg#Licensing","imageDate":"2007","evidenceFile":"image-provenance/mosul-dam-commons.json","evidenceSha256":"24cc7f7e6d87e0313bf07045244006791851a33a996e3b1856e722d1eb96c160","transformations":"Unmodified publisher-generated display-size file; the original source URL and publisher metadata are retained. No AI-generated replacement or content alteration.","originalUrl":"https://upload.wikimedia.org/wikipedia/commons/e/ef/Mosul_Dam_seepage.jpg","downloadUrl":"/cases/mosul-dam/download/project-image","originalSha1":"aa0bd6259fd94c99184966d5b6f57b00092cb239","originalSha256":"5ed3cd442242ea44ce7714f6406861853e493e1e3c9f7ff7bfd283766ce3331c","imageDownloadAllowed":true,"rightsBasis":"See the per-image provenance record and linked license; source hosting alone is not the rights basis."},{"id":"capstone-brief","title":"Capstone brief (Markdown)","kind":"brief","fileName":"mosul-dam-capstone.md","mimeType":"text/markdown","bytes":3389,"sha256":"d6549148f14ee3077870d6d17abbffd5fefc264b92192bbca050323f1979172b","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/mosul-dam/download/capstone-brief"}],"figure":{"assetId":"project-image","kind":"photograph","alt":"Seepage east of and below the Mosul Dam spillway.","caption":"Seepage east of and below the Mosul Dam spillway. The source photograph documents the actual dam setting relevant to the foundation-management case.","credit":"This image or file is a work of a U.S. Army Corps of Engineers soldier or employee, taken or made as part of that person's official duties. As a work of the U.S. federal government , the image is in the public domain .","sourceUrl":"https://commons.wikimedia.org/wiki/File:Mosul_Dam_seepage.jpg","license":"Public domain","licenseUrl":"https://commons.wikimedia.org/wiki/File:Mosul_Dam_seepage.jpg#Licensing","width":652,"height":390,"imageDate":"2007","imageDownloadAllowed":true},"figureCaption":"Seepage east of and below the Mosul Dam spillway. The source photograph documents the actual dam setting relevant to the foundation-management case.","qualityNotes":[],"checked":"2026-11-22","addedIn":"r13","curatedOrder":68,"referenceValues":[],"teachingFigureCaption":"Conceptual study schematic; not an as-built project drawing.","imageEvidence":{"status":"acquired","identityVerified":true,"evidenceFile":"image-provenance/mosul-dam-commons.json","evidenceSha256":"24cc7f7e6d87e0313bf07045244006791851a33a996e3b1856e722d1eb96c160","visualReview":"Viewed the complete publisher photograph in the final contact sheets or individually and compared it with the source identity, date, and caption. The caption distinguishes project context from the particular underground treatment or construction stage.","checked":"2026-11-22"},"localReportCount":0,"downloadBytes":40774,"sourceCount":2,"url":"/cases/mosul-dam"},{"id":"hoover-dam","title":"Hoover Dam — rock-foundation preparation and remedial grouting","summary":"Construction removed river deposits to competent rock and treated the foundation and abutments. Later drainage and remedial grouting addressed uplift and leakage observed during initial reservoir filling.","topics":["rock","dams-levees","seepage","excavation","delivery"],"country":"United States","region":"Colorado River, Nevada–Arizona","owner":"US Bureau of Reclamation","year":1947,"yearLabel":"Case reference year","projectType":"Design, construction and performance","methods":["Rock excavation","Grout curtain","Drainage galleries","Uplift"],"documentationLevel":"technical-report","design":{"availability":"partial","summary":"Reclamation’s construction history and foundation-grouting standard explain original preparation and the later remedial programme. Concrete contraction-joint grouting must not be confused with rock-foundation grouting.","sourceIds":["s1","s2"]},"cost":{"availability":"not-found","summary":"A project-specific estimate, bid schedule or final account was not found in the reviewed sources.","sourceIds":[]},"schedule":{"availability":"not-found","summary":"A dated project programme was not found in the reviewed sources; develop a study schedule from the documented method.","sourceIds":[]},"records":{"availability":"partial","summary":"The design standard records effectiveness of remedial work and later observations; it is not a present-day dam-safety evaluation.","sourceIds":["s1","s2"]},"capstone":{"label":"Suggested capstone study","scope":"An original teaching brief based on the documented project. Study assumptions and student designs are separate from the built project.","brief":"Reassess foundation seepage after reservoir filling reveals pressures above the original design expectation.","inputs":["Separate original grout holes, later remedial work and concrete-joint treatment in the source record.","Extract the reported rationale for changed grout mixes and additional drainage."],"deliverables":["Calculate uplift distributions for alternative drain and curtain effectiveness assumptions.","Design a trial grouting plan with staged pressure limits and monitoring of adjacent drainage.","A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.","A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points."],"questions":["Why might a deeper curtain and additional drains be complementary rather than competing remedies?","What observations would show that apparent grout refusal is caused by premature setting?"],"output":"Design report, calculation workbook, concept drawings, quantity schedule and construction programme."