{"schemaVersion":1,"updated":"2026-11-22","total":13,"records":[{"id":"us14-nicollet","title":"US 14 near Nicollet — preload and vertical drains","summary":"A highway embankment over organic clay used vertical drains, surcharge and staged filling, with remote monitoring of pore pressure and settlement.","topics":["settlement","ground-improvement","problem-soils","monitoring","delivery"],"country":"United States","region":"Nicollet, Minnesota","owner":"Minnesota Department of Transportation","year":2016,"yearLabel":"Case reference year","projectType":"Design and construction","methods":["Prefabricated vertical drains","Staged surcharge","Observational consolidation"],"documentationLevel":"technical-case","design":{"availability":"partial","summary":"The project authors describe drain spacing, surcharge, staged lifts, waiting periods and primary/post-surcharge secondary settlement.","sourceIds":["s1"]},"cost":{"availability":"partial","summary":"The source lists estimated alternatives from $0.3 million for surcharge-only to $1.8 million for a land bridge; these are comparison estimates, not audited final costs.","sourceIds":["s1"]},"schedule":{"availability":"partial","summary":"The documented drain/surcharge design targeted a five-month waiting period after staged filling.","sourceIds":["s1"]},"records":{"availability":"partial","summary":"The submitted case describes automated settlement, piezometric and earth-pressure monitoring.","sourceIds":["s1"]},"capstone":{"label":"Suggested capstone study","scope":"An original teaching brief based on the documented project. Study assumptions and student designs are separate from the built project.","brief":"Design a preload programme that meets a highway opening deadline while controlling stability and residual settlement.","inputs":["Extract layer thicknesses, compression parameters and drain layout from the cited papers.","Use measured settlement and pore-pressure stages to define the observation period."],"deliverables":["Compare untreated waiting time with vertical/radial drainage and secondary compression.","Set stage-release criteria and a contingency for slow pore-pressure dissipation.","A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.","A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points."],"questions":["Which site data control the decision, and what additional investigation would reduce uncertainty?","How would the proposed solution change under the stated sensitivity cases, construction constraints and performance limits?"],"output":"Design report, calculation workbook, concept drawings, quantity schedule and construction programme."},"sources":[{"id":"s1","title":"PVD and fill preloading — US Highway 14","url":"https://www.geoinstitute.org/node/16159","publisher":"ASCE Geo-Institute / named case-history author","year":2024,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"Case submitted by the project manager and MnDOT foundations engineer; technical papers by Lamb/Chow/Bentler (2018, 2019).","checked":"2026-11-22","localAssetIds":["project-image"]}],"assets":[{"id":"schematic","title":"Conceptual study schematic","kind":"figure","fileName":"us14-nicollet.svg","mimeType":"image/svg+xml","bytes":1178,"sha256":"24343c950faef54c58254cb9ddd4a6ab08882609f915b834abe764d4b384f92c","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/us14-nicollet/download/schematic"},{"id":"reference-values","title":"Published reference values (CSV)","kind":"table","fileName":"us14-nicollet-reference-values.csv","mimeType":"text/csv","bytes":1496,"sha256":"007a382e255f2ad4f1b9b13dceb0a7669748d03a85a1b7e11acb980d9a7ba8f7","sourceId":null,"license":"Factual values transcribed with source attribution; original selection and descriptions by Foundation Design","downloadUrl":"/cases/us14-nicollet/download/reference-values"},{"id":"project-image","title":"US 14, Nicollet — prefabricated vertical drains","kind":"project-image","fileName":"us14-nicollet-r13.jpg","mimeType":"image/jpeg","bytes":256005,"sha256":"def13de472acda2ba590bff1ac10ad55ee8c048ab95c68ddc8dc39dce688635d","sourceId":"s1","license":"No open reuse license verified; original copyright retained","width":1920,"height":1080,"credit":"Project photograph published by ASCE Geo-Institute; case submitted by Liang Chern Chow and Rich Lamb","sourceUrl":"https://www.geoinstitute.org/node/16159","licenseUrl":"https://www.geoinstitute.org/node/16159","imageDate":null,"evidenceFile":"image-provenance/us14-nicollet-r13-source.json","evidenceSha256":"d1426baf3baf7a5516e7c258c631b742342f5d3434b36c023779179195338e5b","transformations":"Original published image file copied unchanged; no crop, added labels, or retouching.","originalUrl":"https://www.geoinstitute.org/sites/default/files/inline-images/casehistory1.jpg","originalSha256":"def13de472acda2ba590bff1ac10ad55ee8c048ab95c68ddc8dc39dce688635d","imageDownloadAllowed":false,"rightsStatus":"editorial-reference","permissionStatus":"No open reuse permission verified","rightsNote":"Source-linked editorial reference; copyright remains with the original owner. The site does not offer this image as a reusable download.","imageUsage":"project-photograph","rightsBasis":"See the per-image provenance record and linked license; source hosting alone is not the rights basis.","previewUrl":"/cases/us14-nicollet/figure"},{"id":"capstone-brief","title":"Capstone brief (Markdown)","kind":"brief","fileName":"us14-nicollet-capstone.md","mimeType":"text/markdown","bytes":4241,"sha256":"e99fc8e22bb8ef2a80b680d8678aed4180f17eb7ba1a1d4ae67d4f03094675f0","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/us14-nicollet/download/capstone-brief"}],"figure":{"assetId":"project-image","kind":"photograph","alt":"Vertical-drain construction on the US 14 embankment project near Nicollet, Minnesota.","caption":"Vertical-drain construction on the US 14 embankment project near Nicollet, Minnesota.","credit":"Project photograph published by ASCE Geo-Institute; case submitted by Liang Chern Chow and Rich Lamb","sourceUrl":"https://www.geoinstitute.org/node/16159","license":"No open reuse license verified; original copyright retained","licenseUrl":"https://www.geoinstitute.org/node/16159","width":1920,"height":1080,"imageDate":null,"imageDownloadAllowed":false,"rightsStatus":"editorial-reference","permissionStatus":"No open reuse permission verified","rightsNote":"Source-linked editorial reference; copyright remains with the original owner. The site does not offer this image as a reusable download.","imageUsage":"project-photograph"},"figureCaption":"Vertical-drain construction on the US 14 embankment project near Nicollet, Minnesota.","qualityNotes":[],"checked":"2026-11-22","curatedOrder":11,"referenceValues":[{"label":"Organic-soil thickness","value":34,"unit":"ft","scope":"Reported soft to very soft organic deposit above glacial till.","sourceId":"s1","locator":"Project Summary/Scope","basis":"Reported investigation interpretation."},{"label":"Typical drain spacing","value":6,"unit":"ft","scope":"Triangular drain pattern over 80% of the embankment length.","sourceId":"s1","locator":"Project Summary/Scope","basis":"Reported design geometry."},{"label":"Surcharge-only estimate","value":300000,"unit":"USD","scope":"Alternative with extended waiting period.","sourceId":"s1","locator":"Estimated Costs of Considered Options","basis":"As reported; no escalation or inflation adjustment."},{"label":"Drains and surcharge estimate","value":500000,"unit":"USD","scope":"Alternative including extended wait and geotechnical monitoring.","sourceId":"s1","locator":"Estimated Costs of Considered Options","basis":"As reported; no escalation or inflation adjustment."},{"label":"Geofoam estimate","value":800000,"unit":"USD","scope":"Lightweight-fill alternative.","sourceId":"s1","locator":"Estimated Costs of Considered Options","basis":"As reported; no escalation or inflation adjustment."},{"label":"Column-supported estimate","value":1200000,"unit":"USD","scope":"Column-supported embankment alternative.","sourceId":"s1","locator":"Estimated Costs of Considered Options","basis":"As reported; no escalation or inflation adjustment."},{"label":"Land-bridge estimate","value":1800000,"unit":"USD","scope":"Land-bridge alternative.","sourceId":"s1","locator":"Estimated Costs of Considered Options","basis":"As reported; no escalation or inflation adjustment."}],"teachingFigureCaption":"Conceptual study schematic; not an as-built project drawing.","imageEvidence":{"status":"acquired","identityVerified":true,"evidenceFile":"image-provenance/us14-nicollet-r13-source.json","evidenceSha256":"d1426baf3baf7a5516e7c258c631b742342f5d3434b36c023779179195338e5b","visualReview":"Viewed the complete original photograph and compared it with the identified project/source caption. No generated or unrelated replacement image.","checked":"2026-11-22"},"localReportCount":0,"downloadBytes":6915,"sourceCount":1,"url":"/cases/us14-nicollet"},{"id":"olyphant-distribution","title":"Olyphant distribution centre — variable mine-spoil improvement","summary":"A distribution-centre site on former strip-mine ground combined dynamic compaction with aggregate piers where wet, weak areas did not respond adequately.","topics":["ground-improvement","shallow-foundations","problem-soils","earthworks"],"country":"United States","region":"Olyphant, Pennsylvania","owner":"D&L Realty","year":2022,"yearLabel":"Case reference year","projectType":"Design and construction","methods":["Dynamic compaction","Aggregate piers","Performance verification"],"documentationLevel":"technical-case","design":{"availability":"partial","summary":"The project engineer’s case describes the change in treatment, post-improvement SPT checks and aggregate-pier modulus tests.","sourceIds":["s1"]},"cost":{"availability":"partial","summary":"The source reports about $950,000 for dynamic compaction only; earthwork and aggregate-pier costs are unavailable.","sourceIds":["s1"]},"schedule":{"availability":"partial","summary":"The documented project period is 2021–2022.","sourceIds":["s1"]},"records":{"availability":"partial","summary":"The case includes post-improvement SPT and pier-modulus verification.","sourceIds":["s1"]},"capstone":{"label":"Suggested capstone study","scope":"An original teaching brief based on the documented project. Study assumptions and student designs are separate from the built project.","brief":"Prepare a ground-improvement design with an explicit decision rule for changing treatment in saturated or poorly responding zones.","inputs":["Extract fill depths, initial/post-treatment tests and observed crater response.","Separate warehouse foundation requirements from yard pavement requirements."],"deliverables":["Develop treatment zoning and a field trial with measurable acceptance criteria.","Compare additional compaction, aggregate piers and excavation/replacement.","A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.","A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points."],"questions":["Which site data control the decision, and what additional investigation would reduce uncertainty?","How would the proposed solution change under the stated sensitivity cases, construction constraints and performance limits?"],"output":"Design report, calculation workbook, concept drawings, quantity schedule and construction programme."