{"schemaVersion":1,"updated":"2026-11-22","total":27,"records":[{"id":"wolf-creek","title":"Wolf Creek Dam — karst-foundation cutoff wall","summary":"A deep concrete barrier and associated grouting addressed seepage through the dam’s karst foundation. USACE documents completion and project scope.","topics":["dams-levees","seepage","rock","ground-improvement","delivery"],"country":"United States","region":"Jamestown, Kentucky","owner":"US Army Corps of Engineers","year":2013,"yearLabel":"Case reference year","projectType":"Rehabilitation","methods":["Cutoff wall","Karst grouting","Dam seepage control"],"documentationLevel":"project-summary","design":{"availability":"partial","summary":"The completion account describes approximately 1,197 overlapping piles forming a 4,000-foot barrier. It does not provide a complete issued-for-construction package.","sourceIds":["s1"]},"cost":{"availability":"partial","summary":"The March 2013 USACE account identifies a $594 million rehabilitation project; this is programme scope, not the wall’s final unit-price account.","sourceIds":["s1"]},"schedule":{"availability":"partial","summary":"Last pile placement was reported on 6 March 2013, nine months ahead of the then-planned December completion.","sourceIds":["s1"]},"records":{"availability":"partial","summary":"USACE records barrier completion and the subsequent reservoir review.","sourceIds":["s1"]},"capstone":{"label":"Suggested capstone study","scope":"An original teaching brief based on the documented project. Study assumptions and student designs are separate from the built project.","brief":"Compare a cutoff wall and grouting strategy for an operating dam over soluble rock, including continuity verification and reservoir constraints.","inputs":["Extract the documented barrier dimensions and geological problem.","Define an explicitly sourced or assumed permeability model for the study seepage calculation."],"deliverables":["Develop a seepage/uplift comparison and a wall-continuity QA plan.","Prepare a construction platform section and a reservoir/instrumentation hold-point sequence.","A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.","A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points."],"questions":["Which site data control the decision, and what additional investigation would reduce uncertainty?","How would the proposed solution change under the stated sensitivity cases, construction constraints and performance limits?"],"output":"Design report, calculation workbook, concept drawings, quantity schedule and construction programme."},"sources":[{"id":"s1","title":"Nashville District completes Wolf Creek Dam barrier wall","url":"https://www.dvidshub.net/news/103103/nashville-district-completes-wolf-creek-dam-barrier-wall","publisher":"USACE / DVIDS","year":2013,"access":"public-link","license":"US government public information; original credits retained","notes":"","checked":"2026-11-22"},{"id":"s2","title":"Wolf Creek Dam barrier-wall construction — published image and source","url":"https://www.dvidshub.net/image/1965076/nashville-district-highlights-its-notable-projects-leading-into-national-dam-safety-awareness-day","publisher":"DVIDS / U.S. Army Corps of Engineers","year":2012,"access":"public-link","license":"Public domain — U.S. federal government work","notes":"Project image source. Unmodified bytes from the publisher’s 1000-pixel image; responsive display only.","checked":"2026-11-22","localAssetIds":["project-image"]}],"assets":[{"id":"schematic","title":"Conceptual study schematic","kind":"figure","fileName":"wolf-creek.svg","mimeType":"image/svg+xml","bytes":985,"sha256":"ee95ff57b022b53ff13f55beb263a60b849d824c45c609ed976e0810f3961f8b","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/wolf-creek/download/schematic"},{"id":"project-image","title":"Wolf Creek Dam barrier-wall construction","kind":"project-image","fileName":"wolf-creek.jpg","mimeType":"image/jpeg","bytes":360915,"sha256":"3b361e7407fd987273b67296a8243d56d96b8acaacef0a11a35bbbf016ef58cc","sourceId":"s2","license":"Public domain — U.S. federal government work","width":1000,"height":664,"credit":"Leon Roberts / U.S. Army Corps of Engineers","sourceUrl":"https://www.dvidshub.net/image/1965076/nashville-district-highlights-its-notable-projects-leading-into-national-dam-safety-awareness-day","licenseUrl":"https://www.dvidshub.net/about/copyright","imageDate":"2012-05-02","evidenceFile":"image-provenance/wolf-creek-source.json","evidenceSha256":"7c60540ea61fdb963e680eb0e27ef54375564f419bba957c0086c51479fca3e5","transformations":"Unmodified bytes from the publisher’s 1000-pixel image; responsive display only.","rightsBasis":"See the per-image provenance record and linked license; source hosting alone is not the rights basis.","downloadUrl":"/cases/wolf-creek/download/project-image"},{"id":"capstone-brief","title":"Capstone brief (Markdown)","kind":"brief","fileName":"wolf-creek-capstone.md","mimeType":"text/markdown","bytes":3149,"sha256":"a6a8f5863cc2de9de547b3be3d54e50e32e3a1475422a83b73f24b26ce485245","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/wolf-creek/download/capstone-brief"}],"figure":{"assetId":"project-image","kind":"photograph","alt":"Concrete barrier-wall construction in the Wolf Creek Dam embankment on May 2, 2012.","caption":"Concrete barrier-wall construction in the Wolf Creek Dam embankment on May 2, 2012. U.S. Army Corps of Engineers photograph by Leon Roberts.","credit":"Leon Roberts / U.S. Army Corps of Engineers","sourceUrl":"https://www.dvidshub.net/image/1965076/nashville-district-highlights-its-notable-projects-leading-into-national-dam-safety-awareness-day","license":"Public domain — U.S. federal government work","licenseUrl":"https://www.dvidshub.net/about/copyright","width":1000,"height":664,"imageDate":"2012-05-02"},"figureCaption":"Concrete barrier-wall construction in the Wolf Creek Dam embankment on May 2, 2012. U.S. Army Corps of Engineers photograph by Leon Roberts.","qualityNotes":[],"checked":"2026-11-22","curatedOrder":20,"referenceValues":[],"teachingFigureCaption":"Conceptual study schematic; not an as-built project drawing.","imageEvidence":{"status":"acquired","identityVerified":true,"evidenceFile":"image-provenance/wolf-creek-source.json","evidenceSha256":"7c60540ea61fdb963e680eb0e27ef54375564f419bba957c0086c51479fca3e5","visualReview":"Original image inspected at card scale and against its caption/source; no AI-created replacement.","checked":"2026-11-22"},"localReportCount":0,"downloadBytes":365049,"sourceCount":2,"url":"/cases/wolf-creek"},{"id":"center-hill","title":"Center Hill Dam — grouting, cutoff wall and stabilizing berm","summary":"A staged rehabilitation treated foundation seepage and auxiliary-dam risks using grouting, a deep cutoff wall and a roller-compacted-concrete berm.","topics":["dams-levees","seepage","rock","ground-improvement","delivery"],"country":"United States","region":"DeKalb County, Tennessee","owner":"US Army Corps of Engineers","year":2020,"yearLabel":"Case reference year","projectType":"Rehabilitation","methods":["Foundation grouting","Cutoff wall","Stabilizing berm"],"documentationLevel":"project-summary","design":{"availability":"partial","summary":"USACE describes three major repair phases and their completed components; detailed construction plans are not attached to the completion release.","sourceIds":["s1"]},"cost":{"availability":"partial","summary":"The completion release reports $353 million overall, with $107 million grouting, $122 million cutoff and $50 million berm contracts; scopes differ from the programme total.","sourceIds":["s1"]},"schedule":{"availability":"partial","summary":"Reported phases were grouting in 2008–2010, cutoff in 2012–2015 and final berm completion celebrated in July 2020.","sourceIds":["s1"]},"records":{"availability":"partial","summary":"The USACE release documents the final repair phase and constructed features.","sourceIds":["s1"]},"capstone":{"label":"Suggested capstone study","scope":"An original teaching brief based on the documented project. Study assumptions and student designs are separate from the built project.","brief":"Develop a risk-based sequence of dam repairs in which initial grouting also informs the later cutoff design.","inputs":["Extract phase scope, wall depth and published contract-period information.","Identify the piezometric and geological evidence needed to assess each repaired failure mode."],"deliverables":["Prepare a seepage/stability failure-mode map and an investigation-to-construction decision process.","Compare a single-stage programme with the documented phased strategy.","A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.","A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points."],"questions":["Which site data control the decision, and what additional investigation would reduce uncertainty?","How would the proposed solution change under the stated sensitivity cases, construction constraints and performance limits?"],"output":"Design report, calculation workbook, concept drawings, quantity schedule and construction programme."},"sources":[{"id":"s1","title":"Berm construction completes last repair phase for dam rehabilitation","url":"https://www.usace.army.mil/Media/News-Releases/News-Release-Article-View/Article/2261687/berm-construction-completes-last-repair-phase-for-dam-rehabilitation/","publisher":"USACE","year":2020,"access":"public-link","license":"USACE public information; original credits retained","notes":"","checked":"2026-11-22"},{"id":"s2","title":"Center Hill auxiliary-dam RCC berm — published image and source","url":"https://www.dvidshub.net/image/6260111/berm-construction-completes-last-repair-phase-dam-rehabilitation","publisher":"DVIDS / U.S. Army Corps of Engineers","year":2020,"access":"public-link","license":"Public domain — U.S. federal government work","notes":"Project image source. Unmodified bytes from the publisher’s 1000-pixel image; responsive display only.","checked":"2026-11-22","localAssetIds":["project-image"]}],"assets":[{"id":"schematic","title":"Conceptual study schematic","kind":"figure","fileName":"center-hill.svg","mimeType":"image/svg+xml","bytes":985,"sha256":"ee95ff57b022b53ff13f55beb263a60b849d824c45c609ed976e0810f3961f8b","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/center-hill/download/schematic"},{"id":"project-image","title":"Center Hill auxiliary-dam RCC berm","kind":"project-image","fileName":"center-hill.jpg","mimeType":"image/jpeg","bytes":293503,"sha256":"a0d33fc9f80d78aecd1af015fbcb8573ffccfdd3639abf05c4993f77dfefa73c","sourceId":"s2","license":"Public domain — U.S. federal government work","width":1000,"height":667,"credit":"Leon Roberts / U.S. Army Corps of Engineers","sourceUrl":"https://www.dvidshub.net/image/6260111/berm-construction-completes-last-repair-phase-dam-rehabilitation","licenseUrl":"https://www.dvidshub.net/about/copyright","imageDate":"2020","evidenceFile":"image-provenance/center-hill-source.json","evidenceSha256":"7491f54c4d276ee87d196bb5ab594f571734776ba54d95bb86336014027cecf1","transformations":"Unmodified bytes from the publisher’s 1000-pixel image; responsive display only.","rightsBasis":"See the per-image provenance record and linked license; source hosting alone is not the rights basis.","downloadUrl":"/cases/center-hill/download/project-image"},{"id":"capstone-brief","title":"Capstone brief (Markdown)","kind":"brief","fileName":"center-hill-capstone.md","mimeType":"text/markdown","bytes":3178,"sha256":"fd3962a5077f1d6636c34b684c2ab4f19da43c9623771422cb63d524eb0013d6","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/center-hill/download/capstone-brief"}],"figure":{"assetId":"project-image","kind":"photograph","alt":"The roller-compacted-concrete berm at the Center Hill auxiliary dam, shown in the USACE project-completion image collection published in July 2020..","caption":"The roller-compacted-concrete berm at the Center Hill auxiliary dam, shown in the USACE project-completion image collection published in July 2020.","credit":"Leon Roberts / U.S. Army Corps of Engineers","sourceUrl":"https://www.dvidshub.net/image/6260111/berm-construction-completes-last-repair-phase-dam-rehabilitation","license":"Public domain — U.S. federal government work","licenseUrl":"https://www.dvidshub.net/about/copyright","width":1000,"height":667,"imageDate":"2020"},"figureCaption":"The roller-compacted-concrete berm at the Center Hill auxiliary dam, shown in the USACE project-completion image collection published in July 2020.","qualityNotes":[],"checked":"2026-11-22","curatedOrder":21,"referenceValues":[],"teachingFigureCaption":"Conceptual study schematic; not an as-built project drawing.","imageEvidence":{"status":"acquired","identityVerified":true,"evidenceFile":"image-provenance/center-hill-source.json","evidenceSha256":"7491f54c4d276ee87d196bb5ab594f571734776ba54d95bb86336014027cecf1","visualReview":"Original image inspected at card scale and against its caption/source; no AI-created replacement.","checked":"2026-11-22"},"localReportCount":0,"downloadBytes":297666,"sourceCount":2,"url":"/cases/center-hill"},{"id":"folsom-spillway","title":"Folsom auxiliary spillway — rock excavation and foundation preparation","summary":"The auxiliary spillway required major rock excavation and preparation of the control-structure foundation before concrete placement.","topics":["rock","dams-levees","excavation","delivery"],"country":"United States","region":"Folsom, California","owner":"USACE / Bureau of Reclamation","year":2017,"yearLabel":"Case reference year","projectType":"Design and construction","methods":["Rock excavation","Foundation preparation","Controlled blasting"],"documentationLevel":"project-summary","design":{"availability":"partial","summary":"USACE construction accounts describe blasting completion, foundation cleaning and the subsequent control structure and chute.","sourceIds":["s1","s2"]},"cost":{"availability":"partial","summary":"USACE describes a $900 million cooperative effort, a programme total rather than a rock-excavation unit-rate schedule.","sourceIds":["s2"]},"schedule":{"availability":"partial","summary":"The source records initial excavation in 2008, final concrete stages in 2016 and the October 2017 completion ceremony.","sourceIds":["s2"]},"records":{"availability":"partial","summary":"The owner’s completion release identifies the constructed auxiliary spillway.","sourceIds":["s2"]},"capstone":{"label":"Suggested capstone study","scope":"An original teaching brief based on the documented project. Study assumptions and student designs are separate from the built project.","brief":"Plan a rock-foundation excavation and acceptance programme beside an operating dam and public transport route.","inputs":["Extract published construction stages and final structure dimensions.","Establish study discontinuity, groundwater and blast-vibration parameters explicitly."],"deliverables":["Prepare a temporary rock-slope/bench concept and foundation mapping checklist.","Design sequencing between blasting, cleaning, drainage, acceptance and concrete placement.","A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.","A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points."],"questions":["Which site data control the decision, and what additional investigation would reduce uncertainty?","How would the proposed solution change under the stated sensitivity cases, construction constraints and performance limits?"],"output":"Design report, calculation workbook, concept drawings, quantity schedule and construction programme."},"sources":[{"id":"s1","title":"Corps completes blasting for Folsom Dam spillway","url":"https://www.spk.usace.army.mil/Media/News-Stories/Article/479150/corps-completes-blasting-for-folsom-dam-spillway/","publisher":"USACE","year":2012,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s2","title":"Folsom auxiliary spillway completion ceremony","url":"https://www.spk.usace.army.mil/Media/News-Releases/Article/1347967/folsom-auxiliary-spillway-completion-ceremony-marks-conclusion-of-historic-proj/","publisher":"USACE","year":2017,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s3","title":"Corps completes final rock blasting for Folsom Dam spillway (7074960195).jpg — image and reuse license","url":"https://commons.wikimedia.org/wiki/File:Corps_completes_final_rock_blasting_for_Folsom_Dam_spillway_(7074960195).jpg","publisher":"Wikimedia Commons / U.S. Army Corps of Engineers Sacramento District","year":2012,"access":"public-link","license":"Public domain","notes":"Project image source. Unmodified image bytes from the publisher’s selected-size file; only responsive display sizing is applied by the website.","checked":"2026-11-22","localAssetIds":["project-image"]}],"assets":[{"id":"schematic","title":"Conceptual study schematic","kind":"figure","fileName":"folsom-spillway.svg","mimeType":"image/svg+xml","bytes":1017,"sha256":"ab086e9b878d71ca75443d4083022bf013c864b1ad5c4bbfbedf783b1ffc7360","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/folsom-spillway/download/schematic"},{"id":"project-image","title":"Corps completes final rock blasting for Folsom Dam spillway (7074960195).jpg","kind":"project-image","fileName":"folsom-spillway.jpg","mimeType":"image/jpeg","bytes":464701,"sha256":"7a19a74d7b3b5a33de9a62801a125a79786fab6e5e3741f2489f8163752e394c","sourceId":"s3","license":"Public domain","width":1280,"height":853,"credit":"U.S. Army Corps of Engineers Sacramento District","sourceUrl":"https://commons.wikimedia.org/wiki/File:Corps_completes_final_rock_blasting_for_Folsom_Dam_spillway_(7074960195).jpg","licenseUrl":"https://commons.wikimedia.org/wiki/File:Corps_completes_final_rock_blasting_for_Folsom_Dam_spillway_(7074960195).jpg#Licensing","imageDate":"2012-04-09 13:07","evidenceFile":"image-provenance/folsom-spillway-commons.json","evidenceSha256":"f8c58b1165831e3d43c019c6198f439b3999d2ca0dd921846e86483602a54411","transformations":"Unmodified image bytes from the publisher’s selected-size file; only responsive display sizing is applied by the website.","originalUrl":"https://upload.wikimedia.org/wikipedia/commons/a/a9/Corps_completes_final_rock_blasting_for_Folsom_Dam_spillway_%287074960195%29.jpg","downloadUrl":"/cases/folsom-spillway/download/project-image","rightsBasis":"See the per-image provenance record and linked license; source hosting alone is not the rights basis."