},"sources":[{"id":"s1","title":"Hoover Dam construction history","url":"https://www.usbr.gov/history/hoover.html","publisher":"US Bureau of Reclamation","year":null,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s2","title":"Foundation grouting design standard, Hoover case","url":"https://www.usbr.gov/tsc/techreferences/designstandards-datacollectionguides/finalds-pdfs/DS13-15.pdf","publisher":"US Bureau of Reclamation","year":null,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s3","title":"Hoover Dam, Nevada (Arizona-Nevada, USA) -- 2012 -- 6099.jpg — image and reuse license","url":"https://commons.wikimedia.org/wiki/File:Hoover_Dam,_Nevada_(Arizona-Nevada,_USA)_--_2012_--_6099.jpg","publisher":"Wikimedia Commons / Dietmar Rabich","year":null,"access":"public-link","license":"CC BY-SA 4.0","notes":"Project image source. Unmodified publisher-generated display-size file; the original source URL and publisher metadata are retained. No AI-generated replacement or content alteration.","checked":"2026-11-22","localAssetIds":["project-image"]}],"assets":[{"id":"schematic","title":"Conceptual study schematic","kind":"figure","fileName":"hoover-dam.svg","mimeType":"image/svg+xml","bytes":1017,"sha256":"ab086e9b878d71ca75443d4083022bf013c864b1ad5c4bbfbedf783b1ffc7360","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/hoover-dam/download/schematic"},{"id":"project-image","title":"Hoover Dam, Nevada (Arizona-Nevada, USA) -- 2012 -- 6099.jpg","kind":"project-image","fileName":"hoover-dam.jpg","mimeType":"image/jpeg","bytes":465705,"sha256":"85015660314ac149a4557cb3f98fe7fb03d50be0ec1b734ca92b8a807c6b734e","sourceId":"s3","license":"CC BY-SA 4.0","width":1280,"height":853,"credit":"Dietmar Rabich","sourceUrl":"https://commons.wikimedia.org/wiki/File:Hoover_Dam,_Nevada_(Arizona-Nevada,_USA)_--_2012_--_6099.jpg","licenseUrl":"https://creativecommons.org/licenses/by-sa/4.0","imageDate":"Taken on 26 July 2012, 13:37","evidenceFile":"image-provenance/hoover-dam-commons.json","evidenceSha256":"ec32fc3ca7a4a63c78fa79cebdf26ae9a3b975af6c12b7c48725cb839261eca2","transformations":"Unmodified publisher-generated display-size file; the original source URL and publisher metadata are retained. No AI-generated replacement or content alteration.","originalUrl":"https://upload.wikimedia.org/wikipedia/commons/f/f6/Hoover_Dam%2C_Nevada_%28Arizona-Nevada%2C_USA%29_--_2012_--_6099.jpg","downloadUrl":"/cases/hoover-dam/download/project-image","originalSha1":"4d420802cfaaf32abceb2ae2056cfe87dbc710f9","imageDownloadAllowed":true,"rightsBasis":"See the per-image provenance record and linked license; source hosting alone is not the rights basis."},{"id":"capstone-brief","title":"Capstone brief (Markdown)","kind":"brief","fileName":"hoover-dam-capstone.md","mimeType":"text/markdown","bytes":3357,"sha256":"9454c025e84aa35fa0a13d2587b628d4c439ff0309ef32c508d072347e950f19","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/hoover-dam/download/capstone-brief"}],"figure":{"assetId":"project-image","kind":"photograph","alt":"Hoover Dam and its canyon setting.","caption":"Hoover Dam and its canyon setting. The photograph identifies the completed project; original and remedial foundation grouting are described in Reclamation’s records.","credit":"Dietmar Rabich","sourceUrl":"https://commons.wikimedia.org/wiki/File:Hoover_Dam,_Nevada_(Arizona-Nevada,_USA)_--_2012_--_6099.jpg","license":"CC BY-SA 4.0","licenseUrl":"https://creativecommons.org/licenses/by-sa/4.0","width":1280,"height":853,"imageDate":"Taken on 26 July 2012, 13:37","imageDownloadAllowed":true},"figureCaption":"Hoover Dam and its canyon setting. The photograph identifies the completed project; original and remedial foundation grouting are described in Reclamation’s records.","qualityNotes":[],"checked":"2026-11-22","addedIn":"r13","curatedOrder":69,"referenceValues":[],"teachingFigureCaption":"Conceptual study schematic; not an as-built project drawing.","imageEvidence":{"status":"acquired","identityVerified":true,"evidenceFile":"image-provenance/hoover-dam-commons.json","evidenceSha256":"ec32fc3ca7a4a63c78fa79cebdf26ae9a3b975af6c12b7c48725cb839261eca2","visualReview":"Viewed the complete publisher photograph in the final contact sheets or individually and compared it with the source identity, date, and caption. The caption distinguishes project context from the particular underground treatment or construction stage.","checked":"2026-11-22"},"localReportCount":0,"downloadBytes":470079,"sourceCount":3,"url":"/cases/hoover-dam"},{"id":"glen-canyon-dam","title":"Glen Canyon Dam — sandstone abutments and controlled seepage","summary":"The high concrete dam required canyon-wall stabilization, river diversion and excavation to sandstone bedrock. Reclamation describes rock bolts, seepage measurement and the geological basis of the site selection.","topics":["rock","dams-levees","seepage","dewatering","site-investigation"],"country":"United States","region":"Page, Arizona","owner":"US Bureau of Reclamation","year":1966,"yearLabel":"Case reference year","projectType":"Design, construction and performance","methods":["Rock bolting","Abutment stability","Seepage measurement","River diversion"],"documentationLevel":"technical-case","design":{"availability":"partial","summary":"The owner history explains the construction systems; the USGS regional map supports geological context. Regional mapping does not replace discontinuity surveys at individual abutments.","sourceIds":["s1","s2"]},"cost":{"availability":"not-found","summary":"A project-specific estimate, bid schedule or final account was not found in the reviewed sources.","sourceIds":[]},"schedule":{"availability":"partial","summary":"Reclamation records major construction