},"sources":[{"id":"s1","title":"Distribution Center Site, Olyphant, PA","url":"https://www.geoinstitute.org/node/16272","publisher":"ASCE Geo-Institute / named case-history author","year":2023,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"Case author Chris Woods; technical paper by Woods et al., 2023 DFI conference.","checked":"2026-11-22","localAssetIds":["project-image"]}],"assets":[{"id":"schematic","title":"Conceptual study schematic","kind":"figure","fileName":"olyphant-distribution.svg","mimeType":"image/svg+xml","bytes":1188,"sha256":"1920205333b391315a1a8dc51c3ceea9b1d38258e470b3cd92fd907a2a396e7a","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/olyphant-distribution/download/schematic"},{"id":"reference-values","title":"Published reference values (CSV)","kind":"table","fileName":"olyphant-distribution-reference-values.csv","mimeType":"text/csv","bytes":303,"sha256":"d8e12ade8ad0afe7e13e24904df73ef410ab81246c1bad7429660474dab67db5","sourceId":null,"license":"Factual values transcribed with source attribution; original selection and descriptions by Foundation Design","downloadUrl":"/cases/olyphant-distribution/download/reference-values"},{"id":"project-image","title":"Olyphant distribution centre — ground-improvement site","kind":"project-image","fileName":"olyphant-distribution-r13.jpg","mimeType":"image/jpeg","bytes":221097,"sha256":"3150a03207445e707145f91b89198c78b9e39ad4825baae9e4f25854c5b70ba9","sourceId":"s1","license":"No open reuse license verified; original copyright retained","width":1024,"height":683,"credit":"Densification, Inc.; published by ASCE Geo-Institute","sourceUrl":"https://www.geoinstitute.org/node/16272","licenseUrl":"https://www.geoinstitute.org/node/16272","imageDate":null,"evidenceFile":"image-provenance/olyphant-distribution-r13-source.json","evidenceSha256":"26c7c3c9e1ec0483ce092180cb01289e8ec92ded9ea4a33d4423e2547b5ec3d1","transformations":"Original published image file copied unchanged; no crop, added labels, or retouching.","originalUrl":"https://www.geoinstitute.org/sites/default/files/inline-images/olyphant_center.jpg","originalSha256":"3150a03207445e707145f91b89198c78b9e39ad4825baae9e4f25854c5b70ba9","imageDownloadAllowed":false,"rightsStatus":"editorial-reference","permissionStatus":"No open reuse permission verified","rightsNote":"Source-linked editorial reference; copyright remains with the original owner. The site does not offer this image as a reusable download.","imageUsage":"project-photograph","rightsBasis":"See the per-image provenance record and linked license; source hosting alone is not the rights basis.","previewUrl":"/cases/olyphant-distribution/figure"},{"id":"capstone-brief","title":"Capstone brief (Markdown)","kind":"brief","fileName":"olyphant-distribution-capstone.md","mimeType":"text/markdown","bytes":3085,"sha256":"045c75f6403a1a2cc930baac411103cf2ddb62188ab04145e021984c45afbc77","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/olyphant-distribution/download/capstone-brief"}],"figure":{"assetId":"project-image","kind":"photograph","alt":"The Olyphant, Pennsylvania distribution-centre site during its mine-spoil ground-improvement programme.","caption":"The Olyphant, Pennsylvania distribution-centre site during its mine-spoil ground-improvement programme.","credit":"Densification, Inc.; published by ASCE Geo-Institute","sourceUrl":"https://www.geoinstitute.org/node/16272","license":"No open reuse license verified; original copyright retained","licenseUrl":"https://www.geoinstitute.org/node/16272","width":1024,"height":683,"imageDate":null,"imageDownloadAllowed":false,"rightsStatus":"editorial-reference","permissionStatus":"No open reuse permission verified","rightsNote":"Source-linked editorial reference; copyright remains with the original owner. The site does not offer this image as a reusable download.","imageUsage":"project-photograph"},"figureCaption":"The Olyphant, Pennsylvania distribution-centre site during its mine-spoil ground-improvement programme.","qualityNotes":[],"checked":"2026-11-22","curatedOrder":13,"referenceValues":[{"label":"Dynamic-compaction package","value":950000,"unit":"USD","scope":"Approximate dynamic-compaction cost; earthworks and aggregate columns excluded.","sourceId":"s1","locator":"Cost Information","basis":"As reported; no escalation or inflation adjustment."}],"teachingFigureCaption":"Conceptual study schematic; not an as-built project drawing.","imageEvidence":{"status":"acquired","identityVerified":true,"evidenceFile":"image-provenance/olyphant-distribution-r13-source.json","evidenceSha256":"26c7c3c9e1ec0483ce092180cb01289e8ec92ded9ea4a33d4423e2547b5ec3d1","visualReview":"Viewed the complete original photograph and compared it with the identified project/source caption. No generated or unrelated replacement image.","checked":"2026-11-22"},"localReportCount":0,"downloadBytes":4576,"sourceCount":1,"url":"/cases/olyphant-distribution"},{"id":"inuvik-tuktoyaktuk","title":"Inuvik–Tuktoyaktuk Highway — embankment over permafrost","summary":"The highway used fill placement and separation geotextile to protect permafrost, with much construction undertaken in winter.","topics":["cold-regions","earthworks","problem-soils","monitoring"],"country":"Canada","region":"Northwest Territories","owner":"Government of the Northwest Territories","year":2017,"yearLabel":"Case reference year","projectType":"Design and construction","methods":["Permafrost preservation","Fill-only construction","Thermal monitoring"],"documentationLevel":"technical-report","design":{"availability":"partial","summary":"The owner describes the construction strategy; a Canadian geological report documents regional ground temperatures before and after construction.","sourceIds":["s1","s2"]},"cost":{"availability":"not-found","summary":"A project-specific estimate, bid schedule or final account was not found in the reviewed sources.","sourceIds":[]},"schedule":{"availability":"partial","summary":"The owner project page documents opening and winter construction strategy; use source milestones rather than an assumed year-round programme.","sourceIds":["s1","s2"]},"records":{"availability":"partial","summary":"The owner page and regional ground-temperature report support performance review.","sourceIds":["s1","s2"]},"capstone":{"label":"Suggested capstone study","scope":"An original teaching brief based on the documented project. Study assumptions and student designs are separate from the built project.","brief":"Develop an embankment concept for ice-rich permafrost and compare seasonal construction and thaw-settlement risk.","inputs":["Extract the owner’s construction constraints and select a monitored ground-temperature location.","Record how ground-ice and soil-property information differ along the alignment."],"deliverables":["Prepare a thermal/thaw-settlement screening model and sensitivity to warming and drainage.","Plan borrow, winter hauling, geotextile placement and long-term temperature monitoring.","A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.","A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points."],"questions":["Which site data control the decision, and what additional investigation would reduce uncertainty?","How would the proposed solution change under the stated sensitivity cases, construction constraints and performance limits?"],"output":"Design report, calculation workbook, concept drawings, quantity schedule and construction programme."},"sources":[{"id":"s1","title":"Inuvik Tuktoyaktuk Highway project","url":"https://www.inf.gov.nt.ca/en/ITH","publisher":"Government of the Northwest Territories","year":2017,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s2","title":"Permafrost ground-temperature synthesis 2013–2019, GSC OF 8656","url":"https://publications.gc.ca/collections/collection_2021/rncan-nrcan/m183-2/M183-2-8656-eng.pdf","publisher":"Geological Survey of Canada / NWT Geological Survey","year":2020,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s3","title":"ITH Caribou Hills.jpg — image and reuse license","url":"https://commons.wikimedia.org/wiki/File:ITH_Caribou_Hills.jpg","publisher":"Wikimedia Commons / Samuell","year":2021,"access":"public-link","license":"CC BY 4.0","notes":"Project image source. Unmodified image bytes from the publisher’s selected-size file; only responsive display sizing is applied by the website.","checked":"2026-11-22","localAssetIds":["project-image"]}],"assets":[{"id":"schematic","title":"Conceptual study schematic","kind":"figure","fileName":"inuvik-tuktoyaktuk.svg","mimeType":"image/svg+xml","bytes":968,"sha256":"90bd9d5f0e906d8c86b1dbf936087013600fc464568e53625a08db29592daa87","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/inuvik-tuktoyaktuk/download/schematic"},{"id":"project-image","title":"ITH Caribou Hills.jpg","kind":"project-image","fileName":"inuvik-tuktoyaktuk.jpg","mimeType":"image/jpeg","bytes":291929,"sha256":"55ee8cf3a180f741ff152d7c513710111400d26fa703c4819812f989a97ae89b","sourceId":"s3","license":"CC BY 4.0","width":1280,"height":853,"credit":"Samuell","sourceUrl":"https://commons.wikimedia.org/wiki/File:ITH_Caribou_Hills.jpg","licenseUrl":"https://creativecommons.org/licenses/by/4.0","imageDate":"2021-02-13 17:33:04","evidenceFile":"image-provenance/inuvik-tuktoyaktuk-commons.json","evidenceSha256":"4c6669c299ecf13f73a372be900e2dffe1f4f769b807e13b8c03bd847a5d6646","transformations":"Unmodified image bytes from the publisher’s selected-size file; only responsive display sizing is applied by the website.","originalUrl":"https://upload.wikimedia.org/wikipedia/commons/8/85/ITH_Caribou_Hills.jpg","downloadUrl":"/cases/inuvik-tuktoyaktuk/download/project-image","rightsBasis":"See the per-image provenance record and linked license; source hosting alone is not the rights basis."},{"id":"capstone-brief","title":"Capstone brief (Markdown)","kind":"brief","fileName":"inuvik-tuktoyaktuk-capstone.md","mimeType":"text/markdown","bytes":3026,"sha256":"30173d5e66902d254c9880b2330409a9eda5a055399b3e40289fe7f9edbe9560","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/inuvik-tuktoyaktuk/download/capstone-brief"}],"figure":{"assetId":"project-image","kind":"photograph","alt":"The Inuvik–Tuktoyaktuk Highway through the Caribou Hills north of Inuvik.","caption":"The Inuvik–Tuktoyaktuk Highway through the Caribou Hills north of Inuvik. Photograph of the actual permafrost-road project corridor.","credit":"Samuell","sourceUrl":"https://commons.wikimedia.org/wiki/File:ITH_Caribou_Hills.jpg","license":"CC BY 4.0","licenseUrl":"https://creativecommons.org/licenses/by/4.0","width":1280,"height":853,"imageDate":"2021-02-13 17:33:04"},"figureCaption":"The Inuvik–Tuktoyaktuk Highway through the Caribou Hills north of Inuvik. Photograph of the actual permafrost-road project corridor.","qualityNotes":[],"checked":"2026-11-22","curatedOrder":37,"referenceValues":[],"teachingFigureCaption":"Conceptual study schematic; not an as-built project drawing.","imageEvidence":{"status":"acquired","identityVerified":true,"evidenceFile":"image-provenance/inuvik-tuktoyaktuk-commons.json","evidenceSha256":"4c6669c299ecf13f73a372be900e2dffe1f4f769b807e13b8c03bd847a5d6646","visualReview":"Original image inspected at card scale and against its caption/source; no AI-created replacement.","checked":"2026-11-22"},"localReportCount":0,"downloadBytes":295923,"sourceCount":3,"url":"/cases/inuvik-tuktoyaktuk"},{"id":"ky499-swelling","title":"KY 499, Estill County — pavement swelling investigation","summary":"Field and laboratory work investigated heave of a relatively young pavement over compacted clay shale and distinguished wetting expansion from a suspected sulfate reaction.","topics":["problem-soils","laboratory-testing","earthworks","site-investigation"],"country":"United States","region":"Estill County, Kentucky","owner":"Kentucky Transportation Cabinet / University of Kentucky","year":2005,"yearLabel":"Case reference year","projectType":"Forensic investigation","methods":["Swell testing","Moisture effects","Subgrade diagnosis"],"documentationLevel":"investigation-report","design":{"availability":"partial","summary":"The report tests the cause of distress and discusses the lime-treated subgrade; it does not establish a generic stabilization prescription.","sourceIds":["s1"]},"cost":{"availability":"not-found","summary":"A project-specific estimate, bid schedule or final account was not found in the reviewed sources.","sourceIds":[]},"schedule":{"availability":"not-found","summary":"A dated project programme was not found in the reviewed sources; develop a study schedule from the documented method.","sourceIds":[]},"records":{"availability":"partial","summary":"The technical report contains field/laboratory findings; a later construction closeout record was not established.","sourceIds":["s1"]},"capstone":{"label":"Suggested capstone study","scope":"An original teaching brief based on the documented project. Study assumptions and student designs are separate from the built project.","brief":"Design a laboratory investigation that distinguishes alternative heave mechanisms before selecting pavement rehabilitation.","inputs":["Extract moisture, shale and swell-test results from the investigation.","Identify sampling depth, test stress and wetting conditions needed for a field-heave estimate."],"deliverables":["Develop a mechanism-based diagnosis and a layered heave sensitivity calculation.","Compare moisture control, removal/replacement and treatment using compatible test evidence.","A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.","A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points."],"questions":["Which site data control the decision, and what additional investigation would reduce uncertainty?","How would the proposed solution change under the stated sensitivity cases, construction constraints and performance limits?"],"output":"Design report, calculation workbook, concept drawings, quantity schedule and construction programme."