},{"id":"capstone-brief","title":"Capstone brief (Markdown)","kind":"brief","fileName":"folsom-spillway-capstone.md","mimeType":"text/markdown","bytes":3360,"sha256":"9db574128d7dfcb79de13e692011843039bad04940c148f1a0128a63dc749079","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/folsom-spillway/download/capstone-brief"}],"figure":{"assetId":"project-image","kind":"photograph","alt":"Rock excavation for the Folsom Dam auxiliary spillway, April 2012.","caption":"Rock excavation for the Folsom Dam auxiliary spillway, April 2012. U.S. Army Corps of Engineers construction photograph.","credit":"U.S. Army Corps of Engineers Sacramento District","sourceUrl":"https://commons.wikimedia.org/wiki/File:Corps_completes_final_rock_blasting_for_Folsom_Dam_spillway_(7074960195).jpg","license":"Public domain","licenseUrl":"https://commons.wikimedia.org/wiki/File:Corps_completes_final_rock_blasting_for_Folsom_Dam_spillway_(7074960195).jpg#Licensing","width":1280,"height":853,"imageDate":"2012-04-09 13:07"},"figureCaption":"Rock excavation for the Folsom Dam auxiliary spillway, April 2012. U.S. Army Corps of Engineers construction photograph.","qualityNotes":[],"checked":"2026-11-22","curatedOrder":23,"referenceValues":[],"teachingFigureCaption":"Conceptual study schematic; not an as-built project drawing.","imageEvidence":{"status":"acquired","identityVerified":true,"evidenceFile":"image-provenance/folsom-spillway-commons.json","evidenceSha256":"f8c58b1165831e3d43c019c6198f439b3999d2ca0dd921846e86483602a54411","visualReview":"Original image inspected at card scale and against its caption/source; no AI-created replacement.","checked":"2026-11-22"},"localReportCount":0,"downloadBytes":469078,"sourceCount":3,"url":"/cases/folsom-spillway"},{"id":"oroville-spillways","title":"Oroville spillway recovery — erosion-resistant foundation reconstruction","summary":"Recovery rebuilt the main spillway and added a secant pile wall, splashpad and buttress at the emergency spillway after the 2017 incident.","topics":["rock","scour-erosion","dams-levees","seepage","delivery"],"country":"United States","region":"Oroville, California","owner":"California Department of Water Resources","year":2018,"yearLabel":"Case reference year","projectType":"Rehabilitation","methods":["Erosion control","Secant pile wall","Rock foundation drainage"],"documentationLevel":"technical-report","design":{"availability":"partial","summary":"DWR’s recovery page links investigations and describes the final-design reconstruction; the project update distinguishes initial mobilization from the completed design.","sourceIds":["s1","s2"]},"cost":{"availability":"partial","summary":"The September 2018 update estimated $940 million recovery through 2019, plus $160 million emergency response; these are dated estimates, not a final account.","sourceIds":["s2"]},"schedule":{"availability":"partial","summary":"Temporary main-spillway readiness was targeted for November 2017; final-design reconstruction was completed in 2018.","sourceIds":["s1","s2"]},"records":{"availability":"partial","summary":"DWR links consultant, inspection and forensic records from the recovery page.","sourceIds":["s1","s2"]},"capstone":{"label":"Suggested capstone study","scope":"An original teaching brief based on the documented project. Study assumptions and student designs are separate from the built project.","brief":"Develop an emergency-to-permanent reconstruction plan that addresses erosion, uplift and uncertain rock quality.","inputs":["Review the forensic findings and identify the selected failure mechanisms.","Extract the repair cross sections and distinguish temporary from permanent work."],"deliverables":["Prepare a foundation-drainage and erosion-protection concept with construction hold points.","Reconcile changing estimate scopes and show how geological uncertainty enters contingency.","A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.","A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points."],"questions":["Which site data control the decision, and what additional investigation would reduce uncertainty?","How would the proposed solution change under the stated sensitivity cases, construction constraints and performance limits?"],"output":"Design report, calculation workbook, concept drawings, quantity schedule and construction programme."},"sources":[{"id":"s1","title":"Oroville Spillways Recovery","url":"https://water.ca.gov/Programs/State-Water-Project/SWP-Facilities/Oroville/Oroville-Spillways","publisher":"California DWR","year":2018,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s2","title":"September 2018 construction and cost estimate update","url":"https://water.ca.gov/News/News-Releases/2018/Sept-18/Oroville-Spillways-Construction-and-Cost-Estimate-Update","publisher":"California DWR","year":2018,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s3","title":"Oroville Dam weir and emergency spillway erosion.jpg — image and reuse license","url":"https://commons.wikimedia.org/wiki/File:Oroville_Dam_weir_and_emergency_spillway_erosion.jpg","publisher":"Wikimedia Commons / California Department of Water Resources","year":2017,"access":"public-link","license":"Public domain","notes":"Project image source. Unmodified image bytes from the publisher’s selected-size file; only responsive display sizing is applied by the website.","checked":"2026-11-22","localAssetIds":["project-image"]}],"assets":[{"id":"schematic","title":"Conceptual study schematic","kind":"figure","fileName":"oroville-spillways.svg","mimeType":"image/svg+xml","bytes":1017,"sha256":"ab086e9b878d71ca75443d4083022bf013c864b1ad5c4bbfbedf783b1ffc7360","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/oroville-spillways/download/schematic"},{"id":"project-image","title":"Oroville Dam weir and emergency spillway erosion.jpg","kind":"project-image","fileName":"oroville-spillways.jpg","mimeType":"image/jpeg","bytes":320332,"sha256":"f4bd13af9ead3b5be6c9e4a05f99af18dd1c77f2fec0b5b3abc0cde34b401542","sourceId":"s3","license":"Public domain","width":1200,"height":900,"credit":"California Department of Water Resources","sourceUrl":"https://commons.wikimedia.org/wiki/File:Oroville_Dam_weir_and_emergency_spillway_erosion.jpg","licenseUrl":"https://commons.wikimedia.org/wiki/File:Oroville_Dam_weir_and_emergency_spillway_erosion.jpg#Licensing","imageDate":"2017-02-13","evidenceFile":"image-provenance/oroville-spillways-commons.json","evidenceSha256":"e0d98727520124a4f3f46bcb4cef896752cbd9e8edd6e0aa990b908411566689","transformations":"Unmodified image bytes from the publisher’s selected-size file; only responsive display sizing is applied by the website.","originalUrl":"https://upload.wikimedia.org/wikipedia/commons/b/bc/Oroville_Dam_weir_and_emergency_spillway_erosion.jpg","downloadUrl":"/cases/oroville-spillways/download/project-image","rightsBasis":"See the per-image provenance record and linked license; source hosting alone is not the rights basis."},{"id":"capstone-brief","title":"Capstone brief (Markdown)","kind":"brief","fileName":"oroville-spillways-capstone.md","mimeType":"text/markdown","bytes":3348,"sha256":"56fa6675b828b6b1cd30cec6dd7461afa664e2b2ba051586c8e6dce28299e59a","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/oroville-spillways/download/capstone-brief"}],"figure":{"assetId":"project-image","kind":"photograph","alt":"Oroville Dam’s emergency spillway and the erosion below its weir during the February 2017 spillway incident.","caption":"Oroville Dam’s emergency spillway and the erosion below its weir during the February 2017 spillway incident. California Department of Water Resources project photograph.","credit":"California Department of Water Resources","sourceUrl":"https://commons.wikimedia.org/wiki/File:Oroville_Dam_weir_and_emergency_spillway_erosion.jpg","license":"Public domain","licenseUrl":"https://commons.wikimedia.org/wiki/File:Oroville_Dam_weir_and_emergency_spillway_erosion.jpg#Licensing","width":1200,"height":900,"imageDate":"2017-02-13"},"figureCaption":"Oroville Dam’s emergency spillway and the erosion below its weir during the February 2017 spillway incident. California Department of Water Resources project photograph.","qualityNotes":[],"checked":"2026-11-22","curatedOrder":24,"referenceValues":[],"teachingFigureCaption":"Conceptual study schematic; not an as-built project drawing.","imageEvidence":{"status":"acquired","identityVerified":true,"evidenceFile":"image-provenance/oroville-spillways-commons.json","evidenceSha256":"e0d98727520124a4f3f46bcb4cef896752cbd9e8edd6e0aa990b908411566689","visualReview":"Original image inspected at card scale and against its caption/source; no AI-created replacement.","checked":"2026-11-22"},"localReportCount":0,"downloadBytes":324697,"sourceCount":3,"url":"/cases/oroville-spillways"},{"id":"teton-dam","title":"Teton Dam — internal erosion and first-filling investigation","summary":"The first-filling failure is documented through the Bureau of Reclamation’s history and the independent investigation report.","topics":["dams-levees","seepage","rock","site-investigation"],"country":"United States","region":"Eastern Idaho","owner":"US Bureau of Reclamation","year":1976,"yearLabel":"Case reference year","projectType":"Forensic investigation","methods":["Internal erosion","Filters and contacts","First-filling surveillance"],"documentationLevel":"investigation-report","design":{"availability":"partial","summary":"The official archive provides the original design/foundation investigation context and the 1976 failure report; the dam was not rebuilt.","sourceIds":["s1"]},"cost":{"availability":"not-found","summary":"A project-specific estimate, bid schedule or final account was not found in the reviewed sources.","sourceIds":[]},"schedule":{"availability":"partial","summary":"Failure occurred on 5 June 1976; the independent panel report was submitted in December 1976.","sourceIds":["s1"]},"records":{"availability":"partial","summary":"The official archive links the investigation and contemporary photographs; there is no completed replacement-dam record.","sourceIds":["s1"]},"capstone":{"label":"Suggested capstone study","scope":"An original teaching brief based on the documented project. Study assumptions and student designs are separate from the built project.","brief":"Evaluate alternative core/filter and foundation-treatment concepts using the investigation as a forensic reference, without treating a classroom redesign as an approved remedy.","inputs":["Extract foundation geology, core/filter arrangement and reservoir-filling observations.","Separate contemporary records from later interpretations of the failure mechanism."],"deliverables":["Prepare a potential-failure-mode analysis and a filtered-contact concept.","Design a first-filling monitoring and escalation plan.","A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.","A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points."],"questions":["Which site data control the decision, and what additional investigation would reduce uncertainty?","How would the proposed solution change under the stated sensitivity cases, construction constraints and performance limits?"],"output":"Design report, calculation workbook, concept drawings, quantity schedule and construction programme."},"sources":[{"id":"s1","title":"Teton Dam history and investigation archive","url":"https://www.usbr.gov/pn/snakeriver/dams/uppersnake/teton/","publisher":"Bureau of Reclamation","year":1976,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s2","title":"Breach of Teton Dam - DPLA - 657b673aa7b01ea982116a68bef069b4.jpg — image and reuse license","url":"https://commons.wikimedia.org/wiki/File:Breach_of_Teton_Dam_-_DPLA_-_657b673aa7b01ea982116a68bef069b4.jpg","publisher":"Wikimedia Commons / Department of the Interior. Bureau of Reclamation. Denver Office. 3/4/1988","year":1976,"access":"public-link","license":"Public domain","notes":"Project image source. Unmodified image bytes from the publisher’s selected-size file; only responsive display sizing is applied by the website.","checked":"2026-11-22","localAssetIds":["project-image"]}],"assets":[{"id":"schematic","title":"Conceptual study schematic","kind":"figure","fileName":"teton-dam.svg","mimeType":"image/svg+xml","bytes":985,"sha256":"ee95ff57b022b53ff13f55beb263a60b849d824c45c609ed976e0810f3961f8b","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/teton-dam/download/schematic"},{"id":"project-image","title":"Breach of Teton Dam - DPLA - 657b673aa7b01ea982116a68bef069b4.jpg","kind":"project-image","fileName":"teton-dam.jpg","mimeType":"image/jpeg","bytes":343519,"sha256":"ee45a14882d8e40ef7cdb8d2ece02d9b5374b2d05f99d4b1b102ea2a0eeda844","sourceId":"s2","license":"Public domain","width":1280,"height":1343,"credit":"U.S. Bureau of Reclamation / U.S. National Archives at Denver","sourceUrl":"https://commons.wikimedia.org/wiki/File:Breach_of_Teton_Dam_-_DPLA_-_657b673aa7b01ea982116a68bef069b4.jpg","licenseUrl":"https://commons.wikimedia.org/wiki/File:Breach_of_Teton_Dam_-_DPLA_-_657b673aa7b01ea982116a68bef069b4.jpg#Licensing","imageDate":"1976-06-05","evidenceFile":"image-provenance/teton-dam-commons.json","evidenceSha256":"37ed6c24f2101c2bca27da33b67333e9b1d6149cc3a7f12fc66d13eb389b47b9","transformations":"Unmodified image bytes from the publisher’s selected-size file; only responsive display sizing is applied by the website.","originalUrl":"https://upload.wikimedia.org/wikipedia/commons/0/0c/Breach_of_Teton_Dam_-_DPLA_-_657b673aa7b01ea982116a68bef069b4.jpg","downloadUrl":"/cases/teton-dam/download/project-image","rightsBasis":"See the per-image provenance record and linked license; source hosting alone is not the rights basis."},{"id":"capstone-brief","title":"Capstone brief (Markdown)","kind":"brief","fileName":"teton-dam-capstone.md","mimeType":"text/markdown","bytes":3122,"sha256":"b5d2ac5ede4ca9a488bd21b78156a925a2c65879cecce063d5ca5c2181a91114","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/teton-dam/download/capstone-brief"}],"figure":{"assetId":"project-image","kind":"photograph","alt":"The breach of Teton Dam, June 5, 1976.","caption":"The breach of Teton Dam, June 5, 1976. Historical project photograph from the U.S. Bureau of Reclamation collection.","credit":"U.S. Bureau of Reclamation / U.S. National Archives at Denver","sourceUrl":"https://commons.wikimedia.org/wiki/File:Breach_of_Teton_Dam_-_DPLA_-_657b673aa7b01ea982116a68bef069b4.jpg","license":"Public domain","licenseUrl":"https://commons.wikimedia.org/wiki/File:Breach_of_Teton_Dam_-_DPLA_-_657b673aa7b01ea982116a68bef069b4.jpg#Licensing","width":1280,"height":1343,"imageDate":"1976-06-05"},"figureCaption":"The breach of Teton Dam, June 5, 1976. Historical project photograph from the U.S. Bureau of Reclamation collection.","qualityNotes":["This is a failure-analysis case, not a successfully completed design example."],"checked":"2026-11-22","curatedOrder":25,"referenceValues":[],"teachingFigureCaption":"Conceptual study schematic; not an as-built project drawing.","imageEvidence":{"status":"acquired","identityVerified":true,"evidenceFile":"image-provenance/teton-dam-commons.json","evidenceSha256":"37ed6c24f2101c2bca27da33b67333e9b1d6149cc3a7f12fc66d13eb389b47b9","visualReview":"Original image inspected at card scale and against its caption/source; no AI-created replacement.","checked":"2026-11-22"},"localReportCount":0,"downloadBytes":347626,"sourceCount":2,"url":"/cases/teton-dam"},{"id":"grizzly-creek","title":"I-70 Grizzly Creek — post-fire rockfall risk and betterment","summary":"After the 2020 fire, CDOT compared rockfall mitigation using risk and benefit-cost analysis. Subsequent debris flows exceeded some installed protection capacities.","topics":["rock","slopes","scour-erosion","delivery"],"country":"United States","region":"Glenwood Canyon, Colorado","owner":"Colorado Department of Transportation","year":2021,"yearLabel":"Case reference year","projectType":"Rehabilitation","methods":["Rockfall protection","Risk-based selection","Benefit-cost analysis"],"documentationLevel":"technical-case","design":{"availability":"partial","summary":"The FHWA case documents selected fence treatments, cost assumptions and the importance of distinguishing routine rockfall from larger debris-flow events.","sourceIds":["s1"]},"cost":{"availability":"partial","summary":"The report lists a $2.692 million fence estimate and benefit-cost ratios for one- and five-year periods; other summary totals have different scopes.","sourceIds":["s1"]},"schedule":{"availability":"partial","summary":"Fences were installed in spring 2021; intense rainfall caused damaging debris flows in July 2021.","sourceIds":["s1"]},"records":{"availability":"partial","summary":"The case records both reduced minor-rockfall disruption and damage during larger subsequent events.","sourceIds":["s1"]},"capstone":{"label":"Suggested capstone study","scope":"An original teaching brief based on the documented project. Study assumptions and student designs are separate from the built project.","brief":"Select a rockfall-protection strategy under changing post-fire hazard and explicitly describe the residual risk from events beyond its capacity.","inputs":["Extract the source cost table, hazard categories and analysis periods.","Verify energy units and fence specifications against design documents before using them; the summary’s unit labels require confirmation."],"deliverables":["Recalculate the published benefit-cost comparison with transparent assumptions.","Develop a fence layout concept, inspection triggers and a response to debris-flow exceedance.","A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.","A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points."],"questions":["Which site data control the decision, and what additional investigation would reduce uncertainty?","How would the proposed solution change under the stated sensitivity cases, construction constraints and performance limits?"],"output":"Design report, calculation workbook, concept drawings, quantity schedule and construction programme."