milestones and dedication in 1966; detailed daily excavation records are not included.","sourceIds":["s1","s2"]},"records":{"availability":"not-found","summary":"Complete as-built drawings and acceptance records were not found in the reviewed sources.","sourceIds":[]},"capstone":{"label":"Suggested capstone study","scope":"An original teaching brief based on the documented project. Study assumptions and student designs are separate from the built project.","brief":"Develop rock-abutment support and seepage-monitoring concepts for a dam in fractured sandstone.","inputs":["Use the regional map and owner account to distinguish formation-scale geology from local joints.","Identify the temporary diversion and excavation stages that precede concrete placement."],"deliverables":["Perform a study wedge-stability check with bolt and groundwater sensitivities.","Design a drainage and weir-monitoring layout that distinguishes changing seepage paths from reservoir-level effects.","A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.","A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points."],"questions":["Why is measurable seepage not by itself evidence of dam failure?","What site mapping is required before using a regional joint orientation in a support design?"],"output":"Design report, calculation workbook, concept drawings, quantity schedule and construction programme."},"sources":[{"id":"s1","title":"Glen Canyon construction, geology and monitoring","url":"https://www.usbr.gov/uc/rm/crsp/gc/","publisher":"US Bureau of Reclamation","year":null,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s2","title":"Geologic map of the Glen Canyon Dam quadrangle","url":"https://pubs.usgs.gov/publication/sim3268","publisher":"US Geological Survey","year":null,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s3","title":"Glen Canyon Dam 1962.jpg — image and reuse license","url":"https://commons.wikimedia.org/wiki/File:Glen_Canyon_Dam_1962.jpg","publisher":"Wikimedia Commons / U.S. Bureau of Reclamation","year":1962,"access":"public-link","license":"Public domain","notes":"Project image source. Unmodified publisher-generated display-size file; the original source URL and publisher metadata are retained. No AI-generated replacement or content alteration.","checked":"2026-11-22","localAssetIds":["project-image"]}],"assets":[{"id":"schematic","title":"Conceptual study schematic","kind":"figure","fileName":"glen-canyon-dam.svg","mimeType":"image/svg+xml","bytes":1017,"sha256":"ab086e9b878d71ca75443d4083022bf013c864b1ad5c4bbfbedf783b1ffc7360","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/glen-canyon-dam/download/schematic"},{"id":"project-image","title":"Glen Canyon Dam 1962.jpg","kind":"project-image","fileName":"glen-canyon-dam.jpg","mimeType":"image/jpeg","bytes":417488,"sha256":"9d600d85f07d11d5b66cab14776d263c4e47c5e81665b6b2d1137d1ced913cef","sourceId":"s3","license":"Public domain","width":439,"height":550,"credit":"U.S. Bureau of Reclamation","sourceUrl":"https://commons.wikimedia.org/wiki/File:Glen_Canyon_Dam_1962.jpg","licenseUrl":"https://commons.wikimedia.org/wiki/File:Glen_Canyon_Dam_1962.jpg#Licensing","imageDate":"1962","evidenceFile":"image-provenance/glen-canyon-dam-commons.json","evidenceSha256":"c1a950a228699d14eebae0da50d05260e7eae33821540a6ef62b5fba484d0bc4","transformations":"Unmodified publisher-generated display-size file; the original source URL and publisher metadata are retained. No AI-generated replacement or content alteration.","originalUrl":"https://upload.wikimedia.org/wikipedia/commons/a/ae/Glen_Canyon_Dam_1962.jpg","downloadUrl":"/cases/glen-canyon-dam/download/project-image","originalSha1":"b6a0eb9c6a8100448477e78cd35499d7c07e7d28","originalSha256":"9d600d85f07d11d5b66cab14776d263c4e47c5e81665b6b2d1137d1ced913cef","imageDownloadAllowed":true,"rightsBasis":"See the per-image provenance record and linked license; source hosting alone is not the rights basis."},{"id":"capstone-brief","title":"Capstone brief (Markdown)","kind":"brief","fileName":"glen-canyon-dam-capstone.md","mimeType":"text/markdown","bytes":3082,"sha256":"7812eb24234b655ed2da8b5f24604a3588ab0a135414f74e6e24bd7b9db2dd95","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/glen-canyon-dam/download/capstone-brief"}],"figure":{"assetId":"project-image","kind":"photograph","alt":"Glen Canyon Dam under construction in 1962.","caption":"Glen Canyon Dam under construction in 1962. The historical photograph shows the actual dam and sandstone canyon abutments.","credit":"U.S. Bureau of Reclamation","sourceUrl":"https://commons.wikimedia.org/wiki/File:Glen_Canyon_Dam_1962.jpg","license":"Public domain","licenseUrl":"https://commons.wikimedia.org/wiki/File:Glen_Canyon_Dam_1962.jpg#Licensing","width":439,"height":550,"imageDate":"1962","preserveWholeImage":true,"imageDownloadAllowed":true},"figureCaption":"Glen Canyon Dam under construction in 1962. The historical photograph shows the actual dam and sandstone canyon abutments.","qualityNotes":[],"checked":"2026-11-22","addedIn":"r13","curatedOrder":70,"referenceValues":[],"teachingFigureCaption":"Conceptual study schematic; not an as-built project drawing.","imageEvidence":{"status":"acquired","identityVerified":true,"evidenceFile":"image-provenance/glen-canyon-dam-commons.json","evidenceSha256":"c1a950a228699d14eebae0da50d05260e7eae33821540a6ef62b5fba484d0bc4","visualReview":"Viewed the complete publisher photograph in the final contact sheets or individually and compared it with the source identity, date, and caption. The caption distinguishes project context from the particular underground