},"sources":[{"id":"s1","title":"Swelling Pavement: KY 499 Estill County, KTC-05-01","url":"https://uknowledge.uky.edu/ktc_researchreports/150/","publisher":"Kentucky Transportation Center / project researchers","year":2005,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22","localAssetIds":["project-image"]}],"assets":[{"id":"schematic","title":"Conceptual study schematic","kind":"figure","fileName":"ky499-swelling.svg","mimeType":"image/svg+xml","bytes":1074,"sha256":"f31305ba349170d998041ee804cfc6952d08a61de199d40088aca881bad4100f","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/ky499-swelling/download/schematic"},{"id":"project-image","title":"KY 499, Estill County — observed pavement swelling","kind":"project-image","fileName":"ky499-swelling-r13.jpeg","mimeType":"image/jpeg","bytes":14332,"sha256":"25b496c7f022b670a9288eba0f888ca9ee8acc5a142642e0c4c54bdf2609db34","sourceId":"s1","license":"No open reuse license verified; original copyright retained","width":346,"height":216,"credit":"Tony L. Beckham and Tommy C. Hopkins; Kentucky Transportation Center, University of Kentucky (2005)","sourceUrl":"https://uknowledge.uky.edu/ktc_researchreports/150/","licenseUrl":"https://uknowledge.uky.edu/ktc_researchreports/150/","imageDate":null,"evidenceFile":"image-provenance/ky499-swelling-r13-source.json","evidenceSha256":"f2514f82e5836ee60da40128ec81fe228f8d1c8c55402ad9585d6a22c4b056d6","transformations":"Original embedded photograph extracted unchanged from the source PDF; no crop, added labels, or retouching.","originalUrl":"https://uknowledge.uky.edu/cgi/viewcontent.cgi?article=1153&context=ktc_researchreports","originalSha256":"80004554769d719cae1616026c44940197d11fac6c367330df6a0f0d63ac1474","imageDownloadAllowed":false,"rightsStatus":"editorial-reference","permissionStatus":"No open reuse permission verified","rightsNote":"Source-linked editorial reference; copyright remains with the original owner. The site does not offer this image as a reusable download.","imageUsage":"project-photograph","rightsBasis":"See the per-image provenance record and linked license; source hosting alone is not the rights basis.","previewUrl":"/cases/ky499-swelling/figure"},{"id":"capstone-brief","title":"Capstone brief (Markdown)","kind":"brief","fileName":"ky499-swelling-capstone.md","mimeType":"text/markdown","bytes":2872,"sha256":"581410bda52ce64a5f6f4e201c2afaaa755d7ed584e3d457ae6bef68a6c48c76","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/ky499-swelling/download/capstone-brief"}],"figure":{"assetId":"project-image","kind":"photograph","alt":"Observed pavement distortion on KY 499 in Estill County, Kentucky, documented in the swelling investigation report.","caption":"Observed pavement distortion on KY 499 in Estill County, Kentucky, documented in the swelling investigation report.","credit":"Tony L. Beckham and Tommy C. Hopkins; Kentucky Transportation Center, University of Kentucky (2005)","sourceUrl":"https://uknowledge.uky.edu/ktc_researchreports/150/","license":"No open reuse license verified; original copyright retained","licenseUrl":"https://uknowledge.uky.edu/ktc_researchreports/150/","width":346,"height":216,"imageDate":null,"preserveWholeImage":true,"imageDownloadAllowed":false,"rightsStatus":"editorial-reference","permissionStatus":"No open reuse permission verified","rightsNote":"Source-linked editorial reference; copyright remains with the original owner. The site does not offer this image as a reusable download.","imageUsage":"project-photograph"},"figureCaption":"Observed pavement distortion on KY 499 in Estill County, Kentucky, documented in the swelling investigation report.","qualityNotes":[],"checked":"2026-11-22","curatedOrder":39,"referenceValues":[],"teachingFigureCaption":"Conceptual study schematic; not an as-built project drawing.","imageEvidence":{"status":"acquired","identityVerified":true,"evidenceFile":"image-provenance/ky499-swelling-r13-source.json","evidenceSha256":"f2514f82e5836ee60da40128ec81fe228f8d1c8c55402ad9585d6a22c4b056d6","visualReview":"Viewed the complete original photograph and compared it with the identified project/source caption. No generated or unrelated replacement image.","checked":"2026-11-22"},"localReportCount":0,"downloadBytes":3946,"sourceCount":1,"url":"/cases/ky499-swelling"},{"id":"texas-sh6-sh21","title":"Texas SH 6 and SH 21 — expansive-subgrade distress","summary":"A TxDOT-funded project investigated swelling clay beneath distressed pavement sections and evaluated characterization and stabilization alternatives.","topics":["problem-soils","laboratory-testing","earthworks","site-investigation"],"country":"United States","region":"Texas","owner":"Texas Department of Transportation / Texas A&M","year":1996,"yearLabel":"Case reference year","projectType":"Forensic investigation","methods":["Expansive subgrade","Moisture/strength characterization","Treatment selection"],"documentationLevel":"technical-report","design":{"availability":"partial","summary":"The final research report covers site investigation, interpretation and treatment recommendations; the public catalog alone is not a rehabilitation plan set.","sourceIds":["s1"]},"cost":{"availability":"not-found","summary":"A project-specific estimate, bid schedule or final account was not found in the reviewed sources.","sourceIds":[]},"schedule":{"availability":"not-found","summary":"A dated project programme was not found in the reviewed sources; develop a study schedule from the documented method.","sourceIds":[]},"records":{"availability":"partial","summary":"A final research report is publicly indexed; complete construction records are not established.","sourceIds":["s1"]},"capstone":{"label":"Suggested capstone study","scope":"An original teaching brief based on the documented project. Study assumptions and student designs are separate from the built project.","brief":"Develop a subgrade investigation and rehabilitation alternatives study for a selected documented pavement section.","inputs":["Extract one site’s profile, moisture and laboratory data from the final report.","Keep the two highway sections distinct when comparing properties and distress."],"deliverables":["Prepare a parameter register, moisture/heave mechanism assessment and test matrix.","Compare a moisture barrier, soil replacement and a verified stabilizer treatment.","A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.","A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points."],"questions":["Which site data control the decision, and what additional investigation would reduce uncertainty?","How would the proposed solution change under the stated sensitivity cases, construction constraints and performance limits?"],"output":"Design report, calculation workbook, concept drawings, quantity schedule and construction programme."},"sources":[{"id":"s1","title":"Investigation of swelling clay soils in subgrades of SH 6 and SH 21","url":"https://rosap.ntl.bts.gov/view/dot/84762","publisher":"TxDOT / Texas A&M","year":1996,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22","localAssetIds":["project-image"]}],"assets":[{"id":"schematic","title":"Conceptual study schematic","kind":"figure","fileName":"texas-sh6-sh21.svg","mimeType":"image/svg+xml","bytes":1074,"sha256":"f31305ba349170d998041ee804cfc6952d08a61de199d40088aca881bad4100f","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/texas-sh6-sh21/download/schematic"},{"id":"project-image","title":"Texas SH 6 — pavement distress over swelling clay","kind":"project-image","fileName":"texas-sh6-sh21-r13.png","mimeType":"image/png","bytes":274228,"sha256":"0cd4b7b8af15bdf841f4bfb2310c699fd7a2209492d7e470b1dcec98ca4aa54d","sourceId":"s1","license":"No open reuse license verified; original copyright retained","width":701,"height":469,"credit":"Seong-wan Park, Robert L. Lytton and Joe W. Button; Texas Transportation Institute / Texas A&M (1996)","sourceUrl":"https://rosap.ntl.bts.gov/view/dot/84762","licenseUrl":"https://rosap.ntl.bts.gov/view/dot/84762","imageDate":"1996","evidenceFile":"image-provenance/texas-sh6-sh21-r13-source.json","evidenceSha256":"0ba8ade57932edc72eae1aae2584a6aa62831778b5d368a0d5118747d782e11c","transformations":"Rendered the original Figure 6 photograph region from the scanned report page. Surrounding page margins and caption excluded; no alteration, reconstruction, or retouching within the photograph.","originalUrl":"https://static.tti.tamu.edu/tti.tamu.edu/documents/2965-1F.pdf","originalSha256":"8ca2867a7d79f743350f9ac93847c2c1cd02eec21a912b3b924cf8f25996008d","imageDownloadAllowed":false,"rightsStatus":"editorial-reference","permissionStatus":"No open reuse permission verified","rightsNote":"Source-linked editorial reference; copyright remains with the original owner. The site does not offer this image as a reusable download.","imageUsage":"project-photograph","rightsBasis":"See the per-image provenance record and linked license; source hosting alone is not the rights basis.","previewUrl":"/cases/texas-sh6-sh21/figure"},{"id":"capstone-brief","title":"Capstone brief (Markdown)","kind":"brief","fileName":"texas-sh6-sh21-capstone.md","mimeType":"text/markdown","bytes":2803,"sha256":"6dc6b1867827ec8c1bb1abebd7ac50b29e8c78784634e9d27226dbdd57d3ef70","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/texas-sh6-sh21/download/capstone-brief"}],"figure":{"assetId":"project-image","kind":"photograph","alt":"The SH 6 study section in the original expansive-subgrade investigation, reproduced from the scanned Figure 6 photograph. The source scan has limited image quality.","caption":"The SH 6 study section in the original expansive-subgrade investigation, reproduced from the scanned Figure 6 photograph. The source scan has limited image quality.","credit":"Seong-wan Park, Robert L. Lytton and Joe W. Button; Texas Transportation Institute / Texas A&M (1996)","sourceUrl":"https://rosap.ntl.bts.gov/view/dot/84762","license":"No open reuse license verified; original copyright retained","licenseUrl":"https://rosap.ntl.bts.gov/view/dot/84762","width":701,"height":469,"imageDate":"1996","preserveWholeImage":true,"imageDownloadAllowed":false,"rightsStatus":"editorial-reference","permissionStatus":"No open reuse permission verified","rightsNote":"Source-linked editorial reference; copyright remains with the original owner. The site does not offer this image as a reusable download.","imageUsage":"project-photograph"},"figureCaption":"The SH 6 study section in the original expansive-subgrade investigation, reproduced from the scanned Figure 6 photograph. The source scan has limited image quality.","qualityNotes":[],"checked":"2026-11-22","curatedOrder":40,"referenceValues":[],"teachingFigureCaption":"Conceptual