},"sources":[{"id":"s1","title":"FHWA-HIF-23-029 — reducing risk through rockfall mitigation","url":"https://www.fhwa.dot.gov/programadmin/er/er_case_colorado_grizzlycreek.pdf","publisher":"FHWA / CDOT","year":2023,"access":"public-link","license":"US federal agency case study; original credits retained","notes":"","checked":"2026-11-22","localAssetIds":["grizzly-creek-rockfall","project-image"]}],"assets":[{"id":"schematic","title":"Conceptual study schematic","kind":"figure","fileName":"grizzly-creek.svg","mimeType":"image/svg+xml","bytes":1017,"sha256":"ab086e9b878d71ca75443d4083022bf013c864b1ad5c4bbfbedf783b1ffc7360","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/grizzly-creek/download/schematic"},{"id":"grizzly-creek-rockfall","title":"FHWA-HIF-23-029, Grizzly Creek rockfall","kind":"report","fileName":"grizzly-creek-rockfall.pdf","mimeType":"application/pdf","bytes":719478,"sha256":"8051f0614203a8cb8749182bd5ffbe8c56bb3b094e9d4fdd341be3757026c733","sourceId":"s1","license":"US federal agency case study; original credits retained","rightsUrl":"https://www.fhwa.dot.gov/publications/research/general/15058/024.cfm","rightsBasis":"FHWA agency case publication; original agency photograph credits retained.","rightsEvidenceUrl":"https://www.fhwa.dot.gov/programadmin/er/","pages":3,"downloadUrl":"/cases/grizzly-creek/download/grizzly-creek-rockfall"},{"id":"project-image","title":"Grizzly Creek burn scar beside I-70 — FHWA Figure 1","kind":"project-image","fileName":"grizzly-creek.jpeg","mimeType":"image/jpeg","bytes":208925,"sha256":"6b408b3327d7bf2f33726e93280cc2b73c473ddac3ef901ef911ea3b9543c23b","sourceId":"s1","license":"Public domain — U.S. federal government work","width":1175,"height":661,"credit":"Federal Highway Administration (FHWA)","sourceUrl":"https://www.fhwa.dot.gov/programadmin/er/er_case_colorado_grizzlycreek.pdf","licenseUrl":"https://www.fhwa.dot.gov/publications/research/general/15058/024.cfm","imageDate":null,"evidenceFile":"image-provenance/grizzly-creek-source.json","evidenceSha256":"0e4132c03c8e5e5e14d66e6ac6d452de1ae48d1bc5c08bed5213881269447cf2","transformations":"Unchanged original embedded image extracted from the identified PDF; no new marks, labels, retouching, or crop.","rightsBasis":"See the per-image provenance record and linked license; source hosting alone is not the rights basis.","downloadUrl":"/cases/grizzly-creek/download/project-image"},{"id":"capstone-brief","title":"Capstone brief (Markdown)","kind":"brief","fileName":"grizzly-creek-capstone.md","mimeType":"text/markdown","bytes":2956,"sha256":"b5d9d9eff8777971cac43f025eb24699e0f66497d7e1e95007d6bb13ea3718f0","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/grizzly-creek/download/capstone-brief"}],"figure":{"assetId":"project-image","kind":"photograph","alt":"Burn scars from the Grizzly Creek fire above I-70 in Glenwood Canyon, Colorado.","caption":"Burn scars from the Grizzly Creek fire above I-70 in Glenwood Canyon, Colorado. FHWA photograph from its rockfall and debris-flow mitigation case study.","credit":"Federal Highway Administration (FHWA)","sourceUrl":"https://www.fhwa.dot.gov/programadmin/er/er_case_colorado_grizzlycreek.pdf","license":"Public domain — U.S. federal government work","licenseUrl":"https://www.fhwa.dot.gov/publications/research/general/15058/024.cfm","width":1175,"height":661,"imageDate":null},"figureCaption":"Burn scars from the Grizzly Creek fire above I-70 in Glenwood Canyon, Colorado. FHWA photograph from its rockfall and debris-flow mitigation case study.","qualityNotes":[],"checked":"2026-11-22","curatedOrder":29,"referenceValues":[],"teachingFigureCaption":"Conceptual study schematic; not an as-built project drawing.","imageEvidence":{"status":"acquired","identityVerified":true,"evidenceFile":"image-provenance/grizzly-creek-source.json","evidenceSha256":"0e4132c03c8e5e5e14d66e6ac6d452de1ae48d1bc5c08bed5213881269447cf2","visualReview":"Original image inspected at card scale and against its caption/source; no AI-created replacement.","checked":"2026-11-22"},"localReportCount":1,"downloadBytes":932376,"sourceCount":1,"url":"/cases/grizzly-creek"},{"id":"ocoee-us64","title":"US 64 Ocoee Gorge — emergency rockslide stabilization","summary":"Rockslides near Ocoee Dam 2 required rock removal, bolting and stabilization while weather and difficult access affected the reopening programme.","topics":["rock","slopes","retaining-walls","delivery"],"country":"United States","region":"Polk County, Tennessee","owner":"Tennessee Department of Transportation","year":2010,"yearLabel":"Case reference year","projectType":"Rehabilitation","methods":["Rock bolting","Scaling and controlled removal","Weather-constrained work"],"documentationLevel":"technical-case","design":{"availability":"partial","summary":"The owner update documents stabilization quantities and sequencing. The technical conference account describes geological failure mechanisms.","sourceIds":["s1","s2"]},"cost":{"availability":"not-found","summary":"A project-specific estimate, bid schedule or final account was not found in the reviewed sources.","sourceIds":[]},"schedule":{"availability":"partial","summary":"The March 2010 owner update revised the expected reopening date to April 16 after weather delays; this was a forecast at publication.","sourceIds":["s1","s2"]},"records":{"availability":"partial","summary":"Progress quantities and a technical case paper are linked; a final account was not found.","sourceIds":["s1","s2"]},"capstone":{"label":"Suggested capstone study","scope":"An original teaching brief based on the documented project. Study assumptions and student designs are separate from the built project.","brief":"Develop a temporary and permanent rock-slope repair plan with worker exclusion zones and weather allowances.","inputs":["Extract the documented failures, access limitations and installed treatment quantities.","Identify discontinuity mapping and block geometry required for a study design."],"deliverables":["Prepare a kinematic stability assessment and concept bolt/fence layout.","Build a weather-sensitive schedule and quantity-based estimate.","A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.","A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points."],"questions":["Which site data control the decision, and what additional investigation would reduce uncertainty?","How would the proposed solution change under the stated sensitivity cases, construction constraints and performance limits?"],"output":"Design report, calculation workbook, concept drawings, quantity schedule and construction programme."},"sources":[{"id":"s1","title":"US 64 to reopen April 16 — project update","url":"https://comptroller.extglb.tn.gov/news/2010/3/19/u.s.-64-to-reopen-april-16.html","publisher":"Tennessee DOT","year":2010,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s2","title":"Emergency rockslide mitigation in the Ocoee River Gorge","url":"https://www.researchgate.net/publication/335319508_Emergency_Rockslide_Mitigation_in_Eastern_Tennessee_US_64_Through_the_Ocoee_River_Gorge_2009-2010","publisher":"Jay Smerekanicz / project conference paper","year":2010,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s3","title":"US 64, Polk County, Tennessee — Emergency Rock Slope Stabilization in the Ocoee Gorge","url":"https://ashe.pro/documents/archives/scanner/2011-2.pdf","publisher":"American Society of Highway Engineers / TDOT project author","year":2009,"access":"public-link","license":"No open reuse license verified; original copyright retained","notes":"Project image source. Original embedded photograph extracted unchanged from the source PDF; no crop, added labels, or retouching.","checked":"2026-11-22","localAssetIds":["project-image"]}],"assets":[{"id":"schematic","title":"Conceptual study schematic","kind":"figure","fileName":"ocoee-us64.svg","mimeType":"image/svg+xml","bytes":1017,"sha256":"ab086e9b878d71ca75443d4083022bf013c864b1ad5c4bbfbedf783b1ffc7360","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/ocoee-us64/download/schematic"},{"id":"project-image","title":"US 64 Ocoee Gorge — rockslide stabilization site","kind":"project-image","fileName":"ocoee-us64-r13.jpeg","mimeType":"image/jpeg","bytes":170821,"sha256":"579ec113a100e26fc42fe511826fd4fcbad9af811273131115dc3a92a1c3dd55","sourceId":"s3","license":"No open reuse license verified; original copyright retained","width":542,"height":267,"credit":"Photograph published with Vanessa Bateman’s TDOT project article in ASHE SCANNER, Spring 2011","sourceUrl":"https://ashe.pro/documents/archives/scanner/2011-2.pdf","licenseUrl":"https://ashe.pro/documents/archives/scanner/2011-2.pdf","imageDate":"2009-11-20","evidenceFile":"image-provenance/ocoee-us64-r13-source.json","evidenceSha256":"bab1cbd782e3171d399080740ebd1e88dcb69f166a7781eb8ea937fb6af56334","transformations":"Original embedded photograph extracted unchanged from the source PDF; no crop, added labels, or retouching.","originalUrl":"https://ashe.pro/documents/archives/scanner/2011-2.pdf","originalSha256":"885dab5a39ccf863a025149d6649977f4694a858081971d527ec2be4babee623","imageDownloadAllowed":false,"rightsStatus":"editorial-reference","permissionStatus":"No open reuse permission verified","rightsNote":"Source-linked editorial reference; copyright remains with the original owner. The site does not offer this image as a reusable download.","imageUsage":"project-photograph","rightsBasis":"See the per-image provenance record and linked license; source hosting alone is not the rights basis.","previewUrl":"/cases/ocoee-us64/figure"},{"id":"capstone-brief","title":"Capstone brief (Markdown)","kind":"brief","fileName":"ocoee-us64-capstone.md","mimeType":"text/markdown","bytes":3238,"sha256":"8a31f23ebaecfdf9f45b2a3cef4498b5fdf7b17eb249476bed62871221313169","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/ocoee-us64/download/capstone-brief"}],"figure":{"assetId":"project-image","kind":"photograph","alt":"The Ocoee Gorge rockslide site on 20 November 2009, with the source author’s marked instability zones retained.","caption":"The Ocoee Gorge rockslide site on 20 November 2009, with the source author’s marked instability zones retained.","credit":"Photograph published with Vanessa Bateman’s TDOT project article in ASHE SCANNER, Spring 2011","sourceUrl":"https://ashe.pro/documents/archives/scanner/2011-2.pdf","license":"No open reuse license verified; original copyright retained","licenseUrl":"https://ashe.pro/documents/archives/scanner/2011-2.pdf","width":542,"height":267,"imageDate":"2009-11-20","preserveWholeImage":true,"imageDownloadAllowed":false,"rightsStatus":"editorial-reference","permissionStatus":"No open reuse permission verified","rightsNote":"Source-linked editorial reference; copyright remains with the original owner. The site does not offer this image as a reusable download.","imageUsage":"project-photograph"},"figureCaption":"The Ocoee Gorge rockslide site on 20 November 2009, with the source author’s marked instability zones retained.","qualityNotes":[],"checked":"2026-11-22","curatedOrder":30,"referenceValues":[],"teachingFigureCaption":"Conceptual study schematic; not an as-built project drawing.","imageEvidence":{"status":"acquired","identityVerified":true,"evidenceFile":"image-provenance/ocoee-us64-r13-source.json","evidenceSha256":"bab1cbd782e3171d399080740ebd1e88dcb69f166a7781eb8ea937fb6af56334","visualReview":"Viewed the complete original photograph and compared it with the identified project/source caption. No generated or unrelated replacement image.","checked":"2026-11-22"},"localReportCount":0,"downloadBytes":4255,"sourceCount":3,"url":"/cases/ocoee-us64"},{"id":"millau-viaduct","title":"Millau Viaduct — rock foundations and observational control","summary":"Very tall bridge piers transfer load through large shaft-and-raft foundations in limestone and marl. The geotechnical authors report measured foundation movement and the observational design strategy.","topics":["rock","deep-foundations","settlement","monitoring"],"country":"France","region":"Tarn Valley","owner":"Compagnie Eiffage du Viaduc de Millau","year":2004,"yearLabel":"Case reference year","projectType":"Design, construction and performance","methods":["Rock sockets","Foundation rotation","Observational method"],"documentationLevel":"technical-case","design":{"availability":"partial","summary":"An open research paper describes investigation, foundation geometry and monitoring. The consultant account distinguishes pier geology and a local abutment adaptation.","sourceIds":["s1","s2","s3"]},"cost":{"availability":"not-found","summary":"A project-specific estimate, bid schedule or final account was not found in the reviewed sources.","sourceIds":[]},"schedule":{"availability":"partial","summary":"Eiffage records construction during 2001–2004 and inauguration in December 2004; this is a milestone history, not the full contractor programme.","sourceIds":["s1","s2","s3"]},"records":{"availability":"partial","summary":"The geotechnical paper reports the monitored foundation behavior after construction.","sourceIds":["s1","s2","s3"]},"capstone":{"label":"Suggested capstone study","scope":"An original teaching brief based on the documented project. Study assumptions and student designs are separate from the built project.","brief":"Check a tall-pier foundation on contrasting rock units, with rotation limits governing the design.","inputs":["Extract published shaft, raft and rock-unit descriptions for one selected pier.","Separate measured translations from rotations and identify the construction stages."],"deliverables":["Compare bearing, sliding and rotational stiffness for limestone and marl assumptions.","Draft an instrumentation plan and pre-agreed foundation intervention sequence.","A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.","A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points."],"questions":["Why can small differential movements matter more than total bearing capacity for this bridge?","How should an unexpected weak zone change the verification and contingency plan?"],"output":"Design report, calculation workbook, concept drawings, quantity schedule and construction programme."