treatment or construction stage.","checked":"2026-11-22"},"localReportCount":0,"downloadBytes":421587,"sourceCount":3,"url":"/cases/glen-canyon-dam"},{"id":"bolivar-dam","title":"Bolivar Dam — seepage barriers in outwash and fractured abutment rock","summary":"Rehabilitation combined a partial-depth barrier, blanket improvements, relief wells and an abutment grout curtain. The project authors explain construction problems in thin limestone units with open flow paths.","topics":["dams-levees","seepage","rock","monitoring"],"country":"United States","region":"Tuscarawas County, Ohio","owner":"US Army Corps of Engineers","year":2017,"yearLabel":"Case reference year","projectType":"Design, construction and performance","methods":["Partial-depth cutoff","Relief wells","Abutment grouting","Piping control"],"documentationLevel":"technical-case","design":{"availability":"partial","summary":"The USACE completion account identifies the combined risk-reduction measures. A technical paper details the abutment grouting and downstage treatment decisions.","sourceIds":["s1","s2"]},"cost":{"availability":"not-found","summary":"A project-specific estimate, bid schedule or final account was not found in the reviewed sources.","sourceIds":[]},"schedule":{"availability":"partial","summary":"The owner reports rehabilitation completion in October 2017.","sourceIds":["s1","s2"]},"records":{"availability":"partial","summary":"The completion account describes post-implementation evaluation and the resulting dam-safety classification.","sourceIds":["s1","s2"]},"capstone":{"label":"Suggested capstone study","scope":"An original teaching brief based on the documented project. Study assumptions and student designs are separate from the built project.","brief":"Compare seepage-control combinations for an embankment on permeable outwash beside fractured rock.","inputs":["Separate foundation flow, rock-contact erosion and gate-system issues in the owner record.","Extract the grout-curtain arrangement and treatment response to circulation losses."],"deliverables":["Draw a seepage model with wall, blanket and relief-well alternatives.","Specify drilling/grouting decisions and post-treatment piezometric performance criteria.","A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.","A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points."],"questions":["How can a partial-depth barrier still reduce internal-erosion risk?","Where could seepage concentrate if the wall-to-rock transition is poorly treated?"],"output":"Design report, calculation workbook, concept drawings, quantity schedule and construction programme."},"sources":[{"id":"s1","title":"Completion and post-implementation review","url":"https://www.army.mil/article/200670/bolivar_receives_best_dam_safety_rating","publisher":"US Army / USACE","year":null,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s2","title":"Grout-curtain construction at Bolivar Dam","url":"https://pubs.geoscienceworld.org/aeg/eeg/article-abstract/24/1/121/522957/Grout-Curtain-Construction-At-Bolivar-Dam-Ohio","publisher":"USACE project authors / Environmental & Engineering Geoscience","year":null,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s3","title":"Bolivar Dam (Ohio) upstream.jpg — image and reuse license","url":"https://commons.wikimedia.org/wiki/File:Bolivar_Dam_(Ohio)_upstream.jpg","publisher":"Wikimedia Commons / Roseohioresident","year":null,"access":"public-link","license":"Public domain","notes":"Project image source. Unmodified publisher-generated display-size file; the original source URL and publisher metadata are retained. No AI-generated replacement or content alteration.","checked":"2026-11-22","localAssetIds":["project-image"]}],"assets":[{"id":"schematic","title":"Conceptual study schematic","kind":"figure","fileName":"bolivar-dam.svg","mimeType":"image/svg+xml","bytes":985,"sha256":"ee95ff57b022b53ff13f55beb263a60b849d824c45c609ed976e0810f3961f8b","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/bolivar-dam/download/schematic"},{"id":"project-image","title":"Bolivar Dam (Ohio) upstream.jpg","kind":"project-image","fileName":"bolivar-dam.jpg","mimeType":"image/jpeg","bytes":395437,"sha256":"d20de43c4b633adfc2bdb10b723118662052fad325fe034c3b54fee87c8cd5c5","sourceId":"s3","license":"Public domain","width":1280,"height":960,"credit":"Roseohioresident","sourceUrl":"https://commons.wikimedia.org/wiki/File:Bolivar_Dam_(Ohio)_upstream.jpg","licenseUrl":"https://commons.wikimedia.org/wiki/File:Bolivar_Dam_(Ohio)_upstream.jpg#Licensing","imageDate":"Taken on 18 August 2010","evidenceFile":"image-provenance/bolivar-dam-commons.json","evidenceSha256":"06d3cfbcd6025097e520fe62ad8bbd6609f2d0557a1751445d3a1c76c9f28fc3","transformations":"Unmodified publisher-generated display-size file; the original source URL and publisher metadata are retained. No AI-generated replacement or content alteration.","originalUrl":"https://upload.wikimedia.org/wikipedia/commons/6/6e/Bolivar_Dam_%28Ohio%29_upstream.jpg","downloadUrl":"/cases/bolivar-dam/download/project-image","originalSha1":"9be59df03889845bff4d1c545c9fce0bc1a6693e","imageDownloadAllowed":true,"rightsBasis":"See the per-image provenance record and linked license; source hosting alone is not the rights basis."