study schematic; not an as-built project drawing.","imageEvidence":{"status":"acquired","identityVerified":true,"evidenceFile":"image-provenance/texas-sh6-sh21-r13-source.json","evidenceSha256":"0ba8ade57932edc72eae1aae2584a6aa62831778b5d368a0d5118747d782e11c","visualReview":"Viewed the complete original photograph and compared it with the identified project/source caption. No generated or unrelated replacement image.","checked":"2026-11-22"},"localReportCount":0,"downloadBytes":3877,"sourceCount":1,"url":"/cases/texas-sh6-sh21"},{"id":"kansai-airport","title":"Kansai International Airport — reclamation and long-term settlement","summary":"An offshore airport on deep marine deposits combines accelerated consolidation with ongoing settlement observation and adjustable building supports. The operator publishes measured island subsidence and its mitigation approach.","topics":["settlement","ground-improvement","problem-soils","monitoring","coastal-offshore"],"country":"Japan","region":"Osaka Bay","owner":"Kansai Airports","year":2025,"yearLabel":"Case reference year","projectType":"Design, construction and performance","methods":["Sand drains","Consolidation","Differential settlement","Jacking"],"documentationLevel":"technical-case","design":{"availability":"partial","summary":"The operator explains sand drains, reclaimed-fill compaction and jacking of individual columns. Published settlement histories allow comparison of shallow and deeper clay contributions.","sourceIds":["s1","s2"]},"cost":{"availability":"not-found","summary":"A project-specific estimate, bid schedule or final account was not found in the reviewed sources.","sourceIds":[]},"schedule":{"availability":"not-found","summary":"A dated project programme was not found in the reviewed sources; develop a study schedule from the documented method.","sourceIds":[]},"records":{"availability":"partial","summary":"The operator supplies monitoring updates and explains continuing adjustment; the airport is an operating asset, not a concluded settlement experiment.","sourceIds":["s1","s2"]},"capstone":{"label":"Suggested capstone study","scope":"An original teaching brief based on the documented project. Study assumptions and student designs are separate from the built project.","brief":"Develop a settlement-management plan for a reclaimed airport platform whose terminal and utility connections must remain serviceable.","inputs":["Separate pre-opening settlement from post-opening movement in the owner data.","Define a study clay profile and drainage lengths; clearly label parameters not provided by the owner."],"deliverables":["Fit a consolidation trend and test sensitivity to deep-clay compressibility.","Detail adjustable supports and flexible utility interfaces with a survey-and-maintenance programme.","A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.","A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points."],"questions":["Why does accelerating upper-layer consolidation not eliminate deeper-layer settlement?","Which measurements should trigger a building adjustment rather than a change in the ground model?"],"output":"Design report, calculation workbook, concept drawings, quantity schedule and construction programme."},"sources":[{"id":"s1","title":"Subsidence countermeasures and monitored status","url":"https://www.kansai-airports.co.jp/en/sustainability/society/tech-subsidence-countermeasures/","publisher":"Kansai Airports","year":null,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s2","title":"Uneven settlement and jacking-up","url":"https://www.kansai-airports.co.jp/en/sustainability/society/tech-jacking-up/","publisher":"Kansai Airports","year":null,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s3","title":"Kansai closeup.jpg — image and reuse license","url":"https://commons.wikimedia.org/wiki/File:Kansai_closeup.jpg","publisher":"Wikimedia Commons / NASA Earth Observatory","year":2003,"access":"public-link","license":"Public domain","notes":"Project image source. Unmodified publisher-generated display-size file; the original source URL and publisher metadata are retained. No AI-generated replacement or content alteration.","checked":"2026-11-22","localAssetIds":["project-image"]}],"assets":[{"id":"schematic","title":"Conceptual study schematic","kind":"figure","fileName":"kansai-airport.svg","mimeType":"image/svg+xml","bytes":1178,"sha256":"24343c950faef54c58254cb9ddd4a6ab08882609f915b834abe764d4b384f92c","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/kansai-airport/download/schematic"},{"id":"project-image","title":"Kansai closeup.jpg","kind":"project-image","fileName":"kansai-airport.jpg","mimeType":"image/jpeg","bytes":67326,"sha256":"820c6c19f570694e31a5f52cb274dc257136eb7470b63062a15935302651c7f1","sourceId":"s3","license":"Public domain","width":800,"height":600,"credit":"NASA Earth Observatory","sourceUrl":"https://commons.wikimedia.org/wiki/File:Kansai_closeup.jpg","licenseUrl":"https://commons.wikimedia.org/wiki/File:Kansai_closeup.jpg#Licensing","imageDate":"2003-09-19","evidenceFile":"image-provenance/kansai-airport-commons.json","evidenceSha256":"2496b2e3dbfa9199043b8545d26458c7bcdda034ed833e65f0801d1ca420d53a","transformations":"Unmodified publisher-generated display-size file; the original source URL and publisher metadata are retained. No AI-generated replacement or content alteration.","originalUrl":"https://upload.wikimedia.org/wikipedia/commons/f/fd/Kansai_closeup.jpg","downloadUrl":"/cases/kansai-airport/download/project-image","originalSha1":"55c3ecb6fd4c95b23d3591a32493baddcdb45f4f","originalSha256":"820c6c19f570694e31a5f52cb274dc257136eb7470b63062a15935302651c7f1","imageDownloadAllowed":true,"rightsBasis":"See the per-image provenance record and linked license; source hosting alone is not the rights basis."},{"id":"capstone-brief","title":"Capstone brief (Markdown)","kind":"brief","fileName":"kansai-airport-capstone.md","mimeType":"text/markdown","bytes":3282,"sha256":"ca2f810824f14286d8f604345aa661f6abeadb02f3c83425fedd0f5254b0087d","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/kansai-airport/download/capstone-brief"}],"figure":{"assetId":"project-image","kind":"photograph","alt":"Satellite view of Kansai International Airport and its reclaimed offshore island works.","caption":"Satellite view of Kansai International Airport and its reclaimed offshore island works. The image provides project context for the owner’s settlement and foundation-adjustment records.","credit":"NASA Earth Observatory","sourceUrl":"https://commons.wikimedia.org/wiki/File:Kansai_closeup.jpg","license":"Public domain","licenseUrl":"https://commons.wikimedia.org/wiki/File:Kansai_closeup.jpg#Licensing","width":800,"height":600,"imageDate":"2003-09-19","imageDownloadAllowed":true},"figureCaption":"Satellite view of Kansai International Airport and its reclaimed offshore island works. The image provides project context for the owner’s settlement and foundation-adjustment records.","qualityNotes":[],"checked":"2026-11-22","addedIn":"r13","curatedOrder":48,"referenceValues":[],"teachingFigureCaption":"Conceptual study schematic; not an as-built project drawing.","imageEvidence":{"status":"acquired","identityVerified":true,"evidenceFile":"image-provenance/kansai-airport-commons.json","evidenceSha256":"2496b2e3dbfa9199043b8545d26458c7bcdda034ed833e65f0801d1ca420d53a","visualReview":"Viewed the complete publisher photograph in the final contact sheets or individually and compared it with the source identity, date, and caption. The caption distinguishes project context from the particular underground treatment or construction stage.","checked":"2026-11-22"},"localReportCount":0,"downloadBytes":71786,"sourceCount":3,"url":"/cases/kansai-airport"},{"id":"port-brisbane","title":"Port of Brisbane — vacuum consolidation beside a marine park","summary":"A reclamation trial combined vacuum preloading and vertical drainage in soft dredged mud and underlying clay. A cutoff isolated permeable layers, while stability at the adjacent marine park constrained surcharge filling.","topics":["ground-improvement","settlement","seepage","problem-soils","coastal-offshore"],"country":"Australia","region":"Fisherman Islands, Queensland","owner":"Port of Brisbane","year":2009,"yearLabel":"Case reference year","projectType":"Design, construction and performance","methods":["Vacuum preloading","Vertical drains","Cutoff isolation","Lateral movement"],"documentationLevel":"technical-case","design":{"availability":"partial","summary":"The owner, contractor and consultant paper records the trial design objectives, instrumentation and interpreted performance. Its successful trial does not establish identical behavior in every reclamation cell.","sourceIds":["s1","s2"]},"cost":{"availability":"not-found","summary":"A project-specific estimate, bid schedule or final account was not found in the reviewed sources.","sourceIds":[]},"schedule":{"availability":"not-found","summary":"A dated project programme was not found in the reviewed sources; develop a study schedule from the documented method.","sourceIds":[]},"records":{"availability":"not-found","summary":"Complete as-built drawings and acceptance records were not found in the reviewed sources.","sourceIds":[]},"capstone":{"label":"Suggested capstone study","scope":"An original teaching brief based on the documented project. Study assumptions and student designs are separate from the built project.","brief":"Compare vacuum-assisted and fill-only preloading for an environmentally constrained soft-ground boundary.","inputs":["Extract the trial profile, drainage arrangement and cutoff function.","List the settlement, pore-pressure and lateral-displacement observations needed to separate mechanisms."],"deliverables":["Compare consolidation time and stability for vacuum-plus-fill versus higher surcharge.","Specify vacuum-loss response, cutoff continuity tests and a monitoring plan at the sensitive boundary.","A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.","A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points."],"questions":["How would an undetected sand connection reduce the effective vacuum in the clay?","Why must improved consolidation time be assessed alongside lateral movement?"],"output":"Design report, calculation workbook, concept drawings, quantity schedule and construction programme."},"sources":[{"id":"s1","title":"Successful application of vacuum consolidation","url":"https://rpsonline.com.sg/proceedings/9789810831240/html/GI125.php","publisher":"Port of Brisbane, Menard and Coffey project authors","year":null,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s2","title":"Performance and prediction of vacuum combined surcharge consolidation","url":"https://ascelibrary.com/doi/10.1061/%28ASCE%29GT.1943-5606.0000519","publisher":"Indraratna and project coauthors / ASCE","year":null,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s3","title":"Port of Brisbane and Brisbane Airport June 2015.jpg — image and reuse license","url":"https://commons.wikimedia.org/wiki/File:Port_of_Brisbane_and_Brisbane_Airport_June_2015.jpg","publisher":"Wikimedia Commons / Nick-D","year":2015,"access":"public-link","license":"CC BY-SA 4.0","notes":"Project image source. Unmodified publisher-generated display-size file; the original source URL and publisher metadata are retained. No AI-generated replacement or content alteration.","checked":"2026-11-22","localAssetIds":["project-image"]}],"assets":[{"id":"schematic","title":"Conceptual study schematic","kind":"figure","fileName":"port-brisbane.svg","mimeType":"image/svg+xml","bytes":1188,"sha256":"1920205333b391315a1a8dc51c3ceea9b1d38258e470b3cd92fd907a2a396e7a","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/port-brisbane/download/schematic"},{"id":"project-image","title":"Port of Brisbane and Brisbane Airport June 2015.jpg","kind":"project-image","fileName":"port-brisbane.jpg","mimeType":"image/jpeg","bytes":144392,"sha256":"64dc5639a068a195aeddfa35450009393fb02813c20b5a6d70334cd8a822135f","sourceId":"s3","license":"CC BY-SA 4.0","width":1280,"height":959,"credit":"Nick-D","sourceUrl":"https://commons.wikimedia.org/wiki/File:Port_of_Brisbane_and_Brisbane_Airport_June_2015.jpg","licenseUrl":"https://creativecommons.org/licenses/by-sa/4.0","imageDate":"2015-06-30 11:56:37","evidenceFile":"image-provenance/port-brisbane-commons.json","evidenceSha256":"a5d5469a7028e7ab4d41f10074f724774726a497f48327df25bc2effa337a475","transformations":"Unmodified publisher-generated display-size file; the original source URL and publisher metadata are retained. No AI-generated replacement or content alteration.","originalUrl":"https://upload.wikimedia.org/wikipedia/commons/6/69/Port_of_Brisbane_and_Brisbane_Airport_June_2015.jpg","downloadUrl":"/cases/port-brisbane/download/project-image","originalSha1":"3412db9547a125dd74c90c8c2c9006240612c154","imageDownloadAllowed":true,"rightsBasis":"See the per-image provenance record and linked license; source hosting alone is not the rights basis."