},"sources":[{"id":"s1","title":"Millau viaduct geotechnical studies and foundations","url":"https://www.sciencedirect.com/science/article/pii/S167477551300036X","publisher":"Geotechnical project authors / Journal of Rock Mechanics and Geotechnical Engineering","year":null,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s2","title":"Foundation engineering project account","url":"https://www.terrasol.fr/wp-content/uploads/2017/12/oa07_845_millau_viaduct_eng.pdf","publisher":"Terrasol","year":null,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s3","title":"Construction milestones","url":"https://www.eiffagegeniecivil.com/milau-viaduct","publisher":"Eiffage Génie Civil","year":null,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s4","title":"Viaduc millau 1.JPG — image and reuse license","url":"https://commons.wikimedia.org/wiki/File:Viaduc_millau_1.JPG","publisher":"Wikimedia Commons / Emeraude","year":2004,"access":"public-link","license":"Public domain","notes":"Project image source. Unmodified publisher-generated display-size file; the original source URL and publisher metadata are retained. No AI-generated replacement or content alteration.","checked":"2026-11-22","localAssetIds":["project-image"]}],"assets":[{"id":"schematic","title":"Conceptual study schematic","kind":"figure","fileName":"millau-viaduct.svg","mimeType":"image/svg+xml","bytes":1017,"sha256":"ab086e9b878d71ca75443d4083022bf013c864b1ad5c4bbfbedf783b1ffc7360","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/millau-viaduct/download/schematic"},{"id":"project-image","title":"Viaduc millau 1.JPG","kind":"project-image","fileName":"millau-viaduct.jpg","mimeType":"image/jpeg","bytes":51310,"sha256":"9467ba872ccc50d998b9cc2bfb5188db5146d84c983f005b7d3b9847e693a6b9","sourceId":"s4","license":"Public domain","width":480,"height":640,"credit":"Emeraude","sourceUrl":"https://commons.wikimedia.org/wiki/File:Viaduc_millau_1.JPG","licenseUrl":"https://commons.wikimedia.org/wiki/File:Viaduc_millau_1.JPG#Licensing","imageDate":"2004-03-14","evidenceFile":"image-provenance/millau-viaduct-commons.json","evidenceSha256":"e7a265ad5c20e75ffa310179ed68178f1fb3cf4910a87d8e54fabfba3627795e","transformations":"Unmodified publisher-generated display-size file; the original source URL and publisher metadata are retained. No AI-generated replacement or content alteration.","originalUrl":"https://upload.wikimedia.org/wikipedia/commons/9/9c/Viaduc_millau_1.JPG","downloadUrl":"/cases/millau-viaduct/download/project-image","originalSha1":"cfe891bbedddcb693b57292d9abae9380c489b21","originalSha256":"9467ba872ccc50d998b9cc2bfb5188db5146d84c983f005b7d3b9847e693a6b9","imageDownloadAllowed":true,"rightsBasis":"See the per-image provenance record and linked license; source hosting alone is not the rights basis."},{"id":"capstone-brief","title":"Capstone brief (Markdown)","kind":"brief","fileName":"millau-viaduct-capstone.md","mimeType":"text/markdown","bytes":3222,"sha256":"694e38240fd87fccdac897252bff729b43efe470995f39c65b3c150cb2d6baca","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/millau-viaduct/download/capstone-brief"}],"figure":{"assetId":"project-image","kind":"photograph","alt":"The Millau Viaduct during construction.","caption":"The Millau Viaduct during construction. The tall piers and valley setting provide context for the published rock-foundation and monitoring case.","credit":"Emeraude","sourceUrl":"https://commons.wikimedia.org/wiki/File:Viaduc_millau_1.JPG","license":"Public domain","licenseUrl":"https://commons.wikimedia.org/wiki/File:Viaduc_millau_1.JPG#Licensing","width":480,"height":640,"imageDate":"2004-03-14","preserveWholeImage":true,"imageDownloadAllowed":true},"figureCaption":"The Millau Viaduct during construction. The tall piers and valley setting provide context for the published rock-foundation and monitoring case.","qualityNotes":[],"checked":"2026-11-22","addedIn":"r13","curatedOrder":52,"referenceValues":[],"teachingFigureCaption":"Conceptual study schematic; not an as-built project drawing.","imageEvidence":{"status":"acquired","identityVerified":true,"evidenceFile":"image-provenance/millau-viaduct-commons.json","evidenceSha256":"e7a265ad5c20e75ffa310179ed68178f1fb3cf4910a87d8e54fabfba3627795e","visualReview":"Viewed the complete publisher photograph in the final contact sheets or individually and compared it with the source identity, date, and caption. The caption distinguishes project context from the particular underground treatment or construction stage.","checked":"2026-11-22"},"localReportCount":0,"downloadBytes":55549,"sourceCount":4,"url":"/cases/millau-viaduct"},{"id":"san-vicente-dam","title":"San Vicente Dam raise — rock preparation and RCC interface","summary":"The existing concrete dam was raised using roller-compacted concrete. Owner documents connect excavation to competent rock, treatment of localized poor material and seepage control with the enlarged structure.","topics":["rock","dams-levees","seepage","excavation","delivery"],"country":"United States","region":"San Diego County, California","owner":"San Diego County Water Authority","year":2014,"yearLabel":"Case reference year","projectType":"Design, construction and performance","methods":["Rock excavation","Dental concrete","Consolidation grouting","RCC"],"documentationLevel":"technical-case","design":{"availability":"partial","summary":"The environmental design commitments describe proposed foundation measures; the completion account establishes the constructed dam raise. Detailed final foundation treatment records are not included.","sourceIds":["s1","s2"]},"cost":{"availability":"not-found","summary":"A project-specific estimate, bid schedule or final account was not found in the reviewed sources.","sourceIds":[]},"schedule":{"availability":"partial","summary":"The owner reports foundation preparation beginning in June 2009 and construction ending in June 2014.","sourceIds":["s1","s2"]},"records":{"availability":"not-found","summary":"Complete as-built drawings and acceptance records were not found in the reviewed sources.","sourceIds":[]},"capstone":{"label":"Suggested capstone study","scope":"An original teaching brief based on the documented project. Study assumptions and student designs are separate from the built project.","brief":"Plan foundation preparation and construction of an RCC enlargement beside an existing gravity dam.","inputs":["Extract the owner’s foundation-treatment commitments and construction milestones.","Identify rock defects, existing-dam support and old/new concrete interfaces needing detailed verification."],"deliverables":["Prepare excavation acceptance criteria, dental-concrete details and grout/drain layouts.","Check a representative enlarged section for sliding and uplift, with treatment effectiveness sensitivities.","A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.","A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points."],"questions":["How does excavating beside the original dam change temporary stability requirements?","Which field observations should decide whether a weak rock pocket is removed or treated?"],"output":"Design report, calculation workbook, concept drawings, quantity schedule and construction programme."},"sources":[{"id":"s1","title":"Geology and soils design commitments","url":"https://www.sdcwa.org/sites/default/files/files/environmental-docs/csp/Section%2003_08%2C%20Alt%201%20Geology%20%2008%2024%2007.pdf","publisher":"San Diego County Water Authority","year":null,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s2","title":"Completion of the dam raise","url":"https://www.sdcwa.org/historic-san-vicente-dam-raise-project-completed/","publisher":"San Diego County Water Authority","year":null,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s3","title":"Drone Photography San Vicente Reservoir and Dam San Diego.jpg — image and reuse license","url":"https://commons.wikimedia.org/wiki/File:Drone_Photography_San_Vicente_Reservoir_and_Dam_San_Diego.jpg","publisher":"Wikimedia Commons / Redideo","year":2024,"access":"public-link","license":"CC BY-SA 4.0","notes":"Project image source. Unmodified publisher-generated display-size file; the original source URL and publisher metadata are retained. No AI-generated replacement or content alteration.","checked":"2026-11-22","localAssetIds":["project-image"]}],"assets":[{"id":"schematic","title":"Conceptual study schematic","kind":"figure","fileName":"san-vicente-dam.svg","mimeType":"image/svg+xml","bytes":1017,"sha256":"ab086e9b878d71ca75443d4083022bf013c864b1ad5c4bbfbedf783b1ffc7360","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/san-vicente-dam/download/schematic"},{"id":"project-image","title":"Drone Photography San Vicente Reservoir and Dam San Diego.jpg","kind":"project-image","fileName":"san-vicente-dam.jpg","mimeType":"image/jpeg","bytes":169202,"sha256":"13b8f0c81856c9a03fefd07c981f6913f52c9e46eb2ba83a8706c2f6db0b55e2","sourceId":"s3","license":"CC BY-SA 4.0","width":1280,"height":715,"credit":"Redideo","sourceUrl":"https://commons.wikimedia.org/wiki/File:Drone_Photography_San_Vicente_Reservoir_and_Dam_San_Diego.jpg","licenseUrl":"https://creativecommons.org/licenses/by-sa/4.0","imageDate":"2024-04-21","evidenceFile":"image-provenance/san-vicente-dam-commons.json","evidenceSha256":"e1a6c813b0c557b0253bdb3b0e6764fe4402a1e58f2a6282e512b67dd9e29779","transformations":"Unmodified publisher-generated display-size file; the original source URL and publisher metadata are retained. No AI-generated replacement or content alteration.","originalUrl":"https://upload.wikimedia.org/wikipedia/commons/f/fd/Drone_Photography_San_Vicente_Reservoir_and_Dam_San_Diego.jpg","downloadUrl":"/cases/san-vicente-dam/download/project-image","originalSha1":"a17feb3503b42dbb142e24edfd3a3f2663af8f7b","imageDownloadAllowed":true,"rightsBasis":"See the per-image provenance record and linked license; source hosting alone is not the rights basis."},{"id":"capstone-brief","title":"Capstone brief (Markdown)","kind":"brief","fileName":"san-vicente-dam-capstone.md","mimeType":"text/markdown","bytes":3308,"sha256":"f5024109cac1cebbe29b76af2538e1c2ea9fba72955662e777a3a827ca7baefa","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/san-vicente-dam/download/capstone-brief"}],"figure":{"assetId":"project-image","kind":"photograph","alt":"Aerial view of the raised San Vicente Dam and reservoir in San Diego County.","caption":"Aerial view of the raised San Vicente Dam and reservoir in San Diego County. The photograph shows the actual completed dam, not a rendering of the proposed raise.","credit":"Redideo","sourceUrl":"https://commons.wikimedia.org/wiki/File:Drone_Photography_San_Vicente_Reservoir_and_Dam_San_Diego.jpg","license":"CC BY-SA 4.0","licenseUrl":"https://creativecommons.org/licenses/by-sa/4.0","width":1280,"height":715,"imageDate":"2024-04-21","imageDownloadAllowed":true},"figureCaption":"Aerial view of the raised San Vicente Dam and reservoir in San Diego County. The photograph shows the actual completed dam, not a rendering of the proposed raise.","qualityNotes":[],"checked":"2026-11-22","addedIn":"r13","curatedOrder":62,"referenceValues":[],"teachingFigureCaption":"Conceptual study schematic; not an as-built project drawing.","imageEvidence":{"status":"acquired","identityVerified":true,"evidenceFile":"image-provenance/san-vicente-dam-commons.json","evidenceSha256":"e1a6c813b0c557b0253bdb3b0e6764fe4402a1e58f2a6282e512b67dd9e29779","visualReview":"Viewed the complete publisher photograph in the final contact sheets or individually and compared it with the source identity, date, and caption. The caption distinguishes project context from the particular underground treatment or construction stage.","checked":"2026-11-22"},"localReportCount":0,"downloadBytes":173527,"sourceCount":3,"url":"/cases/san-vicente-dam"},{"id":"calaveras-dam","title":"Calaveras Dam replacement — seismic foundations and unexpected landslides","summary":"Replacement of a seismically vulnerable dam encountered an additional ancient landslide during abutment excavation. Public environmental and budget records document supplemental investigation, design revisions and delivery consequences.","topics":["dams-levees","seismic","slopes","rock","site-investigation","delivery"],"country":"United States","region":"Sunol Valley, California","owner":"San Francisco Public Utilities Commission","year":2019,"yearLabel":"Case reference year","projectType":"Design, construction and performance","methods":["Abutment excavation","Seismic embankment design","Landslide stabilization"],"documentationLevel":"technical-report","design":{"availability":"partial","summary":"The environmental addendum explains the left-abutment investigation and revised slope treatment. The consultant describes final-design responsibilities, while city oversight records track budget changes.","sourceIds":["s1","s2","s3"]},"cost":{"availability":"partial","summary":"The 2019 city analysis traces a budget change from $416 million to $823 million across successive revisions. These are programme budgets with multiple causes, not a foundation-only final account.","sourceIds":["s1","s2","s3"]},"schedule":{"availability":"not-found","summary":"A dated project programme was not found in the reviewed sources; develop a study schedule from the documented method.","sourceIds":[]},"records":{"availability":"not-found","summary":"Complete as-built drawings and acceptance records were not found in the reviewed sources.","sourceIds":[]},"capstone":{"label":"Suggested capstone study","scope":"An original teaching brief based on the documented project. Study assumptions and student designs are separate from the built project.","brief":"Revise a dam-abutment excavation after construction exposes an unrecognized landslide mass.","inputs":["Extract the mapped hazard, supplemental investigation and treatment objective from the addendum.","Separate original design assumptions, newly observed conditions and later access-road damage."],"deliverables":["Compare removal and retained-remnant stabilization with groundwater sensitivities.","Develop a revised excavation sequence, material handling plan and change-control estimate.","A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.","A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points."],"questions":["What observations would distinguish an ancient shear surface from ordinary weathered rock?","How should uncertainty in the residual landslide geometry affect contingency quantities?"],"output":"Design report, calculation workbook, concept drawings, quantity schedule and construction programme."},"sources":[{"id":"s1","title":"Environmental addendum after left-abutment discoveries","url":"https://sfplanning.s3.amazonaws.com/sfmea/2005.0161E_Adm1.pdf","publisher":"San Francisco Planning / SFPUC","year":null,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s2","title":"Final design and geotechnical investigations","url":"https://aecom.com/projects/calaveras-dam-replacement-project/","publisher":"AECOM","year":null,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s3","title":"2019 budget and legislative analysis","url":"https://sfgov.legistar.com/View.ashx?GUID=E44CE420-A2F2-4DE8-BA38-A16B402F5B23&ID=7102715&M=F","publisher":"San Francisco Budget and Legislative Analyst","year":null,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s4","title":"Aerial view of Calaveras Reservoir showing the reconstruction of the dam wall.JPG — image and reuse license","url":"https://commons.wikimedia.org/wiki/File:Aerial_view_of_Calaveras_Reservoir_showing_the_reconstruction_of_the_dam_wall.JPG","publisher":"Wikimedia Commons / Kyle Hawton","year":2015,"access":"public-link","license":"CC BY-SA 4.0","notes":"Project image source. Unmodified publisher-generated display-size file; the original source URL and publisher metadata are retained. No AI-generated replacement or content alteration.","checked":"2026-11-22","localAssetIds":["project-image"]}],"assets":[{"id":"schematic","title":"Conceptual study schematic","kind":"figure","fileName":"calaveras-dam.svg","mimeType":"image/svg+xml","bytes":985,"sha256":"ee95ff57b022b53ff13f55beb263a60b849d824c45c609ed976e0810f3961f8b","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/calaveras-dam/download/schematic"},{"id":"project-image","title":"Aerial view of Calaveras Reservoir showing the reconstruction of the dam wall.JPG","kind":"project-image","fileName":"calaveras-dam.jpg","mimeType":"image/jpeg","bytes":263048,"sha256":"4b2838d0f8faaf72aa29c476d993568f3533c88816ec281b3be550b2f7b06bba","sourceId":"s4","license":"CC BY-SA 4.0","width":1280,"height":720,"credit":"Kyle Hawton","sourceUrl":"https://commons.wikimedia.org/wiki/File:Aerial_view_of_Calaveras_Reservoir_showing_the_reconstruction_of_the_dam_wall.JPG","licenseUrl":"https://creativecommons.org/licenses/by-sa/4.0","imageDate":"2015-03-22 14:12:56","evidenceFile":"image-provenance/calaveras-dam-commons.json","evidenceSha256":"dfe8d170b97213af3fa3c4663da03310fe5fe662f0642aa16a8ccbb7d763b7b7","transformations":"Unmodified publisher-generated display-size file; the original source URL and publisher metadata are retained. No AI-generated replacement or content alteration.","originalUrl":"https://upload.wikimedia.org/wikipedia/commons/6/67/Aerial_view_of_Calaveras_Reservoir_showing_the_reconstruction_of_the_dam_wall.JPG","downloadUrl":"/cases/calaveras-dam/download/project-image","originalSha1":"3c6bd773968322a17452887f8c6e484af5dc8bf4","imageDownloadAllowed":true,"rightsBasis":"See the per-image provenance record and linked license; source hosting alone is not the rights basis."