},{"id":"capstone-brief","title":"Capstone brief (Markdown)","kind":"brief","fileName":"bolivar-dam-capstone.md","mimeType":"text/markdown","bytes":3151,"sha256":"15bf2f4194d6edcc19efb7438c2a05798f6806f3933f4462c59513b14abee9db","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/bolivar-dam/download/capstone-brief"}],"figure":{"assetId":"project-image","kind":"photograph","alt":"Upstream view of Bolivar Dam in Ohio.","caption":"Upstream view of Bolivar Dam in Ohio. The actual embankment is shown; the later seepage barrier and grout curtain are largely below ground.","credit":"Roseohioresident","sourceUrl":"https://commons.wikimedia.org/wiki/File:Bolivar_Dam_(Ohio)_upstream.jpg","license":"Public domain","licenseUrl":"https://commons.wikimedia.org/wiki/File:Bolivar_Dam_(Ohio)_upstream.jpg#Licensing","width":1280,"height":960,"imageDate":"Taken on 18 August 2010","imageDownloadAllowed":true},"figureCaption":"Upstream view of Bolivar Dam in Ohio. The actual embankment is shown; the later seepage barrier and grout curtain are largely below ground.","qualityNotes":[],"checked":"2026-11-22","addedIn":"r13","curatedOrder":71,"referenceValues":[],"teachingFigureCaption":"Conceptual study schematic; not an as-built project drawing.","imageEvidence":{"status":"acquired","identityVerified":true,"evidenceFile":"image-provenance/bolivar-dam-commons.json","evidenceSha256":"06d3cfbcd6025097e520fe62ad8bbd6609f2d0557a1751445d3a1c76c9f28fc3","visualReview":"Viewed the complete publisher photograph in the final contact sheets or individually and compared it with the source identity, date, and caption. The caption distinguishes project context from the particular underground treatment or construction stage.","checked":"2026-11-22"},"localReportCount":0,"downloadBytes":399573,"sourceCount":3,"url":"/cases/bolivar-dam"},{"id":"vajont-landslide","title":"Vajont reservoir — rockslide, groundwater and observational decisions","summary":"The reservoir disaster involved a large pre-existing rockslide and rapid displacement of reservoir water. Geological researchers emphasize the complex shear zone and the influence of groundwater and reservoir operations.","topics":["slopes","rock","dams-levees","seepage","monitoring"],"country":"Italy","region":"Vajont Valley","owner":"Historic reservoir project / Italian public investigation","year":1963,"yearLabel":"Case reference year","projectType":"Failure investigation and lessons","methods":["Rockslide back-analysis","Reservoir drawdown","Shear-zone strength"],"documentationLevel":"forensic-study","design":{"availability":"partial","summary":"This is a forensic case, not a completed slope-remediation design. Competing geological interpretations remain relevant when selecting assumptions for back-analysis.","sourceIds":["s1","s2"]},"cost":{"availability":"not-found","summary":"A project-specific estimate, bid schedule or final account was not found in the reviewed sources.","sourceIds":[]},"schedule":{"availability":"not-found","summary":"A dated project programme was not found in the reviewed sources; develop a study schedule from the documented method.","sourceIds":[]},"records":{"availability":"not-found","summary":"Complete as-built drawings and acceptance records were not found in the reviewed sources.","sourceIds":[]},"capstone":{"label":"Suggested capstone study","scope":"An original teaching brief based on the documented project. Study assumptions and student designs are separate from the built project.","brief":"Reconstruct how alternative geological models change slope-stability decisions during reservoir filling.","inputs":["Compare published interpretations of the old slide mass and basal shear zone.","Compile a source-based sequence of reservoir levels, observations and movement."],"deliverables":["Perform coupled seepage/stability sensitivity studies for the competing models.","Write an observational decision plan with limits on reservoir operations and explicitly conservative triggers.","A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.","A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points."],"questions":["Why can a good fit to one displacement episode fail to validate a unique failure mechanism?","What monitoring evidence would justify stopping filling before a deterministic factor of safety reaches one?"],"output":"Design report, calculation workbook, concept drawings, quantity schedule and construction programme."},"sources":[{"id":"s1","title":"Vajont geological heritage and research context","url":"https://iugs-geoheritage.org/geoheritage_sites/vajont-landslide/","publisher":"International Union of Geological Sciences / case scientists","year":null,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s2","title":"Updated geological model of the prehistoric rockslide","url":"https://www.sciencedirect.com/science/article/pii/S0169555X12002048","publisher":"Paronuzzi and Bolla / Geomorphology","year":null,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s3","title":"Vajont Dam landslide.jpg — image and reuse license","url":"https://commons.wikimedia.org/wiki/File:Vajont_Dam_landslide.jpg","publisher":"Wikimedia Commons / US Army","year":1963,"access":"public-link","license":"Public domain","notes":"Project image source. Unmodified publisher-generated display-size file; the original source URL and publisher metadata are retained. No AI-generated replacement or content alteration.","checked":"2026-11-22","localAssetIds":["project-image"]}],"assets":[{"id":"schematic","title":"Conceptual study schematic","kind":"figure","fileName":"vajont-landslide.svg","mimeType":"image/svg+xml","bytes":1029,"sha256":"ccf2f027816a3de86d722599635826d3b3cadcf8867cf69fa1bf6fc1bdf2d3bf","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/vajont-landslide/download/schematic"},{"id":"project-image","title":"Vajont Dam