},{"id":"capstone-brief","title":"Capstone brief (Markdown)","kind":"brief","fileName":"port-brisbane-capstone.md","mimeType":"text/markdown","bytes":3302,"sha256":"fee1d5cbb729910937eee63cc5be6be0cefc54d4bf4492c6c67611e85d30f71b","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/port-brisbane/download/capstone-brief"}],"figure":{"assetId":"project-image","kind":"photograph","alt":"Aerial view of the Port of Brisbane and adjoining airport in 2015.","caption":"Aerial view of the Port of Brisbane and adjoining airport in 2015. This is the port setting; the precise vacuum-consolidation trial cell is defined in the cited project papers.","credit":"Nick-D","sourceUrl":"https://commons.wikimedia.org/wiki/File:Port_of_Brisbane_and_Brisbane_Airport_June_2015.jpg","license":"CC BY-SA 4.0","licenseUrl":"https://creativecommons.org/licenses/by-sa/4.0","width":1280,"height":959,"imageDate":"2015-06-30 11:56:37","imageDownloadAllowed":true},"figureCaption":"Aerial view of the Port of Brisbane and adjoining airport in 2015. This is the port setting; the precise vacuum-consolidation trial cell is defined in the cited project papers.","qualityNotes":[],"checked":"2026-11-22","addedIn":"r13","curatedOrder":56,"referenceValues":[],"teachingFigureCaption":"Conceptual study schematic; not an as-built project drawing.","imageEvidence":{"status":"acquired","identityVerified":true,"evidenceFile":"image-provenance/port-brisbane-commons.json","evidenceSha256":"a5d5469a7028e7ab4d41f10074f724774726a497f48327df25bc2effa337a475","visualReview":"Viewed the complete publisher photograph in the final contact sheets or individually and compared it with the source identity, date, and caption. The caption distinguishes project context from the particular underground treatment or construction stage.","checked":"2026-11-22"},"localReportCount":0,"downloadBytes":148882,"sourceCount":3,"url":"/cases/port-brisbane"},{"id":"west-closure-complex","title":"West Closure Complex — foundations on soft deltaic deposits","summary":"The gate and pumping complex is founded in soft, compressible deltaic deposits. USACE authors describe exploration, laboratory characterization and pile testing used to develop design strength profiles.","topics":["deep-foundations","laboratory-testing","site-investigation","problem-soils","coastal-offshore"],"country":"United States","region":"New Orleans, Louisiana","owner":"US Army Corps of Engineers","year":2011,"yearLabel":"Case reference year","projectType":"Design, construction and performance","methods":["CPT interpretation","Strength profiling","Static and dynamic pile tests"],"documentationLevel":"technical-paper","design":{"availability":"partial","summary":"The technical publication explains the characterization programme and foundation-selection evidence. A complete final calculation set and acceptance database are not supplied by the abstract.","sourceIds":["s1","s2"]},"cost":{"availability":"not-found","summary":"A project-specific estimate, bid schedule or final account was not found in the reviewed sources.","sourceIds":[]},"schedule":{"availability":"not-found","summary":"A dated project programme was not found in the reviewed sources; develop a study schedule from the documented method.","sourceIds":[]},"records":{"availability":"not-found","summary":"Complete as-built drawings and acceptance records were not found in the reviewed sources.","sourceIds":[]},"capstone":{"label":"Suggested capstone study","scope":"An original teaching brief based on the documented project. Study assumptions and student designs are separate from the built project.","brief":"Design an investigation and test-pile programme for a critical coastal pumping structure on organic clay and silt.","inputs":["Identify the published depositional units and component-specific foundation requirements.","Specify the additional parameters needed for axial, lateral and settlement analyses."],"deliverables":["Develop characteristic strength profiles and compare test-pile interpretations.","Prepare component foundation alternatives with construction access and long-term subsidence allowances.","A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.","A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points."],"questions":["Which laboratory sampling problems are most consequential in soft organic deltaic soils?","How can a test-pile programme distinguish drivability constraints from long-term capacity?"],"output":"Design report, calculation workbook, concept drawings, quantity schedule and construction programme."},"sources":[{"id":"s1","title":"Geocharacterization for design and construction of West Closure Complex","url":"https://ascelibrary.org/doi/10.1061/9780784413272.039","publisher":"USACE project authors / ASCE","year":null,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s2","title":"Indexed technical-paper details","url":"https://trid.trb.org/View/1303129","publisher":"Transportation Research Board","year":null,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s3","title":"West Closure Complex testing, Louisiana 2023 - 01.jpg — image and reuse license","url":"https://commons.wikimedia.org/wiki/File:West_Closure_Complex_testing,_Louisiana_2023_-_01.jpg","publisher":"Wikimedia Commons / Team New Orleans, US Army Corps of Engineers","year":2023,"access":"public-link","license":"Public domain","notes":"Project image source. Unmodified publisher-generated display-size file; the original source URL and publisher metadata are retained. No AI-generated replacement or content alteration.","checked":"2026-11-22","localAssetIds":["project-image"]}],"assets":[{"id":"schematic","title":"Conceptual study schematic","kind":"figure","fileName":"west-closure-complex.svg","mimeType":"image/svg+xml","bytes":1199,"sha256":"2e6aeebf9456a19bc9da1a7d3b9c13bec3912b8bc79cc219008f227e2613f027","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/west-closure-complex/download/schematic"},{"id":"project-image","title":"West Closure Complex testing, Louisiana 2023 - 01.jpg","kind":"project-image","fileName":"west-closure-complex.jpg","mimeType":"image/jpeg","bytes":151852,"sha256":"24ff3fd3f6dcdabc9dc258256e332c4cd04548f9398b99d6a9568ecf307d5697","sourceId":"s3","license":"Public domain","width":1280,"height":854,"credit":"Team New Orleans, US Army Corps of Engineers","sourceUrl":"https://commons.wikimedia.org/wiki/File:West_Closure_Complex_testing,_Louisiana_2023_-_01.jpg","licenseUrl":"https://commons.wikimedia.org/wiki/File:West_Closure_Complex_testing,_Louisiana_2023_-_01.jpg#Licensing","imageDate":"2023-05-11 10:19:39","evidenceFile":"image-provenance/west-closure-complex-commons.json","evidenceSha256":"8d095d27d0a6bde356c186d31570a687b18cca899f9d4b359ceef56a389fc721","transformations":"Unmodified publisher-generated display-size file; the original source URL and publisher metadata are retained. No AI-generated replacement or content alteration.","originalUrl":"https://upload.wikimedia.org/wikipedia/commons/1/13/West_Closure_Complex_testing%2C_Louisiana_2023_-_01.jpg","downloadUrl":"/cases/west-closure-complex/download/project-image","originalSha1":"13204edda35ce31161453465ac85aa6fac1fe530","imageDownloadAllowed":true,"rightsBasis":"See the per-image provenance record and linked license; source hosting alone is not the rights basis."},{"id":"capstone-brief","title":"Capstone brief (Markdown)","kind":"brief","fileName":"west-closure-complex-capstone.md","mimeType":"text/markdown","bytes":3328,"sha256":"fec13d74d145a189bb0a084cecd6f93a464bf18f7883a87b18e15f167b3f654e","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/west-closure-complex/download/capstone-brief"}],"figure":{"assetId":"project-image","kind":"photograph","alt":"The West Closure Complex during its 2023 annual operational testing.","caption":"The West Closure Complex during its 2023 annual operational testing. This is the completed gate and pumping project discussed in the foundation-characterization paper.","credit":"Team New Orleans, US Army Corps of Engineers","sourceUrl":"https://commons.wikimedia.org/wiki/File:West_Closure_Complex_testing,_Louisiana_2023_-_01.jpg","license":"Public domain","licenseUrl":"https://commons.wikimedia.org/wiki/File:West_Closure_Complex_testing,_Louisiana_2023_-_01.jpg#Licensing","width":1280,"height":854,"imageDate":"2023-05-11 10:19:39","imageDownloadAllowed":true},"figureCaption":"The West Closure Complex during its 2023 annual operational testing. This is the completed gate and pumping project discussed in the foundation-characterization paper.","qualityNotes":[],"checked":"2026-11-22","addedIn":"r13","curatedOrder":73,"referenceValues":[],"teachingFigureCaption":"Conceptual study schematic; not an as-built project drawing.","imageEvidence":{"status":"acquired","identityVerified":true,"evidenceFile":"image-provenance/west-closure-complex-commons.json","evidenceSha256":"8d095d27d0a6bde356c186d31570a687b18cca899f9d4b359ceef56a389fc721","visualReview":"Viewed the complete publisher photograph in the final contact sheets or individually and compared it with the source identity, date, and caption. The caption distinguishes project context from the particular underground treatment or construction stage.","checked":"2026-11-22"},"localReportCount":0,"downloadBytes":156379,"sourceCount":3,"url":"/cases/west-closure-complex"},{"id":"trans-alaska-pipeline","title":"Trans-Alaska Pipeline — thermally stabilized supports in permafrost","summary":"The pipeline uses elevated supports where thaw-sensitive permafrost would be disturbed by warm oil. Operator and state-geology sources describe thermal support members, heat-pipe monitoring and maintenance.","topics":["cold-regions","deep-foundations","monitoring","problem-soils"],"country":"United States","region":"Alaska","owner":"Alyeska Pipeline Service Company","year":2022,"yearLabel":"Case reference year","projectType":"Design, construction and performance","methods":["Thermosyphons","Thaw settlement","Thermal piles","Infrared surveillance"],"documentationLevel":"technical-case","design":{"availability":"partial","summary":"The sources explain design modes and thermal monitoring. They do not justify assuming that every support experiences the same ground temperature or ice content.","sourceIds":["s1","s2"]},"cost":{"availability":"not-found","summary":"A project-specific estimate, bid schedule or final account was not found in the reviewed sources.","sourceIds":[]},"schedule":{"availability":"not-found","summary":"A dated project programme was not found in the reviewed sources; develop a study schedule from the documented method.","sourceIds":[]},"records":{"availability":"partial","summary":"The sources describe an operating maintenance system and ongoing observations, not a once-only completed cooling treatment.","sourceIds":["s1","s2"]},"capstone":{"label":"Suggested capstone study","scope":"An original teaching brief based on the documented project. Study assumptions and student designs are separate from the built project.","brief":"Design an elevated pipe support whose foundation must remain stable as the seasonal thermal regime changes.","inputs":["Distinguish thaw-stable and thaw-unstable ground and identify the operator’s design modes.","Define a study soil-ice profile, climate series and support load using clearly stated assumptions."],"deliverables":["Compare thaw-settlement risk for untreated and passively cooled supports.","Prepare heat-pipe inspection, performance assessment and repair priorities.","A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.","A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points."],"questions":["Why is a foundation’s thermal condition as important as its initial bearing capacity?","Which observations distinguish a failed heat pipe from a change in regional ground temperature?"],"output":"Design report, calculation workbook, concept drawings, quantity schedule and construction programme."