},{"id":"capstone-brief","title":"Capstone brief (Markdown)","kind":"brief","fileName":"calaveras-dam-capstone.md","mimeType":"text/markdown","bytes":3596,"sha256":"28570b7ef1084de40740abad204dfe5b3b1cf54b66164bb11fc8d3e016bd0939","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/calaveras-dam/download/capstone-brief"}],"figure":{"assetId":"project-image","kind":"photograph","alt":"Aerial view of Calaveras Reservoir during reconstruction of the dam.","caption":"Aerial view of Calaveras Reservoir during reconstruction of the dam. The image shows the actual replacement-project work area.","credit":"Kyle Hawton","sourceUrl":"https://commons.wikimedia.org/wiki/File:Aerial_view_of_Calaveras_Reservoir_showing_the_reconstruction_of_the_dam_wall.JPG","license":"CC BY-SA 4.0","licenseUrl":"https://creativecommons.org/licenses/by-sa/4.0","width":1280,"height":720,"imageDate":"2015-03-22 14:12:56","imageDownloadAllowed":true},"figureCaption":"Aerial view of Calaveras Reservoir during reconstruction of the dam. The image shows the actual replacement-project work area.","qualityNotes":[],"checked":"2026-11-22","addedIn":"r13","curatedOrder":63,"referenceValues":[],"teachingFigureCaption":"Conceptual study schematic; not an as-built project drawing.","imageEvidence":{"status":"acquired","identityVerified":true,"evidenceFile":"image-provenance/calaveras-dam-commons.json","evidenceSha256":"dfe8d170b97213af3fa3c4663da03310fe5fe662f0642aa16a8ccbb7d763b7b7","visualReview":"Viewed the complete publisher photograph in the final contact sheets or individually and compared it with the source identity, date, and caption. The caption distinguishes project context from the particular underground treatment or construction stage.","checked":"2026-11-22"},"localReportCount":0,"downloadBytes":267629,"sourceCount":4,"url":"/cases/calaveras-dam"},{"id":"isabella-dam","title":"Isabella Dam modifications — seismic, seepage and spillway risk","summary":"The main and auxiliary dams were modified to address combined seismic, seepage and flood-passage concerns. Owner records describe dam raises, downstream buttress work, filters, drainage and major spillway excavation.","topics":["dams-levees","seepage","seismic","rock","earthworks"],"country":"United States","region":"Kern County, California","owner":"US Army Corps of Engineers","year":2023,"yearLabel":"Case reference year","projectType":"Design, construction and performance","methods":["Embankment buttress","Filter compatibility","Rock excavation","Dam raise"],"documentationLevel":"technical-case","design":{"availability":"partial","summary":"USACE publishes the programme scope and completion milestones. A study should keep the different failure modes separate before combining their risk-reduction measures.","sourceIds":["s1","s2"]},"cost":{"availability":"partial","summary":"The owner identifies a $204 million Phase II construction contract awarded in 2017. This amount is contract scope, not the whole programme’s final cost.","sourceIds":["s1","s2"]},"schedule":{"availability":"partial","summary":"USACE reports substantial completion of the Phase II dam and spillway work in 2022; related facilities are separate phases.","sourceIds":["s1","s2"]},"records":{"availability":"partial","summary":"USACE documents a reduced dam-risk classification and lifting of operating restrictions in 2023.","sourceIds":["s1","s2"]},"capstone":{"label":"Suggested capstone study","scope":"An original teaching brief based on the documented project. Study assumptions and student designs are separate from the built project.","brief":"Develop a coordinated rehabilitation concept for an embankment dam with both seepage and seismic deficiencies.","inputs":["Extract the owner’s modification components and their targeted failure modes.","Build study sections for the embankment, filter/drain system and spillway excavation."],"deliverables":["Compare stability and seepage checks before and after buttressing and drainage improvements.","Sequence the work to preserve flood passage and define filter-placement quality controls.","A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.","A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points."],"questions":["Which risk remains if a dam raise is designed without checking seepage gradients?","How should rock excavation and embankment placement share temporary drainage and access?"],"output":"Design report, calculation workbook, concept drawings, quantity schedule and construction programme."},"sources":[{"id":"s1","title":"Isabella Dam safety modification project","url":"https://www.spk.usace.army.mil/Missions/Civil-Works/Isabella-Dam-Safety-Modification-Project/show/all/","publisher":"USACE Sacramento District","year":null,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s2","title":"Operating restrictions lifted after improvements","url":"https://www.spk.usace.army.mil/Media/News-Releases/Article/3465598/usace-lowers-isabella-dam-risk-rating-lifts-operating-restrictions/","publisher":"USACE Sacramento District","year":null,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s3","title":"Aerial view of the Isabella Dam Safety Modification Project.jpg — image and reuse license","url":"https://commons.wikimedia.org/wiki/File:Aerial_view_of_the_Isabella_Dam_Safety_Modification_Project.jpg","publisher":"Wikimedia Commons / U.S. Army Corps of Engineers, Sacramento District","year":2022,"access":"public-link","license":"Public domain","notes":"Project image source. Unmodified publisher-generated display-size file; the original source URL and publisher metadata are retained. No AI-generated replacement or content alteration.","checked":"2026-11-22","localAssetIds":["project-image"]}],"assets":[{"id":"schematic","title":"Conceptual study schematic","kind":"figure","fileName":"isabella-dam.svg","mimeType":"image/svg+xml","bytes":985,"sha256":"ee95ff57b022b53ff13f55beb263a60b849d824c45c609ed976e0810f3961f8b","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/isabella-dam/download/schematic"},{"id":"project-image","title":"Aerial view of the Isabella Dam Safety Modification Project.jpg","kind":"project-image","fileName":"isabella-dam.jpg","mimeType":"image/jpeg","bytes":575748,"sha256":"f66ddb737d1275d09742d361d46183bcf320b45382a1625ec3e4af5f0f9d5750","sourceId":"s3","license":"Public domain","width":1280,"height":960,"credit":"U.S. Army Corps of Engineers, Sacramento District","sourceUrl":"https://commons.wikimedia.org/wiki/File:Aerial_view_of_the_Isabella_Dam_Safety_Modification_Project.jpg","licenseUrl":"https://commons.wikimedia.org/wiki/File:Aerial_view_of_the_Isabella_Dam_Safety_Modification_Project.jpg#Licensing","imageDate":"2022-09-13 20:00:00","evidenceFile":"image-provenance/isabella-dam-commons.json","evidenceSha256":"585cadac20100e6a89c699ae881d201bb11fd0a8f347cfe93812aaa5a2d07c09","transformations":"Unmodified publisher-generated display-size file; the original source URL and publisher metadata are retained. No AI-generated replacement or content alteration.","originalUrl":"https://upload.wikimedia.org/wikipedia/commons/b/bd/Aerial_view_of_the_Isabella_Dam_Safety_Modification_Project.jpg","downloadUrl":"/cases/isabella-dam/download/project-image","originalSha1":"bb9ba911a669570736c2b7ca7f7f5b5e1079e431","imageDownloadAllowed":true,"rightsBasis":"See the per-image provenance record and linked license; source hosting alone is not the rights basis."},{"id":"capstone-brief","title":"Capstone brief (Markdown)","kind":"brief","fileName":"isabella-dam-capstone.md","mimeType":"text/markdown","bytes":3526,"sha256":"4abb6ee3c8ffc12bed66ea962c61321ddb882f4d54ec0ee44678422325316d28","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/isabella-dam/download/capstone-brief"}],"figure":{"assetId":"project-image","kind":"photograph","alt":"Aerial view of the Isabella Dam Safety Modification Project on 14 September 2022.","caption":"Aerial view of the Isabella Dam Safety Modification Project on 14 September 2022. USACE construction photograph of the actual dams and spillway works.","credit":"U.S. Army Corps of Engineers, Sacramento District","sourceUrl":"https://commons.wikimedia.org/wiki/File:Aerial_view_of_the_Isabella_Dam_Safety_Modification_Project.jpg","license":"Public domain","licenseUrl":"https://commons.wikimedia.org/wiki/File:Aerial_view_of_the_Isabella_Dam_Safety_Modification_Project.jpg#Licensing","width":1280,"height":960,"imageDate":"2022-09-13 20:00:00","imageDownloadAllowed":true},"figureCaption":"Aerial view of the Isabella Dam Safety Modification Project on 14 September 2022. USACE construction photograph of the actual dams and spillway works.","qualityNotes":[],"checked":"2026-11-22","addedIn":"r13","curatedOrder":64,"referenceValues":[],"teachingFigureCaption":"Conceptual study schematic; not an as-built project drawing.","imageEvidence":{"status":"acquired","identityVerified":true,"evidenceFile":"image-provenance/isabella-dam-commons.json","evidenceSha256":"585cadac20100e6a89c699ae881d201bb11fd0a8f347cfe93812aaa5a2d07c09","visualReview":"Viewed the complete publisher photograph in the final contact sheets or individually and compared it with the source identity, date, and caption. The caption distinguishes project context from the particular underground treatment or construction stage.","checked":"2026-11-22"},"localReportCount":0,"downloadBytes":580259,"sourceCount":3,"url":"/cases/isabella-dam"},{"id":"clearwater-dam","title":"Clearwater Dam — karst pretreatment and a hanging cutoff","summary":"A sinkhole prompted foundation exploration and grouting before construction of a deep seepage cutoff. The owner explains why treating solution-enlarged fractures was necessary for slurry-supported excavation.","topics":["dams-levees","seepage","rock","ground-improvement"],"country":"United States","region":"Wayne and Reynolds counties, Missouri","owner":"US Army Corps of Engineers","year":2011,"yearLabel":"Case reference year","projectType":"Design, construction and performance","methods":["Karst grouting","Hydromill cutoff","Slurry loss control"],"documentationLevel":"technical-case","design":{"availability":"partial","summary":"USACE’s rehabilitation account describes the grouting sequence, epikarst treatment and cutoff construction. Its forecast of later completion is retained as a forecast rather than a final-account statement.","sourceIds":["s1","s2"]},"cost":{"availability":"partial","summary":"The owner page forecast approximately $240 million for the overall rehabilitation. It is not presented here as a verified final account.","sourceIds":["s1","s2"]},"schedule":{"availability":"partial","summary":"USACE records placement of the final cutoff panel on 6 December 2011; the page’s remaining-work milestones were forecasts.","sourceIds":["s1","s2"]},"records":{"availability":"not-found","summary":"Complete as-built drawings and acceptance records were not found in the reviewed sources.","sourceIds":[]},"capstone":{"label":"Suggested capstone study","scope":"An original teaching brief based on the documented project. Study assumptions and student designs are separate from the built project.","brief":"Design a pretreatment and cutoff-wall sequence for a dam with connected karst features.","inputs":["Extract the reported seepage problem and the relationship between pretreatment and panel excavation.","Define a study range for rock permeability and connected-void sizes."],"deliverables":["Compare seepage paths around a hanging cutoff and through a locally defective panel.","Specify staged grouting, slurry-loss response and test-panel acceptance requirements.","A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.","A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points."],"questions":["Why can grouting be necessary even when a cutoff wall is the main permanent barrier?","How should treatment change when drilling loses circulation in a solution feature?"],"output":"Design report, calculation workbook, concept drawings, quantity schedule and construction programme."},"sources":[{"id":"s1","title":"Clearwater major rehabilitation","url":"https://www.swl.usace.army.mil/Missions/Civil-Works/Program-and-Project-Management/Clearwater-Major-Rehab/","publisher":"USACE Little Rock District","year":null,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s2","title":"Cutoff-wall construction account","url":"https://www.keller-na.com/projects/clearwater-lake-dam","publisher":"Keller","year":null,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22","localAssetIds":["project-image"]}],"assets":[{"id":"schematic","title":"Conceptual study schematic","kind":"figure","fileName":"clearwater-dam.svg","mimeType":"image/svg+xml","bytes":985,"sha256":"ee95ff57b022b53ff13f55beb263a60b849d824c45c609ed976e0810f3961f8b","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/clearwater-dam/download/schematic"},{"id":"project-image","title":"Clearwater Lake Dam — rehabilitation works in Missouri","kind":"project-image","fileName":"clearwater-dam-r13.jpg","mimeType":"image/jpeg","bytes":157363,"sha256":"6ba4f3f9f46427acca852befd6cbcf86ed02208a0029c7b3d592a2bc62707bea","sourceId":"s2","license":"No open reuse license verified; original copyright retained","width":900,"height":561,"credit":"Keller / Keller Management Services, LLC","sourceUrl":"https://www.keller-na.com/projects/clearwater-lake-dam","licenseUrl":"https://www.keller-na.com/projects/clearwater-lake-dam","imageDate":null,"evidenceFile":"image-provenance/clearwater-dam-r13-source.json","evidenceSha256":"c4e83124dafe5ca3ef277b3db6f7ac973e45d1e9d7dd7b6067175829993234e6","transformations":"Resized the full 2500 × 1559 source photograph proportionally to 900 × 561 pixels, JPEG quality 90; no cropping, added labels, or retouching.","originalUrl":"https://www.keller-na.com/sites/keller-na/files/2019-11/Clearwater-Lake-Dam-aerial.jpg","originalSha256":"a42680ec532691b4140cd8daf9878188de455cc941f6b4b7c9dd8eb695ee1575","imageDownloadAllowed":false,"rightsStatus":"editorial-reference","permissionStatus":"No open reuse permission verified","rightsNote":"Source-linked editorial reference; copyright remains with the original owner. The site does not offer this image as a reusable download.","imageUsage":"project-photograph","rightsBasis":"See the per-image provenance record and linked license; source hosting alone is not the rights basis.","previewUrl":"/cases/clearwater-dam/figure"},{"id":"capstone-brief","title":"Capstone brief (Markdown)","kind":"brief","fileName":"clearwater-dam-capstone.md","mimeType":"text/markdown","bytes":3059,"sha256":"784e54f18432f07f72ef06f300e14058dcca60705b6602c74041dc9056c09cb9","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/clearwater-dam/download/capstone-brief"}],"figure":{"assetId":"project-image","kind":"photograph","alt":"Aerial view of construction equipment along the crest of Clearwater Lake Dam in Missouri.","caption":"Aerial view of Clearwater Lake Dam in Missouri during the rehabilitation works, from Keller’s project account. The photograph shows construction along the dam crest.","credit":"Keller / Keller Management Services, LLC","sourceUrl":"https://www.keller-na.com/projects/clearwater-lake-dam","license":"No open reuse license verified; original copyright retained","licenseUrl":"https://www.keller-na.com/projects/clearwater-lake-dam","width":900,"height":561,"imageDate":null,"preserveWholeImage":true,"imageDownloadAllowed":false,"rightsStatus":"editorial-reference","permissionStatus":"No open reuse permission verified","rightsNote":"Source-linked editorial reference; copyright remains with the original owner. The site does not offer this image as a reusable download.","imageUsage":"project-photograph"},"figureCaption":"Aerial view of Clearwater Lake Dam in Missouri during the rehabilitation works, from Keller’s project account. The photograph shows construction along the dam crest.","qualityNotes":[],"checked":"2026-11-22","addedIn":"r13","curatedOrder":66,"referenceValues":[],"teachingFigureCaption":"Conceptual study schematic; not an as-built project drawing.","imageEvidence":{"status":"acquired","identityVerified":true,"evidenceFile":"image-provenance/clearwater-dam-r13-source.json","evidenceSha256":"c4e83124dafe5ca3ef277b3db6f7ac973e45d1e9d7dd7b6067175829993234e6","visualReview":"Inspected the full uncropped photograph and its 900 pixel derivative. It shows a reservoir, the Missouri dam embankment, and construction equipment on the crest. No embedded credit or other edge content was removed.","checked":"2026-11-22"},"localReportCount":0,"downloadBytes":4044,"sourceCount":2,"url":"/cases/clearwater-dam"},{"id":"bluestone-dam","title":"Bluestone Dam — rock anchors and spillway-foundation protection","summary":"The safety programme combines anchoring, drainage and armor over the bedrock stilling basin. Construction must be staged while the spillway remains an active river-release route.","topics":["dams-levees","rock","scour-erosion","dewatering","delivery"],"country":"United States","region":"Hinton, West Virginia","owner":"US Army Corps of Engineers","year":2026,"yearLabel":"Case reference year","projectType":"Design, construction and performance","methods":["Rock anchors","Uplift drainage","Stilling-basin armor","Cofferdams"],"documentationLevel":"technical-case","design":{"availability":"partial","summary":"USACE describes completed earlier phases and the ongoing stilling-basin work. The project is not labeled fully complete; the owner’s 2026 programme forecasts completion in 2030.","sourceIds":["s1","s2"]},"cost":{"availability":"partial","summary":"The 2020 notice identifies a $319.6 million Phase 5 contract. It is not a final cost for all phases.","sourceIds":["s1","s2"]},"schedule":{"availability":"partial","summary":"The 2026 owner update reports one half complete and forecasts overall completion in 2030; this supersedes the older 2020 contract forecast.","sourceIds":["s1","s2"]},"records":{"availability":"not-found","summary":"Complete as-built drawings and acceptance records were not found in the reviewed sources.","sourceIds":[]},"capstone":{"label":"Suggested capstone study","scope":"An original teaching brief based on the documented project. Study assumptions and student designs are separate from the built project.","brief":"Stage foundation anchoring and armor placement in half of an operating stilling basin.","inputs":["Extract the owner’s phase boundaries, diversion concept and uplift-control components.","Define a study flood window and rock discontinuity model for temporary and permanent checks."],"deliverables":["Check anchor demand and drain effectiveness for intact and blocked-drain scenarios.","Prepare a cofferdam sequence and flood-response plan with excavation hold points.","A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.","A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points."],"questions":["How does temporary river diversion alter uplift beneath the work area?","Which inspection or proof-test result should delay concreting over an anchor zone?"],"output":"Design report, calculation workbook, concept drawings, quantity schedule and construction programme."