landslide.jpg","kind":"project-image","fileName":"vajont-landslide.jpg","mimeType":"image/jpeg","bytes":115238,"sha256":"101bf55fce288261b9be5350624ada515293ee27254dc4ea441259aa489fcb16","sourceId":"s3","license":"Public domain","width":800,"height":550,"credit":"US Army","sourceUrl":"https://commons.wikimedia.org/wiki/File:Vajont_Dam_landslide.jpg","licenseUrl":"https://commons.wikimedia.org/wiki/File:Vajont_Dam_landslide.jpg#Licensing","imageDate":"1963","evidenceFile":"image-provenance/vajont-landslide-commons.json","evidenceSha256":"5c02ae2fe38b9b323a7f6211233de9232d9a3ef4bd2bf62b925e09b40fcb24d2","transformations":"Unmodified publisher-generated display-size file; the original source URL and publisher metadata are retained. No AI-generated replacement or content alteration.","originalUrl":"https://upload.wikimedia.org/wikipedia/commons/f/f4/Vajont_Dam_landslide.jpg","downloadUrl":"/cases/vajont-landslide/download/project-image","originalSha1":"fdceebd3956b8ae854e0327568b91a20d76834f8","originalSha256":"101bf55fce288261b9be5350624ada515293ee27254dc4ea441259aa489fcb16","imageDownloadAllowed":true,"rightsBasis":"See the per-image provenance record and linked license; source hosting alone is not the rights basis."},{"id":"capstone-brief","title":"Capstone brief (Markdown)","kind":"brief","fileName":"vajont-landslide-capstone.md","mimeType":"text/markdown","bytes":3153,"sha256":"def386340f1865b5b949a68cec0b779fa5789e9497ca974f589aa46aeb58ad98","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/vajont-landslide/download/capstone-brief"}],"figure":{"assetId":"project-image","kind":"photograph","alt":"The Vajont landslide in 1963.","caption":"The Vajont landslide in 1963. Historical US Army photograph showing the actual landslide and reservoir-dam setting.","credit":"US Army","sourceUrl":"https://commons.wikimedia.org/wiki/File:Vajont_Dam_landslide.jpg","license":"Public domain","licenseUrl":"https://commons.wikimedia.org/wiki/File:Vajont_Dam_landslide.jpg#Licensing","width":800,"height":550,"imageDate":"1963","preserveWholeImage":true,"imageDownloadAllowed":true},"figureCaption":"The Vajont landslide in 1963. Historical US Army photograph showing the actual landslide and reservoir-dam setting.","qualityNotes":[],"checked":"2026-11-22","addedIn":"r13","curatedOrder":87,"referenceValues":[],"teachingFigureCaption":"Conceptual study schematic; not an as-built project drawing.","imageEvidence":{"status":"acquired","identityVerified":true,"evidenceFile":"image-provenance/vajont-landslide-commons.json","evidenceSha256":"5c02ae2fe38b9b323a7f6211233de9232d9a3ef4bd2bf62b925e09b40fcb24d2","visualReview":"Viewed the complete publisher photograph in the final contact sheets or individually and compared it with the source identity, date, and caption. The caption distinguishes project context from the particular underground treatment or construction stage.","checked":"2026-11-22"},"localReportCount":0,"downloadBytes":119420,"sourceCount":3,"url":"/cases/vajont-landslide"},{"id":"malpasset-dam","title":"Malpasset Dam — abutment wedge failure and uplift","summary":"The arch dam failed after instability developed in its rock foundation. The French dam committee and government accident record describe the role of discontinuity geometry, uplift and stress-dependent drainage.","topics":["rock","dams-levees","seepage","site-investigation"],"country":"France","region":"Fréjus","owner":"Historic Malpasset water-supply project","year":1959,"yearLabel":"Case reference year","projectType":"Failure investigation and lessons","methods":["Rock-wedge stability","Uplift pressure","Stress-dependent permeability"],"documentationLevel":"forensic-study","design":{"availability":"partial","summary":"The English technical material supports a forensic rock-wedge study. It is not an as-built remediation proposal for the ruined dam.","sourceIds":["s1","s2"]},"cost":{"availability":"not-found","summary":"A project-specific estimate, bid schedule or final account was not found in the reviewed sources.","sourceIds":[]},"schedule":{"availability":"not-found","summary":"A dated project programme was not found in the reviewed sources; develop a study schedule from the documented method.","sourceIds":[]},"records":{"availability":"not-found","summary":"Complete as-built drawings and acceptance records were not found in the reviewed sources.","sourceIds":[]},"capstone":{"label":"Suggested capstone study","scope":"An original teaching brief based on the documented project. Study assumptions and student designs are separate from the built project.","brief":"Evaluate an arch-dam abutment where intersecting discontinuities create a potentially unstable rock wedge.","inputs":["Extract the reported fault, foliation and abutment-force relationships.","Separate known observations from later interpretations of permeability changes."],"deliverables":["Calculate wedge stability for several groundwater-pressure distributions.","Specify investigation and drainage verification that could discriminate between the competing assumptions.","A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.","A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points."],"questions":["How can increased compressive stress reduce drainage yet raise destabilizing uplift?","Why may strong intact rock still provide an inadequate dam abutment?"],"output":"Design report, calculation workbook, concept drawings, quantity schedule and construction programme."