},"sources":[{"id":"s1","title":"Permafrost and pipeline design modes","url":"https://alyeska-pipe.com/environmental-protection/","publisher":"Alyeska Pipeline Service Company","year":null,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s2","title":"Guide to permafrost and pipeline thermal supports","url":"https://dggs.alaska.gov/webpubs/dggs/gb/text/gb011.pdf","publisher":"Alaska Division of Geological & Geophysical Surveys","year":null,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s3","title":"Pipeline vertical support member.jpg — image and reuse license","url":"https://commons.wikimedia.org/wiki/File:Pipeline_vertical_support_member.jpg","publisher":"Wikimedia Commons / JKBrooks85","year":2009,"access":"public-link","license":"Public domain","notes":"Project image source. Unmodified publisher-generated display-size file; the original source URL and publisher metadata are retained. No AI-generated replacement or content alteration.","checked":"2026-11-22","localAssetIds":["project-image"]}],"assets":[{"id":"schematic","title":"Conceptual study schematic","kind":"figure","fileName":"trans-alaska-pipeline.svg","mimeType":"image/svg+xml","bytes":968,"sha256":"90bd9d5f0e906d8c86b1dbf936087013600fc464568e53625a08db29592daa87","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/trans-alaska-pipeline/download/schematic"},{"id":"project-image","title":"Pipeline vertical support member.jpg","kind":"project-image","fileName":"trans-alaska-pipeline.jpg","mimeType":"image/jpeg","bytes":276864,"sha256":"95af32a5a9e743df4620352815794b8e849ecacf42f144afd7539bfb960faf59","sourceId":"s3","license":"Public domain","width":1280,"height":1786,"credit":"JKBrooks85","sourceUrl":"https://commons.wikimedia.org/wiki/File:Pipeline_vertical_support_member.jpg","licenseUrl":"https://commons.wikimedia.org/wiki/File:Pipeline_vertical_support_member.jpg#Licensing","imageDate":"2009-07-15","evidenceFile":"image-provenance/trans-alaska-pipeline-commons.json","evidenceSha256":"35ae4095e2d748ed8f40f58a36da1e011fc8623305a2e9c5960b497c63202f7a","transformations":"Unmodified publisher-generated display-size file; the original source URL and publisher metadata are retained. No AI-generated replacement or content alteration.","originalUrl":"https://upload.wikimedia.org/wikipedia/commons/7/7c/Pipeline_vertical_support_member.jpg","downloadUrl":"/cases/trans-alaska-pipeline/download/project-image","originalSha1":"d00ccb10f81ff141b64657c56034afc9de8df237","imageDownloadAllowed":true,"rightsBasis":"See the per-image provenance record and linked license; source hosting alone is not the rights basis."},{"id":"capstone-brief","title":"Capstone brief (Markdown)","kind":"brief","fileName":"trans-alaska-pipeline-capstone.md","mimeType":"text/markdown","bytes":3223,"sha256":"ec3686dad92cdeee5d12b99ad4f7a2c3957dd463a9f24f58d97ff6e6ea2535eb","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/trans-alaska-pipeline/download/capstone-brief"}],"figure":{"assetId":"project-image","kind":"photograph","alt":"A vertical support member of the Trans-Alaska Pipeline topped by two heat-pipe radiators.","caption":"A vertical support member of the Trans-Alaska Pipeline topped by two heat-pipe radiators. The photograph shows the actual foundation-cooling detail used to protect frozen ground around supports.","credit":"JKBrooks85","sourceUrl":"https://commons.wikimedia.org/wiki/File:Pipeline_vertical_support_member.jpg","license":"Public domain","licenseUrl":"https://commons.wikimedia.org/wiki/File:Pipeline_vertical_support_member.jpg#Licensing","width":1280,"height":1786,"imageDate":"2009-07-15","preserveWholeImage":true,"imageDownloadAllowed":true},"figureCaption":"A vertical support member of the Trans-Alaska Pipeline topped by two heat-pipe radiators. The photograph shows the actual foundation-cooling detail used to protect frozen ground around supports.","qualityNotes":[],"checked":"2026-11-22","addedIn":"r13","curatedOrder":85,"referenceValues":[],"teachingFigureCaption":"Conceptual study schematic; not an as-built project drawing.","imageEvidence":{"status":"acquired","identityVerified":true,"evidenceFile":"image-provenance/trans-alaska-pipeline-commons.json","evidenceSha256":"35ae4095e2d748ed8f40f58a36da1e011fc8623305a2e9c5960b497c63202f7a","visualReview":"Viewed the complete publisher photograph in the final contact sheets or individually and compared it with the source identity, date, and caption. The caption distinguishes project context from the particular underground treatment or construction stage.","checked":"2026-11-22"},"localReportCount":0,"downloadBytes":281055,"sourceCount":3,"url":"/cases/trans-alaska-pipeline"},{"id":"qinghai-tibet-railway","title":"Qinghai–Tibet Railway — crushed-rock embankments over warming permafrost","summary":"Instrumented railway embankments provide evidence on the cooling and deformation of crushed-rock configurations. Researchers compare thermal performance, sunny/shady slope effects and continuing permafrost change.","topics":["cold-regions","earthworks","monitoring","problem-soils"],"country":"China","region":"Qinghai–Tibet Plateau","owner":"Qinghai–Tibet Railway","year":2020,"yearLabel":"Case reference year","projectType":"Design, construction and performance","methods":["Air-convection embankments","Thermal monitoring","Thaw deformation"],"documentationLevel":"monitoring-study","design":{"availability":"partial","summary":"The monitoring paper reports several embankment configurations. Later proposed reinforcement is research, not proof that every monitored section was reconstructed with that measure.","sourceIds":["s1","s2"]},"cost":{"availability":"not-found","summary":"A project-specific estimate, bid schedule or final account was not found in the reviewed sources.","sourceIds":[]},"schedule":{"availability":"not-found","summary":"A dated project programme was not found in the reviewed sources; develop a study schedule from the documented method.","sourceIds":[]},"records":{"availability":"not-found","summary":"Complete as-built drawings and acceptance records were not found in the reviewed sources.","sourceIds":[]},"capstone":{"label":"Suggested capstone study","scope":"An original teaching brief based on the documented project. Study assumptions and student designs are separate from the built project.","brief":"Select an embankment cross-section for warm permafrost using both thermal and deformation performance.","inputs":["Extract the monitoring period and distinguish the compared crushed-rock arrangements.","Define climate, aspect and rock-layer permeability sensitivities for the study section."],"deliverables":["Compare seasonal cooling and thaw-depth trends under alternative geometries.","Develop maintenance checks for clogging, slope asymmetry and track-level movement.","A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.","A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points."],"questions":["How can a rock layer lose cooling effectiveness even when its thickness is unchanged?","Why should the warmest year and cumulative thermal trend both inform maintenance decisions?"],"output":"Design report, calculation workbook, concept drawings, quantity schedule and construction programme."},"sources":[{"id":"s1","title":"Cooling performance and deformation of railway embankments","url":"https://www.sciencedirect.com/science/article/pii/S0013795219312098","publisher":"Tai and coauthors / Engineering Geology","year":null,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s2","title":"Performance and reinforcement study","url":"https://pmc.ncbi.nlm.nih.gov/articles/PMC11471204/","publisher":"Research authors / open journal article","year":null,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s3","title":"Lhassa-Xining railway.JPG — image and reuse license","url":"https://commons.wikimedia.org/wiki/File:Lhassa-Xining_railway.JPG","publisher":"Wikimedia Commons / This illustration was made by ( User:Royonx ) and released under the license(s) stated above. You are free to use it for any purpose as long as you credit me and follow the terms of the license. Example : © Michel Royon / Wikimedia Commons If you use this image outside of the Wikimedia projects, I would be happy to hear from you par courriel ( royonx gmail.com). Thanks ! Ce message en français","year":2012,"access":"public-link","license":"CC0","notes":"Project image source. Unmodified publisher-generated display-size file; the original source URL and publisher metadata are retained. No AI-generated replacement or content alteration.","checked":"2026-11-22","localAssetIds":["project-image"]}],"assets":[{"id":"schematic","title":"Conceptual study schematic","kind":"figure","fileName":"qinghai-tibet-railway.svg","mimeType":"image/svg+xml","bytes":968,"sha256":"90bd9d5f0e906d8c86b1dbf936087013600fc464568e53625a08db29592daa87","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/qinghai-tibet-railway/download/schematic"},{"id":"project-image","title":"Lhassa-Xining railway.JPG","kind":"project-image","fileName":"qinghai-tibet-railway.jpg","mimeType":"image/jpeg","bytes":577578,"sha256":"e3bdb64f0cac308615d1017bb64abcec0d6a428ad400ccf8d23332aaaef94bc0","sourceId":"s3","license":"CC0","width":1280,"height":961,"credit":"This illustration was made by ( User:Royonx ) and released under the license(s) stated above. You are free to use it for any purpose as long as you credit me and follow the terms of the license. Example : © Michel Royon / Wikimedia Commons If you use this image outside of the Wikimedia projects, I would be happy to hear from you par courriel ( royonx gmail.com). Thanks ! Ce message en français","sourceUrl":"https://commons.wikimedia.org/wiki/File:Lhassa-Xining_railway.JPG","licenseUrl":"https://creativecommons.org/publicdomain/zero/1.0/deed.en","imageDate":"2012-05-14","evidenceFile":"image-provenance/qinghai-tibet-railway-commons.json","evidenceSha256":"570452a99f700b14e881a3d7d43b31edcc6795fb8a69c2b1e322e281bafca47d","transformations":"Unmodified publisher-generated display-size file; the original source URL and publisher metadata are retained. No AI-generated replacement or content alteration.","originalUrl":"https://upload.wikimedia.org/wikipedia/commons/9/90/Lhassa-Xining_railway.JPG","downloadUrl":"/cases/qinghai-tibet-railway/download/project-image","originalSha1":"e561258d5e03d572416a91865a11a4421aca973f","imageDownloadAllowed":true,"rightsBasis":"See the per-image provenance record and linked license; source hosting alone is not the rights basis."