},"sources":[{"id":"s1","title":"Safety assurance project and 2026 progress","url":"https://www.lrd.usace.army.mil/Missions/Projects/Article/3631104/bluestone-dam-dam-safety-assurance-mega-project/","publisher":"USACE Great Lakes and Ohio River Division","year":null,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s2","title":"Phase 5 contract milestone","url":"https://www.usace.army.mil/Media/News/Article/2126116/bluestone-pdt-achieves-milestone/","publisher":"USACE","year":null,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s3","title":"Bluestone Dam 2022a.jpg — image and reuse license","url":"https://commons.wikimedia.org/wiki/File:Bluestone_Dam_2022a.jpg","publisher":"Wikimedia Commons / Antony-22","year":2022,"access":"public-link","license":"CC BY-SA 4.0","notes":"Project image source. Unmodified publisher-generated display-size file; the original source URL and publisher metadata are retained. No AI-generated replacement or content alteration.","checked":"2026-11-22","localAssetIds":["project-image"]}],"assets":[{"id":"schematic","title":"Conceptual study schematic","kind":"figure","fileName":"bluestone-dam.svg","mimeType":"image/svg+xml","bytes":985,"sha256":"ee95ff57b022b53ff13f55beb263a60b849d824c45c609ed976e0810f3961f8b","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/bluestone-dam/download/schematic"},{"id":"project-image","title":"Bluestone Dam 2022a.jpg","kind":"project-image","fileName":"bluestone-dam.jpg","mimeType":"image/jpeg","bytes":346957,"sha256":"1956f06dd42d585fa5868ce36388d01e769be3f4e1558d874872a4fa7143082e","sourceId":"s3","license":"CC BY-SA 4.0","width":1280,"height":853,"credit":"Antony-22","sourceUrl":"https://commons.wikimedia.org/wiki/File:Bluestone_Dam_2022a.jpg","licenseUrl":"https://creativecommons.org/licenses/by-sa/4.0","imageDate":"2022-04-02 13:13:58","evidenceFile":"image-provenance/bluestone-dam-commons.json","evidenceSha256":"55a381e13ba93c79b945faaf64fc9910ada6981407ff3b529abc3e1d4a12faa5","transformations":"Unmodified publisher-generated display-size file; the original source URL and publisher metadata are retained. No AI-generated replacement or content alteration.","originalUrl":"https://upload.wikimedia.org/wikipedia/commons/9/90/Bluestone_Dam_2022a.jpg","downloadUrl":"/cases/bluestone-dam/download/project-image","originalSha1":"7a54bc8e6d12bb134ada88de7744b4def9c86426","imageDownloadAllowed":true,"rightsBasis":"See the per-image provenance record and linked license; source hosting alone is not the rights basis."},{"id":"capstone-brief","title":"Capstone brief (Markdown)","kind":"brief","fileName":"bluestone-dam-capstone.md","mimeType":"text/markdown","bytes":3056,"sha256":"db4860c066a5468d0b6af254a88a791ef3657652ddccc228ec5e7352a5e98892","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/bluestone-dam/download/capstone-brief"}],"figure":{"assetId":"project-image","kind":"photograph","alt":"Bluestone Dam in 2022, showing work in the spillway area.","caption":"Bluestone Dam in 2022, showing work in the spillway area. The photograph corresponds to the ongoing dam-safety programme.","credit":"Antony-22","sourceUrl":"https://commons.wikimedia.org/wiki/File:Bluestone_Dam_2022a.jpg","license":"CC BY-SA 4.0","licenseUrl":"https://creativecommons.org/licenses/by-sa/4.0","width":1280,"height":853,"imageDate":"2022-04-02 13:13:58","imageDownloadAllowed":true},"figureCaption":"Bluestone Dam in 2022, showing work in the spillway area. The photograph corresponds to the ongoing dam-safety programme.","qualityNotes":[],"checked":"2026-11-22","addedIn":"r13","curatedOrder":67,"referenceValues":[],"teachingFigureCaption":"Conceptual study schematic; not an as-built project drawing.","imageEvidence":{"status":"acquired","identityVerified":true,"evidenceFile":"image-provenance/bluestone-dam-commons.json","evidenceSha256":"55a381e13ba93c79b945faaf64fc9910ada6981407ff3b529abc3e1d4a12faa5","visualReview":"Viewed the complete publisher photograph in the final contact sheets or individually and compared it with the source identity, date, and caption. The caption distinguishes project context from the particular underground treatment or construction stage.","checked":"2026-11-22"},"localReportCount":0,"downloadBytes":350998,"sourceCount":3,"url":"/cases/bluestone-dam"},{"id":"mosul-dam","title":"Mosul Dam — maintenance grouting in soluble foundations","summary":"The dam overlies soluble limestone and gypsum. A rehabilitation programme strengthened maintenance grouting, equipment and instrumentation; continuing operation depends on sustained foundation management.","topics":["dams-levees","seepage","rock","monitoring","delivery"],"country":"Iraq","region":"Tigris River, northern Iraq","owner":"Iraq Ministry of Water Resources","year":2019,"yearLabel":"Case reference year","projectType":"Design, construction and performance","methods":["Maintenance grouting","Karst dissolution","Instrumented surveillance"],"documentationLevel":"technical-case","design":{"availability":"partial","summary":"USACE’s project history explains the grouting-gallery purpose and the 2016–2019 rehabilitation. It does not portray dissolution as permanently eliminated.","sourceIds":["s1"]},"cost":{"availability":"not-found","summary":"A project-specific estimate, bid schedule or final account was not found in the reviewed sources.","sourceIds":[]},"schedule":{"availability":"partial","summary":"The history documents the 2016–2019 task force; operation and maintenance remained the responsibility of Iraq’s Ministry of Water Resources.","sourceIds":["s1"]},"records":{"availability":"partial","summary":"The source records equipment, workforce and instrumentation improvements, with continued grouting required.","sourceIds":["s1"]},"capstone":{"label":"Suggested capstone study","scope":"An original teaching brief based on the documented project. Study assumptions and student designs are separate from the built project.","brief":"Develop an operations-linked grouting and surveillance plan for a dam on a dissolving foundation.","inputs":["Identify the soluble strata, access-gallery function and monitoring system described by the project team.","Define study groundwater chemistry and hydraulic gradients, marking them as assumptions where unpublished."],"deliverables":["Compare targeted and blanket grouting using permeability and grout-take scenarios.","Create inspection, drilling, instrumentation and response schedules that remain workable during outages.","A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.","A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points."],"questions":["Why is completion of a rehabilitation contract different from ending maintenance grouting?","How can changing grout take indicate either successful closure or a new flow path?"],"output":"Design report, calculation workbook, concept drawings, quantity schedule and construction programme."},"sources":[{"id":"s1","title":"Mosul Dam Task Force project history","url":"https://www.tad.usace.army.mil/About/History/","publisher":"USACE Transatlantic Division","year":null,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s2","title":"Mosul Dam seepage.jpg — image and reuse license","url":"https://commons.wikimedia.org/wiki/File:Mosul_Dam_seepage.jpg","publisher":"Wikimedia Commons / This image or file is a work of a U.S. Army Corps of Engineers soldier or employee, taken or made as part of that person's official duties. As a work of the U.S. federal government , the image is in the public domain .","year":2007,"access":"public-link","license":"Public domain","notes":"Project image source. Unmodified publisher-generated display-size file; the original source URL and publisher metadata are retained. No AI-generated replacement or content alteration.","checked":"2026-11-22","localAssetIds":["project-image"]}],"assets":[{"id":"schematic","title":"Conceptual study schematic","kind":"figure","fileName":"mosul-dam.svg","mimeType":"image/svg+xml","bytes":985,"sha256":"ee95ff57b022b53ff13f55beb263a60b849d824c45c609ed976e0810f3961f8b","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/mosul-dam/download/schematic"},{"id":"project-image","title":"Mosul Dam seepage.jpg","kind":"project-image","fileName":"mosul-dam.jpg","mimeType":"image/jpeg","bytes":36400,"sha256":"5ed3cd442242ea44ce7714f6406861853e493e1e3c9f7ff7bfd283766ce3331c","sourceId":"s2","license":"Public domain","width":652,"height":390,"credit":"This image or file is a work of a U.S. Army Corps of Engineers soldier or employee, taken or made as part of that person's official duties. As a work of the U.S. federal government , the image is in the public domain .","sourceUrl":"https://commons.wikimedia.org/wiki/File:Mosul_Dam_seepage.jpg","licenseUrl":"https://commons.wikimedia.org/wiki/File:Mosul_Dam_seepage.jpg#Licensing","imageDate":"2007","evidenceFile":"image-provenance/mosul-dam-commons.json","evidenceSha256":"24cc7f7e6d87e0313bf07045244006791851a33a996e3b1856e722d1eb96c160","transformations":"Unmodified publisher-generated display-size file; the original source URL and publisher metadata are retained. No AI-generated replacement or content alteration.","originalUrl":"https://upload.wikimedia.org/wikipedia/commons/e/ef/Mosul_Dam_seepage.jpg","downloadUrl":"/cases/mosul-dam/download/project-image","originalSha1":"aa0bd6259fd94c99184966d5b6f57b00092cb239","originalSha256":"5ed3cd442242ea44ce7714f6406861853e493e1e3c9f7ff7bfd283766ce3331c","imageDownloadAllowed":true,"rightsBasis":"See the per-image provenance record and linked license; source hosting alone is not the rights basis."},{"id":"capstone-brief","title":"Capstone brief (Markdown)","kind":"brief","fileName":"mosul-dam-capstone.md","mimeType":"text/markdown","bytes":3389,"sha256":"d6549148f14ee3077870d6d17abbffd5fefc264b92192bbca050323f1979172b","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/mosul-dam/download/capstone-brief"}],"figure":{"assetId":"project-image","kind":"photograph","alt":"Seepage east of and below the Mosul Dam spillway.","caption":"Seepage east of and below the Mosul Dam spillway. The source photograph documents the actual dam setting relevant to the foundation-management case.","credit":"This image or file is a work of a U.S. Army Corps of Engineers soldier or employee, taken or made as part of that person's official duties. As a work of the U.S. federal government , the image is in the public domain .","sourceUrl":"https://commons.wikimedia.org/wiki/File:Mosul_Dam_seepage.jpg","license":"Public domain","licenseUrl":"https://commons.wikimedia.org/wiki/File:Mosul_Dam_seepage.jpg#Licensing","width":652,"height":390,"imageDate":"2007","imageDownloadAllowed":true},"figureCaption":"Seepage east of and below the Mosul Dam spillway. The source photograph documents the actual dam setting relevant to the foundation-management case.","qualityNotes":[],"checked":"2026-11-22","addedIn":"r13","curatedOrder":68,"referenceValues":[],"teachingFigureCaption":"Conceptual study schematic; not an as-built project drawing.","imageEvidence":{"status":"acquired","identityVerified":true,"evidenceFile":"image-provenance/mosul-dam-commons.json","evidenceSha256":"24cc7f7e6d87e0313bf07045244006791851a33a996e3b1856e722d1eb96c160","visualReview":"Viewed the complete publisher photograph in the final contact sheets or individually and compared it with the source identity, date, and caption. The caption distinguishes project context from the particular underground treatment or construction stage.","checked":"2026-11-22"},"localReportCount":0,"downloadBytes":40774,"sourceCount":2,"url":"/cases/mosul-dam"},{"id":"hoover-dam","title":"Hoover Dam — rock-foundation preparation and remedial grouting","summary":"Construction removed river deposits to competent rock and treated the foundation and abutments. Later drainage and remedial grouting addressed uplift and leakage observed during initial reservoir filling.","topics":["rock","dams-levees","seepage","excavation","delivery"],"country":"United States","region":"Colorado River, Nevada–Arizona","owner":"US Bureau of Reclamation","year":1947,"yearLabel":"Case reference year","projectType":"Design, construction and performance","methods":["Rock excavation","Grout curtain","Drainage galleries","Uplift"],"documentationLevel":"technical-report","design":{"availability":"partial","summary":"Reclamation’s construction history and foundation-grouting standard explain original preparation and the later remedial programme. Concrete contraction-joint grouting must not be confused with rock-foundation grouting.","sourceIds":["s1","s2"]},"cost":{"availability":"not-found","summary":"A project-specific estimate, bid schedule or final account was not found in the reviewed sources.","sourceIds":[]},"schedule":{"availability":"not-found","summary":"A dated project programme was not found in the reviewed sources; develop a study schedule from the documented method.","sourceIds":[]},"records":{"availability":"partial","summary":"The design standard records effectiveness of remedial work and later observations; it is not a present-day dam-safety evaluation.","sourceIds":["s1","s2"]},"capstone":{"label":"Suggested capstone study","scope":"An original teaching brief based on the documented project. Study assumptions and student designs are separate from the built project.","brief":"Reassess foundation seepage after reservoir filling reveals pressures above the original design expectation.","inputs":["Separate original grout holes, later remedial work and concrete-joint treatment in the source record.","Extract the reported rationale for changed grout mixes and additional drainage."],"deliverables":["Calculate uplift distributions for alternative drain and curtain effectiveness assumptions.","Design a trial grouting plan with staged pressure limits and monitoring of adjacent drainage.","A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.","A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points."],"questions":["Why might a deeper curtain and additional drains be complementary rather than competing remedies?","What observations would show that apparent grout refusal is caused by premature setting?"],"output":"Design report, calculation workbook, concept drawings, quantity schedule and construction programme."},"sources":[{"id":"s1","title":"Hoover Dam construction history","url":"https://www.usbr.gov/history/hoover.html","publisher":"US Bureau of Reclamation","year":null,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s2","title":"Foundation grouting design standard, Hoover case","url":"https://www.usbr.gov/tsc/techreferences/designstandards-datacollectionguides/finalds-pdfs/DS13-15.pdf","publisher":"US Bureau of Reclamation","year":null,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s3","title":"Hoover Dam, Nevada (Arizona-Nevada, USA) -- 2012 -- 6099.jpg — image and reuse license","url":"https://commons.wikimedia.org/wiki/File:Hoover_Dam,_Nevada_(Arizona-Nevada,_USA)_--_2012_--_6099.jpg","publisher":"Wikimedia Commons / Dietmar Rabich","year":null,"access":"public-link","license":"CC BY-SA 4.0","notes":"Project image source. Unmodified publisher-generated display-size file; the original source URL and publisher metadata are retained. No AI-generated replacement or content alteration.","checked":"2026-11-22","localAssetIds":["project-image"]}],"assets":[{"id":"schematic","title":"Conceptual study schematic","kind":"figure","fileName":"hoover-dam.svg","mimeType":"image/svg+xml","bytes":1017,"sha256":"ab086e9b878d71ca75443d4083022bf013c864b1ad5c4bbfbedf783b1ffc7360","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/hoover-dam/download/schematic"},{"id":"project-image","title":"Hoover Dam, Nevada (Arizona-Nevada, USA) -- 2012 -- 6099.jpg","kind":"project-image","fileName":"hoover-dam.jpg","mimeType":"image/jpeg","bytes":465705,"sha256":"85015660314ac149a4557cb3f98fe7fb03d50be0ec1b734ca92b8a807c6b734e","sourceId":"s3","license":"CC BY-SA 4.0","width":1280,"height":853,"credit":"Dietmar Rabich","sourceUrl":"https://commons.wikimedia.org/wiki/File:Hoover_Dam,_Nevada_(Arizona-Nevada,_USA)_--_2012_--_6099.jpg","licenseUrl":"https://creativecommons.org/licenses/by-sa/4.0","imageDate":"Taken on 26 July 2012, 13:37","evidenceFile":"image-provenance/hoover-dam-commons.json","evidenceSha256":"ec32fc3ca7a4a63c78fa79cebdf26ae9a3b975af6c12b7c48725cb839261eca2","transformations":"Unmodified publisher-generated display-size file; the original source URL and publisher metadata are retained. No AI-generated replacement or content alteration.","originalUrl":"https://upload.wikimedia.org/wikipedia/commons/f/f6/Hoover_Dam%2C_Nevada_%28Arizona-Nevada%2C_USA%29_--_2012_--_6099.jpg","downloadUrl":"/cases/hoover-dam/download/project-image","originalSha1":"4d420802cfaaf32abceb2ae2056cfe87dbc710f9","imageDownloadAllowed":true,"rightsBasis":"See the per-image provenance record and linked license; source hosting alone is not the rights basis."