},"sources":[{"id":"s1","title":"Government accident review","url":"https://www.aria.developpement-durable.gouv.fr/fiche_detaillee/29490_en/?lang=en","publisher":"French Ministry environmental accident database","year":null,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s2","title":"Arch-dam guidance and Malpasset foundation case","url":"https://www.barrages-cfbr.eu/IMG/pdf/gtvoute_vienne2018.pdf","publisher":"French Committee on Dams and Reservoirs","year":null,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s3","title":"Barrage Malpasset 2007.jpg — image and reuse license","url":"https://commons.wikimedia.org/wiki/File:Barrage_Malpasset_2007.jpg","publisher":"Wikimedia Commons / Bonho1962","year":2007,"access":"public-link","license":"Public domain","notes":"Project image source. Unmodified publisher-generated display-size file; the original source URL and publisher metadata are retained. No AI-generated replacement or content alteration.","checked":"2026-11-22","localAssetIds":["project-image"]}],"assets":[{"id":"schematic","title":"Conceptual study schematic","kind":"figure","fileName":"malpasset-dam.svg","mimeType":"image/svg+xml","bytes":1017,"sha256":"ab086e9b878d71ca75443d4083022bf013c864b1ad5c4bbfbedf783b1ffc7360","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/malpasset-dam/download/schematic"},{"id":"project-image","title":"Barrage Malpasset 2007.jpg","kind":"project-image","fileName":"malpasset-dam.jpg","mimeType":"image/jpeg","bytes":168986,"sha256":"039a3c531fb72c3b49904ea6e1f9da2bea8acdddbc138a8643e5ba023bab74e5","sourceId":"s3","license":"Public domain","width":1280,"height":453,"credit":"Bonho1962","sourceUrl":"https://commons.wikimedia.org/wiki/File:Barrage_Malpasset_2007.jpg","licenseUrl":"https://commons.wikimedia.org/wiki/File:Barrage_Malpasset_2007.jpg#Licensing","imageDate":"2007-06-08","evidenceFile":"image-provenance/malpasset-dam-commons.json","evidenceSha256":"04369b2ef16501c643e1aea885269ffa0c83d1f6cd2aae2c207a48b564d30a04","transformations":"Unmodified publisher-generated display-size file; the original source URL and publisher metadata are retained. No AI-generated replacement or content alteration.","originalUrl":"https://upload.wikimedia.org/wikipedia/commons/6/64/Barrage_Malpasset_2007.jpg","downloadUrl":"/cases/malpasset-dam/download/project-image","originalSha1":"30bd87cf637b57e5f5502beeba47afb24b14f92f","imageDownloadAllowed":true,"rightsBasis":"See the per-image provenance record and linked license; source hosting alone is not the rights basis."},{"id":"capstone-brief","title":"Capstone brief (Markdown)","kind":"brief","fileName":"malpasset-dam-capstone.md","mimeType":"text/markdown","bytes":3016,"sha256":"ed57709c549dd09a23398800a53df70f4909ccb6252c938df716172917eaf451","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/malpasset-dam/download/capstone-brief"}],"figure":{"assetId":"project-image","kind":"photograph","alt":"Ruins of Malpasset Dam photographed in 2007.","caption":"Ruins of Malpasset Dam photographed in 2007. The remaining concrete and rock setting belong to the actual 1959 failure site.","credit":"Bonho1962","sourceUrl":"https://commons.wikimedia.org/wiki/File:Barrage_Malpasset_2007.jpg","license":"Public domain","licenseUrl":"https://commons.wikimedia.org/wiki/File:Barrage_Malpasset_2007.jpg#Licensing","width":1280,"height":453,"imageDate":"2007-06-08","imageDownloadAllowed":true},"figureCaption":"Ruins of Malpasset Dam photographed in 2007. The remaining concrete and rock setting belong to the actual 1959 failure site.","qualityNotes":[],"checked":"2026-11-22","addedIn":"r13","curatedOrder":88,"referenceValues":[],"teachingFigureCaption":"Conceptual study schematic; not an as-built project drawing.","imageEvidence":{"status":"acquired","identityVerified":true,"evidenceFile":"image-provenance/malpasset-dam-commons.json","evidenceSha256":"04369b2ef16501c643e1aea885269ffa0c83d1f6cd2aae2c207a48b564d30a04","visualReview":"Viewed the complete publisher photograph in the final contact sheets or individually and compared it with the source identity, date, and caption. The caption distinguishes project context from the particular underground treatment or construction stage.","checked":"2026-11-22"},"localReportCount":0,"downloadBytes":173019,"sourceCount":3,"url":"/cases/malpasset-dam"},{"id":"st-francis-dam","title":"St. Francis Dam — investigation evidence and foundation reassessment","summary":"The 1928 collapse prompted an official investigation and later reassessments of geology and foundation behavior. The records make a useful exercise in distinguishing contemporary findings from subsequent hypotheses.","topics":["rock","dams-levees","problem-soils","site-investigation"],"country":"United States","region":"San Francisquito Canyon, California","owner":"Historic Los Angeles water-supply project","year":1928,"yearLabel":"Case reference year","projectType":"Failure investigation and lessons","methods":["Forensic ground model","Foundation saturation","Abutment stability"],"documentationLevel":"forensic-study","design":{"availability":"partial","summary":"The commission report and later research represent different stages of interpretation. No single disputed mechanism is presented as conclusively established by this catalog.","sourceIds":["s1","s2","s3"]},"cost":{"availability":"not-found","summary":"A project-specific estimate, bid schedule or final account was not found in the reviewed sources.","sourceIds":[]},"schedule":{"availability":"not-found","summary":"A dated project programme was not found in the reviewed sources; develop a study schedule from the documented method.","sourceIds":[]},"records":{"availability":"not-found","summary":"Complete as-built drawings and acceptance records were not found in the reviewed sources.","sourceIds":[]},"capstone":{"label":"Suggested capstone study","scope":"An