},{"id":"capstone-brief","title":"Capstone brief (Markdown)","kind":"brief","fileName":"qinghai-tibet-railway-capstone.md","mimeType":"text/markdown","bytes":3908,"sha256":"9fd34b9e382fbf6d1d0107977d066f9ff370d3eb2ecab7364cad29b308c04651","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/qinghai-tibet-railway/download/capstone-brief"}],"figure":{"assetId":"project-image","kind":"photograph","alt":"The Qinghai–Tibet railway route beyond Golmud.","caption":"The Qinghai–Tibet railway route beyond Golmud. This is corridor context; it is not labeled as one of the instrumented cross-sections in the cited monitoring papers.","credit":"This illustration was made by ( User:Royonx ) and released under the license(s) stated above. You are free to use it for any purpose as long as you credit me and follow the terms of the license. Example : © Michel Royon / Wikimedia Commons If you use this image outside of the Wikimedia projects, I would be happy to hear from you par courriel ( royonx gmail.com). Thanks ! Ce message en français","sourceUrl":"https://commons.wikimedia.org/wiki/File:Lhassa-Xining_railway.JPG","license":"CC0","licenseUrl":"https://creativecommons.org/publicdomain/zero/1.0/deed.en","width":1280,"height":961,"imageDate":"2012-05-14","imageDownloadAllowed":true},"figureCaption":"The Qinghai–Tibet railway route beyond Golmud. This is corridor context; it is not labeled as one of the instrumented cross-sections in the cited monitoring papers.","qualityNotes":[],"checked":"2026-11-22","addedIn":"r13","curatedOrder":86,"referenceValues":[],"teachingFigureCaption":"Conceptual study schematic; not an as-built project drawing.","imageEvidence":{"status":"acquired","identityVerified":true,"evidenceFile":"image-provenance/qinghai-tibet-railway-commons.json","evidenceSha256":"570452a99f700b14e881a3d7d43b31edcc6795fb8a69c2b1e322e281bafca47d","visualReview":"Viewed the complete publisher photograph in the final contact sheets or individually and compared it with the source identity, date, and caption. The caption distinguishes project context from the particular underground treatment or construction stage.","checked":"2026-11-22"},"localReportCount":0,"downloadBytes":582454,"sourceCount":3,"url":"/cases/qinghai-tibet-railway"},{"id":"st-francis-dam","title":"St. Francis Dam — investigation evidence and foundation reassessment","summary":"The 1928 collapse prompted an official investigation and later reassessments of geology and foundation behavior. The records make a useful exercise in distinguishing contemporary findings from subsequent hypotheses.","topics":["rock","dams-levees","problem-soils","site-investigation"],"country":"United States","region":"San Francisquito Canyon, California","owner":"Historic Los Angeles water-supply project","year":1928,"yearLabel":"Case reference year","projectType":"Failure investigation and lessons","methods":["Forensic ground model","Foundation saturation","Abutment stability"],"documentationLevel":"forensic-study","design":{"availability":"partial","summary":"The commission report and later research represent different stages of interpretation. No single disputed mechanism is presented as conclusively established by this catalog.","sourceIds":["s1","s2","s3"]},"cost":{"availability":"not-found","summary":"A project-specific estimate, bid schedule or final account was not found in the reviewed sources.","sourceIds":[]},"schedule":{"availability":"not-found","summary":"A dated project programme was not found in the reviewed sources; develop a study schedule from the documented method.","sourceIds":[]},"records":{"availability":"not-found","summary":"Complete as-built drawings and acceptance records were not found in the reviewed sources.","sourceIds":[]},"capstone":{"label":"Suggested capstone study","scope":"An original teaching brief based on the documented project. Study assumptions and student designs are separate from the built project.","brief":"Compare competing foundation-failure explanations and propose the investigation that would best distinguish them.","inputs":["Extract evidence from the original commission report separately from later interpretations.","Map the contrasting abutment materials and identify changes associated with reservoir filling."],"deliverables":["Prepare sensitivity checks for sliding, uplift and material degradation.","Build an evidence matrix showing which observations support or contradict each mechanism.","A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.","A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points."],"questions":["Which conclusion depends most strongly on an assumed pre-failure groundwater condition?","How would modern investigation reduce uncertainty without claiming hindsight makes the outcome inevitable?"],"output":"Design report, calculation workbook, concept drawings, quantity schedule and construction programme."},"sources":[{"id":"s1","title":"Original commission report record","url":"https://damsafety.org/content/causes-leading-failure-saint-francis-dam","publisher":"California investigation commission / ASDSO archive","year":null,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s2","title":"Later foundation reassessment","url":"https://damsafety.org/content/reassessment-st-francis-dam-failure-0","publisher":"J. David Rogers and David McMahon / ASDSO","year":null,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s3","title":"USGS historical overview","url":"https://www.usgs.gov/media/images/st-francis-dam-disaster","publisher":"US Geological Survey","year":null,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s4","title":"Saint Francis Dam Site 2012.jpg — image and reuse license","url":"https://commons.wikimedia.org/wiki/File:Saint_Francis_Dam_Site_2012.jpg","publisher":"Wikimedia Commons / Chevy111","year":2012,"access":"public-link","license":"CC BY-SA 4.0","notes":"Project image source. Unmodified publisher-generated display-size file; the original source URL and publisher metadata are retained. No AI-generated replacement or content alteration.","checked":"2026-11-22","localAssetIds":["project-image"]}],"assets":[{"id":"schematic","title":"Conceptual study schematic","kind":"figure","fileName":"st-francis-dam.svg","mimeType":"image/svg+xml","bytes":1017,"sha256":"ab086e9b878d71ca75443d4083022bf013c864b1ad5c4bbfbedf783b1ffc7360","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/st-francis-dam/download/schematic"},{"id":"project-image","title":"Saint Francis Dam Site 2012.jpg","kind":"project-image","fileName":"st-francis-dam.jpg","mimeType":"image/jpeg","bytes":410499,"sha256":"615231c05357069092a774fa146cb08b7be245e4ef4479873474fa16986d23f3","sourceId":"s4","license":"CC BY-SA 4.0","width":1280,"height":960,"credit":"Chevy111","sourceUrl":"https://commons.wikimedia.org/wiki/File:Saint_Francis_Dam_Site_2012.jpg","licenseUrl":"https://creativecommons.org/licenses/by-sa/4.0","imageDate":"2012-08-05 09:47:38","evidenceFile":"image-provenance/st-francis-dam-commons.json","evidenceSha256":"53a2c42e8c9d7963c83e036424e0cf8fc84572d726d0e567074b0648702bb588","transformations":"Unmodified publisher-generated display-size file; the original source URL and publisher metadata are retained. No AI-generated replacement or content alteration.","originalUrl":"https://upload.wikimedia.org/wikipedia/commons/a/a3/Saint_Francis_Dam_Site_2012.jpg","downloadUrl":"/cases/st-francis-dam/download/project-image","originalSha1":"9f6c998731ed25f57bb2d83749f0b6043c7ec96b","imageDownloadAllowed":true,"rightsBasis":"See the per-image provenance record and linked license; source hosting alone is not the rights basis."},{"id":"capstone-brief","title":"Capstone brief (Markdown)","kind":"brief","fileName":"st-francis-dam-capstone.md","mimeType":"text/markdown","bytes":3301,"sha256":"5af44503b48f4b65d84af1c900f2f16e6943ff68d5b7e370826792c2a549f618","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/st-francis-dam/download/capstone-brief"}],"figure":{"assetId":"project-image","kind":"photograph","alt":"Concrete ruins at the St.","caption":"Concrete ruins at the St. Francis Dam site in San Francisquito Canyon, photographed in 2012. The image shows the actual historic failure site.","credit":"Chevy111","sourceUrl":"https://commons.wikimedia.org/wiki/File:Saint_Francis_Dam_Site_2012.jpg","license":"CC BY-SA 4.0","licenseUrl":"https://creativecommons.org/licenses/by-sa/4.0","width":1280,"height":960,"imageDate":"2012-08-05 09:47:38","imageDownloadAllowed":true},"figureCaption":"Concrete ruins at the St. Francis Dam site in San Francisquito Canyon, photographed in 2012. The image shows the actual historic failure site.","qualityNotes":[],"checked":"2026-11-22","addedIn":"r13","curatedOrder":89,"referenceValues":[],"teachingFigureCaption":"Conceptual study schematic; not an as-built project drawing.","imageEvidence":{"status":"acquired","identityVerified":true,"evidenceFile":"image-provenance/st-francis-dam-commons.json","evidenceSha256":"53a2c42e8c9d7963c83e036424e0cf8fc84572d726d0e567074b0648702bb588","visualReview":"Viewed the complete publisher photograph in the final contact sheets or individually and compared it with the source identity, date, and caption. The caption distinguishes project context from the particular underground treatment or construction stage.","checked":"2026-11-22"},"localReportCount":0,"downloadBytes":414817,"sourceCount":4,"url":"/cases/st-francis-dam"},{"id":"rissa-landslide","title":"Rissa landslide — sensitive clay and retrogressive failure","summary":"The quick-clay landslide was filmed during retrogressive movement. NGI explains the remoulding mechanism and publishes strength and geometry evidence used in stability interpretation.","topics":["slopes","problem-soils","laboratory-testing","site-investigation"],"country":"Norway","region":"Rissa, Trøndelag","owner":"Historic landslide investigation / Norwegian Geotechnical Institute","year":1978,"yearLabel":"Case reference year","projectType":"Failure investigation and lessons","methods":["Quick-clay characterization","Undrained stability","Retrogression"],"documentationLevel":"forensic-study","design":{"availability":"partial","summary":"The research supports analysis of sensitive-clay behavior and failure extent. A back-analysis is not a local development approval or a current hazard map.","sourceIds":["s1","s2"]},"cost":{"availability":"not-found","summary":"A project-specific estimate, bid schedule or final account was not found in the reviewed sources.","sourceIds":[]},"schedule":{"availability":"not-found","summary":"A dated project programme was not found in the reviewed sources; develop a study schedule from the documented method.","sourceIds":[]},"records":{"availability":"not-found","summary":"Complete as-built drawings and acceptance records were not found in the reviewed sources.","sourceIds":[]},"capstone":{"label":"Suggested capstone study","scope":"An original teaching brief based on the documented project. Study assumptions and student designs are separate from the built project.","brief":"Develop an investigation and stability assessment for a gentle slope underlain by sensitive marine clay.","inputs":["Extract the published intact and remoulded strength evidence and groundwater setting.","Separate initial triggering from subsequent retrogressive propagation."],"deliverables":["Compare intact-strength stability with a remoulding-sensitive scenario.","Specify sampling, sensitivity testing and a conservative exclusion-zone rationale.","A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.","A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points."],"questions":["Why can an initially small disturbance lead to failure far behind the original slope face?","Which laboratory sample disturbance would most distort the assessment of clay sensitivity?"],"output":"Design report, calculation workbook, concept drawings, quantity schedule and construction programme."