},{"id":"capstone-brief","title":"Capstone brief (Markdown)","kind":"brief","fileName":"hoover-dam-capstone.md","mimeType":"text/markdown","bytes":3357,"sha256":"9454c025e84aa35fa0a13d2587b628d4c439ff0309ef32c508d072347e950f19","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/hoover-dam/download/capstone-brief"}],"figure":{"assetId":"project-image","kind":"photograph","alt":"Hoover Dam and its canyon setting.","caption":"Hoover Dam and its canyon setting. The photograph identifies the completed project; original and remedial foundation grouting are described in Reclamation’s records.","credit":"Dietmar Rabich","sourceUrl":"https://commons.wikimedia.org/wiki/File:Hoover_Dam,_Nevada_(Arizona-Nevada,_USA)_--_2012_--_6099.jpg","license":"CC BY-SA 4.0","licenseUrl":"https://creativecommons.org/licenses/by-sa/4.0","width":1280,"height":853,"imageDate":"Taken on 26 July 2012, 13:37","imageDownloadAllowed":true},"figureCaption":"Hoover Dam and its canyon setting. The photograph identifies the completed project; original and remedial foundation grouting are described in Reclamation’s records.","qualityNotes":[],"checked":"2026-11-22","addedIn":"r13","curatedOrder":69,"referenceValues":[],"teachingFigureCaption":"Conceptual study schematic; not an as-built project drawing.","imageEvidence":{"status":"acquired","identityVerified":true,"evidenceFile":"image-provenance/hoover-dam-commons.json","evidenceSha256":"ec32fc3ca7a4a63c78fa79cebdf26ae9a3b975af6c12b7c48725cb839261eca2","visualReview":"Viewed the complete publisher photograph in the final contact sheets or individually and compared it with the source identity, date, and caption. The caption distinguishes project context from the particular underground treatment or construction stage.","checked":"2026-11-22"},"localReportCount":0,"downloadBytes":470079,"sourceCount":3,"url":"/cases/hoover-dam"},{"id":"glen-canyon-dam","title":"Glen Canyon Dam — sandstone abutments and controlled seepage","summary":"The high concrete dam required canyon-wall stabilization, river diversion and excavation to sandstone bedrock. Reclamation describes rock bolts, seepage measurement and the geological basis of the site selection.","topics":["rock","dams-levees","seepage","dewatering","site-investigation"],"country":"United States","region":"Page, Arizona","owner":"US Bureau of Reclamation","year":1966,"yearLabel":"Case reference year","projectType":"Design, construction and performance","methods":["Rock bolting","Abutment stability","Seepage measurement","River diversion"],"documentationLevel":"technical-case","design":{"availability":"partial","summary":"The owner history explains the construction systems; the USGS regional map supports geological context. Regional mapping does not replace discontinuity surveys at individual abutments.","sourceIds":["s1","s2"]},"cost":{"availability":"not-found","summary":"A project-specific estimate, bid schedule or final account was not found in the reviewed sources.","sourceIds":[]},"schedule":{"availability":"partial","summary":"Reclamation records major construction milestones and dedication in 1966; detailed daily excavation records are not included.","sourceIds":["s1","s2"]},"records":{"availability":"not-found","summary":"Complete as-built drawings and acceptance records were not found in the reviewed sources.","sourceIds":[]},"capstone":{"label":"Suggested capstone study","scope":"An original teaching brief based on the documented project. Study assumptions and student designs are separate from the built project.","brief":"Develop rock-abutment support and seepage-monitoring concepts for a dam in fractured sandstone.","inputs":["Use the regional map and owner account to distinguish formation-scale geology from local joints.","Identify the temporary diversion and excavation stages that precede concrete placement."],"deliverables":["Perform a study wedge-stability check with bolt and groundwater sensitivities.","Design a drainage and weir-monitoring layout that distinguishes changing seepage paths from reservoir-level effects.","A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.","A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points."],"questions":["Why is measurable seepage not by itself evidence of dam failure?","What site mapping is required before using a regional joint orientation in a support design?"],"output":"Design report, calculation workbook, concept drawings, quantity schedule and construction programme."},"sources":[{"id":"s1","title":"Glen Canyon construction, geology and monitoring","url":"https://www.usbr.gov/uc/rm/crsp/gc/","publisher":"US Bureau of Reclamation","year":null,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s2","title":"Geologic map of the Glen Canyon Dam quadrangle","url":"https://pubs.usgs.gov/publication/sim3268","publisher":"US Geological Survey","year":null,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s3","title":"Glen Canyon Dam 1962.jpg — image and reuse license","url":"https://commons.wikimedia.org/wiki/File:Glen_Canyon_Dam_1962.jpg","publisher":"Wikimedia Commons / U.S. Bureau of Reclamation","year":1962,"access":"public-link","license":"Public domain","notes":"Project image source. Unmodified publisher-generated display-size file; the original source URL and publisher metadata are retained. No AI-generated replacement or content alteration.","checked":"2026-11-22","localAssetIds":["project-image"]}],"assets":[{"id":"schematic","title":"Conceptual study schematic","kind":"figure","fileName":"glen-canyon-dam.svg","mimeType":"image/svg+xml","bytes":1017,"sha256":"ab086e9b878d71ca75443d4083022bf013c864b1ad5c4bbfbedf783b1ffc7360","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/glen-canyon-dam/download/schematic"},{"id":"project-image","title":"Glen Canyon Dam 1962.jpg","kind":"project-image","fileName":"glen-canyon-dam.jpg","mimeType":"image/jpeg","bytes":417488,"sha256":"9d600d85f07d11d5b66cab14776d263c4e47c5e81665b6b2d1137d1ced913cef","sourceId":"s3","license":"Public domain","width":439,"height":550,"credit":"U.S. Bureau of Reclamation","sourceUrl":"https://commons.wikimedia.org/wiki/File:Glen_Canyon_Dam_1962.jpg","licenseUrl":"https://commons.wikimedia.org/wiki/File:Glen_Canyon_Dam_1962.jpg#Licensing","imageDate":"1962","evidenceFile":"image-provenance/glen-canyon-dam-commons.json","evidenceSha256":"c1a950a228699d14eebae0da50d05260e7eae33821540a6ef62b5fba484d0bc4","transformations":"Unmodified publisher-generated display-size file; the original source URL and publisher metadata are retained. No AI-generated replacement or content alteration.","originalUrl":"https://upload.wikimedia.org/wikipedia/commons/a/ae/Glen_Canyon_Dam_1962.jpg","downloadUrl":"/cases/glen-canyon-dam/download/project-image","originalSha1":"b6a0eb9c6a8100448477e78cd35499d7c07e7d28","originalSha256":"9d600d85f07d11d5b66cab14776d263c4e47c5e81665b6b2d1137d1ced913cef","imageDownloadAllowed":true,"rightsBasis":"See the per-image provenance record and linked license; source hosting alone is not the rights basis."},{"id":"capstone-brief","title":"Capstone brief (Markdown)","kind":"brief","fileName":"glen-canyon-dam-capstone.md","mimeType":"text/markdown","bytes":3082,"sha256":"7812eb24234b655ed2da8b5f24604a3588ab0a135414f74e6e24bd7b9db2dd95","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/glen-canyon-dam/download/capstone-brief"}],"figure":{"assetId":"project-image","kind":"photograph","alt":"Glen Canyon Dam under construction in 1962.","caption":"Glen Canyon Dam under construction in 1962. The historical photograph shows the actual dam and sandstone canyon abutments.","credit":"U.S. Bureau of Reclamation","sourceUrl":"https://commons.wikimedia.org/wiki/File:Glen_Canyon_Dam_1962.jpg","license":"Public domain","licenseUrl":"https://commons.wikimedia.org/wiki/File:Glen_Canyon_Dam_1962.jpg#Licensing","width":439,"height":550,"imageDate":"1962","preserveWholeImage":true,"imageDownloadAllowed":true},"figureCaption":"Glen Canyon Dam under construction in 1962. The historical photograph shows the actual dam and sandstone canyon abutments.","qualityNotes":[],"checked":"2026-11-22","addedIn":"r13","curatedOrder":70,"referenceValues":[],"teachingFigureCaption":"Conceptual study schematic; not an as-built project drawing.","imageEvidence":{"status":"acquired","identityVerified":true,"evidenceFile":"image-provenance/glen-canyon-dam-commons.json","evidenceSha256":"c1a950a228699d14eebae0da50d05260e7eae33821540a6ef62b5fba484d0bc4","visualReview":"Viewed the complete publisher photograph in the final contact sheets or individually and compared it with the source identity, date, and caption. The caption distinguishes project context from the particular underground treatment or construction stage.","checked":"2026-11-22"},"localReportCount":0,"downloadBytes":421587,"sourceCount":3,"url":"/cases/glen-canyon-dam"},{"id":"bolivar-dam","title":"Bolivar Dam — seepage barriers in outwash and fractured abutment rock","summary":"Rehabilitation combined a partial-depth barrier, blanket improvements, relief wells and an abutment grout curtain. The project authors explain construction problems in thin limestone units with open flow paths.","topics":["dams-levees","seepage","rock","monitoring"],"country":"United States","region":"Tuscarawas County, Ohio","owner":"US Army Corps of Engineers","year":2017,"yearLabel":"Case reference year","projectType":"Design, construction and performance","methods":["Partial-depth cutoff","Relief wells","Abutment grouting","Piping control"],"documentationLevel":"technical-case","design":{"availability":"partial","summary":"The USACE completion account identifies the combined risk-reduction measures. A technical paper details the abutment grouting and downstage treatment decisions.","sourceIds":["s1","s2"]},"cost":{"availability":"not-found","summary":"A project-specific estimate, bid schedule or final account was not found in the reviewed sources.","sourceIds":[]},"schedule":{"availability":"partial","summary":"The owner reports rehabilitation completion in October 2017.","sourceIds":["s1","s2"]},"records":{"availability":"partial","summary":"The completion account describes post-implementation evaluation and the resulting dam-safety classification.","sourceIds":["s1","s2"]},"capstone":{"label":"Suggested capstone study","scope":"An original teaching brief based on the documented project. Study assumptions and student designs are separate from the built project.","brief":"Compare seepage-control combinations for an embankment on permeable outwash beside fractured rock.","inputs":["Separate foundation flow, rock-contact erosion and gate-system issues in the owner record.","Extract the grout-curtain arrangement and treatment response to circulation losses."],"deliverables":["Draw a seepage model with wall, blanket and relief-well alternatives.","Specify drilling/grouting decisions and post-treatment piezometric performance criteria.","A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.","A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points."],"questions":["How can a partial-depth barrier still reduce internal-erosion risk?","Where could seepage concentrate if the wall-to-rock transition is poorly treated?"],"output":"Design report, calculation workbook, concept drawings, quantity schedule and construction programme."},"sources":[{"id":"s1","title":"Completion and post-implementation review","url":"https://www.army.mil/article/200670/bolivar_receives_best_dam_safety_rating","publisher":"US Army / USACE","year":null,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s2","title":"Grout-curtain construction at Bolivar Dam","url":"https://pubs.geoscienceworld.org/aeg/eeg/article-abstract/24/1/121/522957/Grout-Curtain-Construction-At-Bolivar-Dam-Ohio","publisher":"USACE project authors / Environmental & Engineering Geoscience","year":null,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s3","title":"Bolivar Dam (Ohio) upstream.jpg — image and reuse license","url":"https://commons.wikimedia.org/wiki/File:Bolivar_Dam_(Ohio)_upstream.jpg","publisher":"Wikimedia Commons / Roseohioresident","year":null,"access":"public-link","license":"Public domain","notes":"Project image source. Unmodified publisher-generated display-size file; the original source URL and publisher metadata are retained. No AI-generated replacement or content alteration.","checked":"2026-11-22","localAssetIds":["project-image"]}],"assets":[{"id":"schematic","title":"Conceptual study schematic","kind":"figure","fileName":"bolivar-dam.svg","mimeType":"image/svg+xml","bytes":985,"sha256":"ee95ff57b022b53ff13f55beb263a60b849d824c45c609ed976e0810f3961f8b","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/bolivar-dam/download/schematic"},{"id":"project-image","title":"Bolivar Dam (Ohio) upstream.jpg","kind":"project-image","fileName":"bolivar-dam.jpg","mimeType":"image/jpeg","bytes":395437,"sha256":"d20de43c4b633adfc2bdb10b723118662052fad325fe034c3b54fee87c8cd5c5","sourceId":"s3","license":"Public domain","width":1280,"height":960,"credit":"Roseohioresident","sourceUrl":"https://commons.wikimedia.org/wiki/File:Bolivar_Dam_(Ohio)_upstream.jpg","licenseUrl":"https://commons.wikimedia.org/wiki/File:Bolivar_Dam_(Ohio)_upstream.jpg#Licensing","imageDate":"Taken on 18 August 2010","evidenceFile":"image-provenance/bolivar-dam-commons.json","evidenceSha256":"06d3cfbcd6025097e520fe62ad8bbd6609f2d0557a1751445d3a1c76c9f28fc3","transformations":"Unmodified publisher-generated display-size file; the original source URL and publisher metadata are retained. No AI-generated replacement or content alteration.","originalUrl":"https://upload.wikimedia.org/wikipedia/commons/6/6e/Bolivar_Dam_%28Ohio%29_upstream.jpg","downloadUrl":"/cases/bolivar-dam/download/project-image","originalSha1":"9be59df03889845bff4d1c545c9fce0bc1a6693e","imageDownloadAllowed":true,"rightsBasis":"See the per-image provenance record and linked license; source hosting alone is not the rights basis."},{"id":"capstone-brief","title":"Capstone brief (Markdown)","kind":"brief","fileName":"bolivar-dam-capstone.md","mimeType":"text/markdown","bytes":3151,"sha256":"15bf2f4194d6edcc19efb7438c2a05798f6806f3933f4462c59513b14abee9db","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/bolivar-dam/download/capstone-brief"}],"figure":{"assetId":"project-image","kind":"photograph","alt":"Upstream view of Bolivar Dam in Ohio.","caption":"Upstream view of Bolivar Dam in Ohio. The actual embankment is shown; the later seepage barrier and grout curtain are largely below ground.","credit":"Roseohioresident","sourceUrl":"https://commons.wikimedia.org/wiki/File:Bolivar_Dam_(Ohio)_upstream.jpg","license":"Public domain","licenseUrl":"https://commons.wikimedia.org/wiki/File:Bolivar_Dam_(Ohio)_upstream.jpg#Licensing","width":1280,"height":960,"imageDate":"Taken on 18 August 2010","imageDownloadAllowed":true},"figureCaption":"Upstream view of Bolivar Dam in Ohio. The actual embankment is shown; the later seepage barrier and grout curtain are largely below ground.","qualityNotes":[],"checked":"2026-11-22","addedIn":"r13","curatedOrder":71,"referenceValues":[],"teachingFigureCaption":"Conceptual study schematic; not an as-built project drawing.","imageEvidence":{"status":"acquired","identityVerified":true,"evidenceFile":"image-provenance/bolivar-dam-commons.json","evidenceSha256":"06d3cfbcd6025097e520fe62ad8bbd6609f2d0557a1751445d3a1c76c9f28fc3","visualReview":"Viewed the complete publisher photograph in the final contact sheets or individually and compared it with the source identity, date, and caption. The caption distinguishes project context from the particular underground treatment or construction stage.","checked":"2026-11-22"},"localReportCount":0,"downloadBytes":399573,"sourceCount":3,"url":"/cases/bolivar-dam"},{"id":"gotthard-base-tunnel","title":"Gotthard Base Tunnel — squeezing rock and adaptive support","summary":"Deep tunnel sections encountered squeezing rock and strongly variable geological behavior. The Swiss geotechnical society’s project history explains both anticipated and unexpected support challenges at Sedrun and Faido.","topics":["tunnels","rock","site-investigation","monitoring","delivery"],"country":"Switzerland","region":"Swiss Alps","owner":"AlpTransit Gotthard","year":2016,"yearLabel":"Case reference year","projectType":"Design, construction and performance","methods":["Squeezing-ground support","Convergence monitoring","Geological prediction"],"documentationLevel":"technical-case","design":{"availability":"partial","summary":"The heritage case includes geology and support-system discussions from project records. It supports assessment of alternatives and field observations rather than transfer of one support class to all rock.","sourceIds":["s1","s2"]},"cost":{"availability":"not-found","summary":"A project-specific estimate, bid schedule or final account was not found in the reviewed sources.","sourceIds":[]},"schedule":{"availability":"partial","summary":"The engineering overview records opening in June 2016 after a long multi-heading construction programme.","sourceIds":["s1","s2"]},"records":{"availability":"not-found","summary":"Complete as-built drawings and acceptance records were not found in the reviewed sources.","sourceIds":[]},"capstone":{"label":"Suggested capstone study","scope":"An original teaching brief based on the documented project. Study assumptions and student designs are separate from the built project.","brief":"Select and revise a tunnel support scheme when measured convergence exceeds the original forecast.","inputs":["Choose one published squeezing section and extract its geology and support sequence.","Distinguish forecast ground conditions from observations obtained during excavation."],"deliverables":["Compare yielding and stiff support with a convergence–confinement study.","Prepare an observational trigger plan and construction-time implications for revised support.","A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.","A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points."],"questions":["Why can stronger initial support fail to stop continuing squeezing?","Which measurements indicate that a support change is needed before the next excavation round?"],"output":"Design report, calculation workbook, concept drawings, quantity schedule and construction programme."