original teaching brief based on the documented project. Study assumptions and student designs are separate from the built project.","brief":"Compare competing foundation-failure explanations and propose the investigation that would best distinguish them.","inputs":["Extract evidence from the original commission report separately from later interpretations.","Map the contrasting abutment materials and identify changes associated with reservoir filling."],"deliverables":["Prepare sensitivity checks for sliding, uplift and material degradation.","Build an evidence matrix showing which observations support or contradict each mechanism.","A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.","A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points."],"questions":["Which conclusion depends most strongly on an assumed pre-failure groundwater condition?","How would modern investigation reduce uncertainty without claiming hindsight makes the outcome inevitable?"],"output":"Design report, calculation workbook, concept drawings, quantity schedule and construction programme."},"sources":[{"id":"s1","title":"Original commission report record","url":"https://damsafety.org/content/causes-leading-failure-saint-francis-dam","publisher":"California investigation commission / ASDSO archive","year":null,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s2","title":"Later foundation reassessment","url":"https://damsafety.org/content/reassessment-st-francis-dam-failure-0","publisher":"J. David Rogers and David McMahon / ASDSO","year":null,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s3","title":"USGS historical overview","url":"https://www.usgs.gov/media/images/st-francis-dam-disaster","publisher":"US Geological Survey","year":null,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s4","title":"Saint Francis Dam Site 2012.jpg — image and reuse license","url":"https://commons.wikimedia.org/wiki/File:Saint_Francis_Dam_Site_2012.jpg","publisher":"Wikimedia Commons / Chevy111","year":2012,"access":"public-link","license":"CC BY-SA 4.0","notes":"Project image source. Unmodified publisher-generated display-size file; the original source URL and publisher metadata are retained. No AI-generated replacement or content alteration.","checked":"2026-11-22","localAssetIds":["project-image"]}],"assets":[{"id":"schematic","title":"Conceptual study schematic","kind":"figure","fileName":"st-francis-dam.svg","mimeType":"image/svg+xml","bytes":1017,"sha256":"ab086e9b878d71ca75443d4083022bf013c864b1ad5c4bbfbedf783b1ffc7360","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/st-francis-dam/download/schematic"},{"id":"project-image","title":"Saint Francis Dam Site 2012.jpg","kind":"project-image","fileName":"st-francis-dam.jpg","mimeType":"image/jpeg","bytes":410499,"sha256":"615231c05357069092a774fa146cb08b7be245e4ef4479873474fa16986d23f3","sourceId":"s4","license":"CC BY-SA 4.0","width":1280,"height":960,"credit":"Chevy111","sourceUrl":"https://commons.wikimedia.org/wiki/File:Saint_Francis_Dam_Site_2012.jpg","licenseUrl":"https://creativecommons.org/licenses/by-sa/4.0","imageDate":"2012-08-05 09:47:38","evidenceFile":"image-provenance/st-francis-dam-commons.json","evidenceSha256":"53a2c42e8c9d7963c83e036424e0cf8fc84572d726d0e567074b0648702bb588","transformations":"Unmodified publisher-generated display-size file; the original source URL and publisher metadata are retained. No AI-generated replacement or content alteration.","originalUrl":"https://upload.wikimedia.org/wikipedia/commons/a/a3/Saint_Francis_Dam_Site_2012.jpg","downloadUrl":"/cases/st-francis-dam/download/project-image","originalSha1":"9f6c998731ed25f57bb2d83749f0b6043c7ec96b","imageDownloadAllowed":true,"rightsBasis":"See the per-image provenance record and linked license; source hosting alone is not the rights basis."},{"id":"capstone-brief","title":"Capstone brief (Markdown)","kind":"brief","fileName":"st-francis-dam-capstone.md","mimeType":"text/markdown","bytes":3301,"sha256":"5af44503b48f4b65d84af1c900f2f16e6943ff68d5b7e370826792c2a549f618","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/st-francis-dam/download/capstone-brief"}],"figure":{"assetId":"project-image","kind":"photograph","alt":"Concrete ruins at the St.","caption":"Concrete ruins at the St. Francis Dam site in San Francisquito Canyon, photographed in 2012. The image shows the actual historic failure site.","credit":"Chevy111","sourceUrl":"https://commons.wikimedia.org/wiki/File:Saint_Francis_Dam_Site_2012.jpg","license":"CC BY-SA 4.0","licenseUrl":"https://creativecommons.org/licenses/by-sa/4.0","width":1280,"height":960,"imageDate":"2012-08-05 09:47:38","imageDownloadAllowed":true},"figureCaption":"Concrete ruins at the St. Francis Dam site in San Francisquito Canyon, photographed in 2012. The image shows the actual historic failure site.","qualityNotes":[],"checked":"2026-11-22","addedIn":"r13","curatedOrder":89,"referenceValues":[],"teachingFigureCaption":"Conceptual study schematic; not an as-built project drawing.","imageEvidence":{"status":"acquired","identityVerified":true,"evidenceFile":"image-provenance/st-francis-dam-commons.json","evidenceSha256":"53a2c42e8c9d7963c83e036424e0cf8fc84572d726d0e567074b0648702bb588","visualReview":"Viewed the complete publisher photograph in the final contact sheets or individually and compared it with the source identity, date, and caption. The caption distinguishes project context from the particular underground treatment or construction stage.","checked":"2026-11-22"},"localReportCount":0,"downloadBytes":414817,"sourceCount":4,"url":"/cases/st-francis-dam"}]}