},"sources":[{"id":"s1","title":"Quick clay and the Rissa event","url":"https://www.ngi.no/en/research-and-consulting/natural-hazards-container/avalanches-and-slides/quick-clay-landslides/what-is-quick-clay/","publisher":"Norwegian Geotechnical Institute","year":null,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s2","title":"Stability of natural slopes in quick clay","url":"https://ngi.brage.unit.no/ngi-xmlui/bitstream/handle/11250/3031017/Aas_Lacasse%20%282022%29%205.pdf?sequence=1","publisher":"Aas and Lacasse / NGI repository","year":null,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s3","title":"Rissaraset i 1978 - Se videoen som gikk verden rundt","url":"https://www.ngu.no/en/node/183","publisher":"Geological Survey of Norway (NGU)","year":1978,"access":"public-link","license":"No open reuse license verified; original copyright retained","notes":"Project image source. Resized the full 1440 × 947 NGU JPEG derivative proportionally to 900 × 592 pixels, JPEG quality 90; no cropping, added labels, or retouching.","checked":"2026-11-22","localAssetIds":["project-image"]}],"assets":[{"id":"schematic","title":"Conceptual study schematic","kind":"figure","fileName":"rissa-landslide.svg","mimeType":"image/svg+xml","bytes":1029,"sha256":"ccf2f027816a3de86d722599635826d3b3cadcf8867cf69fa1bf6fc1bdf2d3bf","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/rissa-landslide/download/schematic"},{"id":"project-image","title":"Rissa landslide — the 1978 aftermath","kind":"project-image","fileName":"rissa-landslide-r13.jpg","mimeType":"image/jpeg","bytes":144975,"sha256":"feb55ed544ec8f298dd564198d08a00755dd292e80ddc81f192f55187577389b","sourceId":"s3","license":"No open reuse license verified; original copyright retained","width":900,"height":592,"credit":"Bjørn Bergstrøm / Geological Survey of Norway (NGU)","sourceUrl":"https://www.ngu.no/en/node/183","licenseUrl":"https://www.ngu.no/en/node/183","imageDate":"1978","evidenceFile":"image-provenance/rissa-landslide-r13-source.json","evidenceSha256":"c539032706b8042ad7776dcef3d3d44dc044c4b5729bc09c618e42e38c3a6d4e","transformations":"Resized the full 1440 × 947 NGU JPEG derivative proportionally to 900 × 592 pixels, JPEG quality 90; no cropping, added labels, or retouching.","originalUrl":"https://www.ngu.no/sites/default/files/styles/full_content_width/public/2023-03/Mann%20ser%20p%C3%A5%20skadene%20etter%20Rissaraset.%20Foto%20Bj%C3%B8rn%20Bergstr%C3%B8m%20NGU..jpg?itok=0SuzRFv9","originalSha256":"bcb5d813d802c6b165174d59b4a412ab0b9d5cedf95831466956c51c3c204960","imageDownloadAllowed":false,"rightsStatus":"editorial-reference","permissionStatus":"No open reuse permission verified","rightsNote":"Source-linked editorial reference; copyright remains with the original owner. The site does not offer this image as a reusable download.","imageUsage":"project-photograph","rightsBasis":"See the per-image provenance record and linked license; source hosting alone is not the rights basis.","previewUrl":"/cases/rissa-landslide/figure"},{"id":"capstone-brief","title":"Capstone brief (Markdown)","kind":"brief","fileName":"rissa-landslide-capstone.md","mimeType":"text/markdown","bytes":3113,"sha256":"85e26a6127f09820a20adf40744fc933794b19146f55a747550aef80a132cd93","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/rissa-landslide/download/capstone-brief"}],"figure":{"assetId":"project-image","kind":"photograph","alt":"A person standing beside damaged buildings and the failed ground after the 1978 Rissa landslide.","caption":"A person examines the damage left by the 1978 Rissa landslide. NGU identifies the event and credits the original photograph to Bjørn Bergstrøm.","credit":"Bjørn Bergstrøm / Geological Survey of Norway (NGU)","sourceUrl":"https://www.ngu.no/en/node/183","license":"No open reuse license verified; original copyright retained","licenseUrl":"https://www.ngu.no/en/node/183","width":900,"height":592,"imageDate":"1978","preserveWholeImage":true,"imageDownloadAllowed":false,"rightsStatus":"editorial-reference","permissionStatus":"No open reuse permission verified","rightsNote":"Source-linked editorial reference; copyright remains with the original owner. The site does not offer this image as a reusable download.","imageUsage":"project-photograph"},"figureCaption":"A person examines the damage left by the 1978 Rissa landslide. NGU identifies the event and credits the original photograph to Bjørn Bergstrøm.","qualityNotes":[],"checked":"2026-11-22","addedIn":"r13","curatedOrder":90,"referenceValues":[],"teachingFigureCaption":"Conceptual study schematic; not an as-built project drawing.","imageEvidence":{"status":"acquired","identityVerified":true,"evidenceFile":"image-provenance/rissa-landslide-r13-source.json","evidenceSha256":"c539032706b8042ad7776dcef3d3d44dc044c4b5729bc09c618e42e38c3a6d4e","visualReview":"Inspected the full 1440 × 947 source and the proportional 900 pixel derivative. They show an observer, damaged red buildings and the landslide scarp/failed ground. The entire published scene is retained.","checked":"2026-11-22"},"localReportCount":0,"downloadBytes":4142,"sourceCount":3,"url":"/cases/rissa-landslide"},{"id":"turnagain-heights","title":"Turnagain Heights — earthquake-triggered bluff failure","summary":"The earthquake triggered destructive ground movement in bluffs underlain by the Bootlegger Cove Formation. USGS later characterized individual facies to examine their roles in the landslide.","topics":["slopes","seismic","problem-soils","laboratory-testing"],"country":"United States","region":"Anchorage, Alaska","owner":"USGS / Alaska geological investigation","year":1964,"yearLabel":"Case reference year","projectType":"Design, construction and performance","methods":["Cyclic strength loss","Sensitive strata","Landslide back-analysis"],"documentationLevel":"technical-report","design":{"availability":"partial","summary":"Public reports contain maps, sections and geotechnical observations. They support evaluation of alternative strength-loss mechanisms without treating the formation as one uniform clay.","sourceIds":["s1","s2"]},"cost":{"availability":"not-found","summary":"A project-specific estimate, bid schedule or final account was not found in the reviewed sources.","sourceIds":[]},"schedule":{"availability":"not-found","summary":"A dated project programme was not found in the reviewed sources; develop a study schedule from the documented method.","sourceIds":[]},"records":{"availability":"not-found","summary":"Complete as-built drawings and acceptance records were not found in the reviewed sources.","sourceIds":[]},"capstone":{"label":"Suggested capstone study","scope":"An original teaching brief based on the documented project. Study assumptions and student designs are separate from the built project.","brief":"Reassess an earthquake-prone bluff using facies-based strength characterization instead of a single averaged profile.","inputs":["Extract the mapped slide geometry and stratigraphic distinctions from the USGS report.","Identify which observations constrain sand-layer liquefaction versus sensitive-clay response."],"deliverables":["Compare static and post-shaking stability for alternative weak-layer models.","Prepare a targeted sampling and cyclic-testing programme with a redevelopment setback argument.","A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.","A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points."],"questions":["How does shaking duration affect the applicability of a historical failure analogy?","Which geological detail would be lost by averaging all fine-grained layers into one unit?"],"output":"Design report, calculation workbook, concept drawings, quantity schedule and construction programme."},"sources":[{"id":"s1","title":"Geologic and geotechnical conditions at Turnagain Heights","url":"https://pubs.usgs.gov/publication/b1817","publisher":"US Geological Survey","year":null,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s2","title":"Effects of the 1964 Anchorage earthquake","url":"https://www.usgs.gov/publications/effects-earthquake-march-27-1964-anchorage-alaska","publisher":"US Geological Survey","year":null,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s3","title":"AlaskaQuake-Turnagain.jpg — image and reuse license","url":"https://commons.wikimedia.org/wiki/File:AlaskaQuake-Turnagain.jpg","publisher":"Wikimedia Commons / U.S. Geological Survey","year":1964,"access":"public-link","license":"Public domain in the United States — U.S. Geological Survey photograph","notes":"Project image source. Unmodified publisher-generated display-size file; the original source URL and publisher metadata are retained. No AI-generated replacement or content alteration.","checked":"2026-11-22","localAssetIds":["project-image"]}],"assets":[{"id":"schematic","title":"Conceptual study schematic","kind":"figure","fileName":"turnagain-heights.svg","mimeType":"image/svg+xml","bytes":1029,"sha256":"ccf2f027816a3de86d722599635826d3b3cadcf8867cf69fa1bf6fc1bdf2d3bf","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/turnagain-heights/download/schematic"},{"id":"project-image","title":"AlaskaQuake-Turnagain.jpg","kind":"project-image","fileName":"turnagain-heights.jpg","mimeType":"image/jpeg","bytes":163445,"sha256":"64d155e422d3ffedc05225737c8a4783eea93a28638a3997a6d6c9379ee2637b","sourceId":"s3","license":"Public domain in the United States — U.S. Geological Survey photograph","width":1000,"height":666,"credit":"U.S. Geological Survey (USGS)","sourceUrl":"https://commons.wikimedia.org/wiki/File:AlaskaQuake-Turnagain.jpg","licenseUrl":"https://commons.wikimedia.org/wiki/File:AlaskaQuake-Turnagain.jpg#Licensing","imageDate":"1964","evidenceFile":"image-provenance/turnagain-heights-commons.json","evidenceSha256":"4b620dbe87d14515ba12fbfef07c15c15a516577346fcaf7a0f6c1837eb05094","transformations":"Unmodified publisher-generated display-size file; the original source URL and publisher metadata are retained. No AI-generated replacement or content alteration.","originalUrl":"https://upload.wikimedia.org/wikipedia/commons/a/a5/AlaskaQuake-Turnagain.jpg","downloadUrl":"/cases/turnagain-heights/download/project-image","originalSha1":"1751807d2f10356306ff1d388d967c59b30b322b","originalSha256":"64d155e422d3ffedc05225737c8a4783eea93a28638a3997a6d6c9379ee2637b","imageDownloadAllowed":true,"rightsNote":"The file description identifies this image as originating with USGS; the photographer is not individually named.","rightsBasis":"See the per-image provenance record and linked license; source hosting alone is not the rights basis."},{"id":"capstone-brief","title":"Capstone brief (Markdown)","kind":"brief","fileName":"turnagain-heights-capstone.md","mimeType":"text/markdown","bytes":3181,"sha256":"605b8502d5a6f7c893353f83697df369df656dab0d21028f505d5e49b62c69c4","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/turnagain-heights/download/capstone-brief"}],"figure":{"assetId":"project-image","kind":"photograph","alt":"The Turnagain Heights landslide after the 1964 Alaska earthquake.","caption":"The Turnagain Heights landslide after the 1964 Alaska earthquake. Historical photograph of the actual damaged bluff and neighborhood.","credit":"U.S. Geological Survey (USGS)","sourceUrl":"https://commons.wikimedia.org/wiki/File:AlaskaQuake-Turnagain.jpg","license":"Public domain in the United States — U.S. Geological Survey photograph","licenseUrl":"https://commons.wikimedia.org/wiki/File:AlaskaQuake-Turnagain.jpg#Licensing","width":1000,"height":666,"imageDate":"1964","preserveWholeImage":true,"imageDownloadAllowed":true,"rightsNote":"The file description identifies this image as originating with USGS; the photographer is not individually named."},"figureCaption":"The Turnagain Heights landslide after the 1964 Alaska earthquake. Historical photograph of the actual damaged bluff and neighborhood.","qualityNotes":[],"checked":"2026-11-22","addedIn":"r13","curatedOrder":91,"referenceValues":[],"teachingFigureCaption":"Conceptual study schematic; not an as-built project drawing.","imageEvidence":{"status":"acquired","identityVerified":true,"evidenceFile":"image-provenance/turnagain-heights-commons.json","evidenceSha256":"4b620dbe87d14515ba12fbfef07c15c15a516577346fcaf7a0f6c1837eb05094","visualReview":"Viewed the complete publisher photograph in the final contact sheets or individually and compared it with the source identity, date, and caption. The caption distinguishes project context from the particular underground treatment or construction stage.","checked":"2026-11-22"},"localReportCount":0,"downloadBytes":167655,"sourceCount":3,"url":"/cases/turnagain-heights"}]}