},"sources":[{"id":"s1","title":"Gotthard Base Tunnel engineering heritage case","url":"https://htc.issmge.org/virtual-time-capsule/member-societies/swiss-geotechnical-society-geotechnik-schweiz/gotthard-base-tunnel","publisher":"Swiss Geotechnical Society / ISSMGE","year":null,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s2","title":"Project engineering overview","url":"https://www.satw.ch/en/gotthard-base-tunnel-1","publisher":"Swiss Academy of Engineering Sciences","year":null,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s3","title":"20141120 gotthard-basistunnel05-wiki.jpg — image and reuse license","url":"https://commons.wikimedia.org/wiki/File:20141120_gotthard-basistunnel05-wiki.jpg","publisher":"Wikimedia Commons / Hannes Ortlieb ( Diskussion )","year":2014,"access":"public-link","license":"CC BY-SA 3.0 de","notes":"Project image source. Unmodified publisher-generated display-size file; the original source URL and publisher metadata are retained. No AI-generated replacement or content alteration.","checked":"2026-11-22","localAssetIds":["project-image"]}],"assets":[{"id":"schematic","title":"Conceptual study schematic","kind":"figure","fileName":"gotthard-base-tunnel.svg","mimeType":"image/svg+xml","bytes":1125,"sha256":"6e6bc7d568720504ae2ac68b2111e026e4bb56fc1979d2a2854bd49ec8c3b1db","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/gotthard-base-tunnel/download/schematic"},{"id":"project-image","title":"20141120 gotthard-basistunnel05-wiki.jpg","kind":"project-image","fileName":"gotthard-base-tunnel.jpg","mimeType":"image/jpeg","bytes":270024,"sha256":"c34e7149142543a6d7467bab8777410c8eda3fd5bea95792762d9de0b49230d5","sourceId":"s3","license":"CC BY-SA 3.0 de","width":1280,"height":853,"credit":"Hannes Ortlieb ( Diskussion )","sourceUrl":"https://commons.wikimedia.org/wiki/File:20141120_gotthard-basistunnel05-wiki.jpg","licenseUrl":"https://creativecommons.org/licenses/by-sa/3.0/de/deed.en","imageDate":"2014-11-20","evidenceFile":"image-provenance/gotthard-base-tunnel-commons.json","evidenceSha256":"b0b8e93d8f2238bc07cd984600507c4e88264e3ece95c7661871510ceae09f35","transformations":"Unmodified publisher-generated display-size file; the original source URL and publisher metadata are retained. No AI-generated replacement or content alteration.","originalUrl":"https://upload.wikimedia.org/wikipedia/commons/6/69/20141120_gotthard-basistunnel05-wiki.jpg","downloadUrl":"/cases/gotthard-base-tunnel/download/project-image","originalSha1":"e74de4bfce9b76c9c98d216f3edbb245cb2a7ec5","imageDownloadAllowed":true,"rightsBasis":"See the per-image provenance record and linked license; source hosting alone is not the rights basis."},{"id":"capstone-brief","title":"Capstone brief (Markdown)","kind":"brief","fileName":"gotthard-base-tunnel-capstone.md","mimeType":"text/markdown","bytes":3256,"sha256":"76ba7c8ccd685844c7f7ec46648cb4988358b8db5be5d2a9269651d4d408168b","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/gotthard-base-tunnel/download/capstone-brief"}],"figure":{"assetId":"project-image","kind":"photograph","alt":"Faido crossover area in the Gotthard Base Tunnel during construction in 2014.","caption":"Faido crossover area in the Gotthard Base Tunnel during construction in 2014. The actual underground works are shown; squeezing-ground support stages are described in the technical case.","credit":"Hannes Ortlieb ( Diskussion )","sourceUrl":"https://commons.wikimedia.org/wiki/File:20141120_gotthard-basistunnel05-wiki.jpg","license":"CC BY-SA 3.0 de","licenseUrl":"https://creativecommons.org/licenses/by-sa/3.0/de/deed.en","width":1280,"height":853,"imageDate":"2014-11-20","imageDownloadAllowed":true},"figureCaption":"Faido crossover area in the Gotthard Base Tunnel during construction in 2014. The actual underground works are shown; squeezing-ground support stages are described in the technical case.","qualityNotes":[],"checked":"2026-11-22","addedIn":"r13","curatedOrder":74,"referenceValues":[],"teachingFigureCaption":"Conceptual study schematic; not an as-built project drawing.","imageEvidence":{"status":"acquired","identityVerified":true,"evidenceFile":"image-provenance/gotthard-base-tunnel-commons.json","evidenceSha256":"b0b8e93d8f2238bc07cd984600507c4e88264e3ece95c7661871510ceae09f35","visualReview":"Viewed the complete publisher photograph in the final contact sheets or individually and compared it with the source identity, date, and caption. The caption distinguishes project context from the particular underground treatment or construction stage.","checked":"2026-11-22"},"localReportCount":0,"downloadBytes":274405,"sourceCount":3,"url":"/cases/gotthard-base-tunnel"},{"id":"channel-tunnel","title":"Channel Tunnel — geological alignment and water-pressure control","summary":"The alignment sought low-permeability marly chalk while accommodating more fractured ground on the French side. Project geologists describe how marine seismic surveys and boreholes informed route selection and machine requirements.","topics":["tunnels","rock","site-investigation","dewatering"],"country":"United Kingdom / France","region":"English Channel","owner":"Eurotunnel","year":1994,"yearLabel":"Case reference year","projectType":"Design, construction and performance","methods":["Marine ground investigation","Geological alignment","Face-pressure control"],"documentationLevel":"technical-case","design":{"availability":"partial","summary":"The account is written by geologists involved in design and construction and includes the geological section. It does not provide all TBM operating logs.","sourceIds":["s1"]},"cost":{"availability":"not-found","summary":"A project-specific estimate, bid schedule or final account was not found in the reviewed sources.","sourceIds":[]},"schedule":{"availability":"not-found","summary":"A dated project programme was not found in the reviewed sources; develop a study schedule from the documented method.","sourceIds":[]},"records":{"availability":"not-found","summary":"Complete as-built drawings and acceptance records were not found in the reviewed sources.","sourceIds":[]},"capstone":{"label":"Suggested capstone study","scope":"An original teaching brief based on the documented project. Study assumptions and student designs are separate from the built project.","brief":"Select a sub-sea tunnel alignment that balances cover, geological continuity and water-inflow risk.","inputs":["Extract the main stratigraphic marker and the reported contrast between the two shores.","Identify where sparse boreholes require interpretation supported by seismic profiles."],"deliverables":["Prepare a route-risk section and specify investigation priorities.","Compare open and closed-face excavation assumptions with water-pressure and fault-zone scenarios.","A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.","A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points."],"questions":["Why is the shortest geometric route not necessarily the lowest ground-risk route?","What evidence should trigger closed-mode operation before a permeable zone is entered?"],"output":"Design report, calculation workbook, concept drawings, quantity schedule and construction programme."},"sources":[{"id":"s1","title":"Channel Tunnel geology by project geologists","url":"https://www.geolsoc.org.uk/science-and-policy/100-great-geosites/industrial-and-economic-importance/channel-tunnel/","publisher":"Bill Rankin and Ron Williams / Geological Society","year":null,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s2","title":"Site of the Channel Tunnel Construction in May 1991.jpg — image and reuse license","url":"https://commons.wikimedia.org/wiki/File:Site_of_the_Channel_Tunnel_Construction_in_May_1991.jpg","publisher":"Wikimedia Commons / The Basingstoker","year":null,"access":"public-link","license":"CC BY-SA 2.0","notes":"Project image source. Unmodified publisher-generated display-size file; the original source URL and publisher metadata are retained. No AI-generated replacement or content alteration.","checked":"2026-11-22","localAssetIds":["project-image"]}],"assets":[{"id":"schematic","title":"Conceptual study schematic","kind":"figure","fileName":"channel-tunnel.svg","mimeType":"image/svg+xml","bytes":1125,"sha256":"6e6bc7d568720504ae2ac68b2111e026e4bb56fc1979d2a2854bd49ec8c3b1db","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/channel-tunnel/download/schematic"},{"id":"project-image","title":"Site of the Channel Tunnel Construction in May 1991.jpg","kind":"project-image","fileName":"channel-tunnel.jpg","mimeType":"image/jpeg","bytes":294751,"sha256":"f4aaa8dd8d642ab88dc0d9b42b5b4256db7db5a638caa32ec433aa1961dcde9e","sourceId":"s2","license":"CC BY-SA 2.0","width":1280,"height":821,"credit":"The Basingstoker","sourceUrl":"https://commons.wikimedia.org/wiki/File:Site_of_the_Channel_Tunnel_Construction_in_May_1991.jpg","licenseUrl":"https://creativecommons.org/licenses/by-sa/2.0","imageDate":"Unknown date","evidenceFile":"image-provenance/channel-tunnel-commons.json","evidenceSha256":"9649b153db1a0137d64094b16abc794aca62ee229ecfa64ae4748d3f01da2f74","transformations":"Unmodified publisher-generated display-size file; the original source URL and publisher metadata are retained. No AI-generated replacement or content alteration.","originalUrl":"https://upload.wikimedia.org/wikipedia/commons/a/a0/Site_of_the_Channel_Tunnel_Construction_in_May_1991.jpg","downloadUrl":"/cases/channel-tunnel/download/project-image","originalSha1":"8ccf8054cb87766b63fdca45e2f2a8059e15029b","imageDownloadAllowed":true,"rightsBasis":"See the per-image provenance record and linked license; source hosting alone is not the rights basis."},{"id":"capstone-brief","title":"Capstone brief (Markdown)","kind":"brief","fileName":"channel-tunnel-capstone.md","mimeType":"text/markdown","bytes":3106,"sha256":"12ad7d067a39fc330a07359b02e2fa40ea999e32678268d8ca45ee7002155e26","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/channel-tunnel/download/capstone-brief"}],"figure":{"assetId":"project-image","kind":"photograph","alt":"The Channel Tunnel construction site in May 1991.","caption":"The Channel Tunnel construction site in May 1991. The historical project photograph provides context for the geological alignment and excavation study.","credit":"The Basingstoker","sourceUrl":"https://commons.wikimedia.org/wiki/File:Site_of_the_Channel_Tunnel_Construction_in_May_1991.jpg","license":"CC BY-SA 2.0","licenseUrl":"https://creativecommons.org/licenses/by-sa/2.0","width":1280,"height":821,"imageDate":"Unknown date","imageDownloadAllowed":true},"figureCaption":"The Channel Tunnel construction site in May 1991. The historical project photograph provides context for the geological alignment and excavation study.","qualityNotes":[],"checked":"2026-11-22","addedIn":"r13","curatedOrder":75,"referenceValues":[],"teachingFigureCaption":"Conceptual study schematic; not an as-built project drawing.","imageEvidence":{"status":"acquired","identityVerified":true,"evidenceFile":"image-provenance/channel-tunnel-commons.json","evidenceSha256":"9649b153db1a0137d64094b16abc794aca62ee229ecfa64ae4748d3f01da2f74","visualReview":"Viewed the complete publisher photograph in the final contact sheets or individually and compared it with the source identity, date, and caption. The caption distinguishes project context from the particular underground treatment or construction stage.","checked":"2026-11-22"},"localReportCount":0,"downloadBytes":298982,"sourceCount":2,"url":"/cases/channel-tunnel"},{"id":"smart-tunnel","title":"SMART Tunnel — tunnelling through urban karst","summary":"The combined stormwater and road tunnel passes through highly irregular limestone and overlying deposits. The builder and ground-treatment contractor describe slurry-shield excavation, grouting and sinkhole-management challenges.","topics":["tunnels","rock","dewatering","ground-improvement","site-investigation"],"country":"Malaysia","region":"Kuala Lumpur","owner":"Department of Irrigation and Drainage / Malaysian Highway Authority","year":2007,"yearLabel":"Case reference year","projectType":"Design, construction and performance","methods":["Karst investigation","Slurry shield","Fissure and compaction grouting"],"documentationLevel":"technical-case","design":{"availability":"partial","summary":"The primary construction accounts explain the selected methods and localized treatment purposes. They do not establish that karst uncertainty can be removed by one uniform grouting grid.","sourceIds":["s1","s2","s3"]},"cost":{"availability":"not-found","summary":"A project-specific estimate, bid schedule or final account was not found in the reviewed sources.","sourceIds":[]},"schedule":{"availability":"partial","summary":"The builder identifies operation from 2007; the page is a project history rather than a detailed monthly programme.","sourceIds":["s1","s2","s3"]},"records":{"availability":"not-found","summary":"Complete as-built drawings and acceptance records were not found in the reviewed sources.","sourceIds":[]},"capstone":{"label":"Suggested capstone study","scope":"An original teaching brief based on the documented project. Study assumptions and student designs are separate from the built project.","brief":"Plan ground investigation and treatment for a tunnel encountering pinnacles, cavities and variable cover beneath a city.","inputs":["Extract the reported karst features and the purpose of each grouting method.","Specify investigation coverage at shafts, interventions and transitions rather than uniform spacing alone."],"deliverables":["Develop face-pressure and groundwater-control concepts for mixed ground.","Prepare a cavity/sinkhole response plan with survey triggers and treatment verification.","A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.","A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points."],"questions":["How can groundwater drawdown cause a surface collapse away from the tunnel face?","Which evidence separates a treatable local void from a larger connected karst system?"],"output":"Design report, calculation workbook, concept drawings, quantity schedule and construction programme."},"sources":[{"id":"s1","title":"SMART construction and geology","url":"https://www.smarttunnel.com.my/construction/print_project_construction.htm","publisher":"SMART project","year":null,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s2","title":"Ground-treatment contractor case","url":"https://www.kellerasean.com/projects/storm-water-management-and-road-tunnel","publisher":"Keller","year":null,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s3","title":"Builder project record","url":"https://gamuda.com/our-expertise/engineering-construction/stormwater-management-and-road-tunnel-smart/","publisher":"Gamuda","year":null,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s4","title":"KL-SMARTtunnelentrance.JPG — image and reuse license","url":"https://commons.wikimedia.org/wiki/File:KL-SMARTtunnelentrance.JPG","publisher":"Wikimedia Commons / Azreey","year":2007,"access":"public-link","license":"CC BY-SA 4.0","notes":"Project image source. Unmodified publisher-generated display-size file; the original source URL and publisher metadata are retained. No AI-generated replacement or content alteration.","checked":"2026-11-22","localAssetIds":["project-image"]}],"assets":[{"id":"schematic","title":"Conceptual study schematic","kind":"figure","fileName":"smart-tunnel.svg","mimeType":"image/svg+xml","bytes":1125,"sha256":"6e6bc7d568720504ae2ac68b2111e026e4bb56fc1979d2a2854bd49ec8c3b1db","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/smart-tunnel/download/schematic"},{"id":"project-image","title":"KL-SMARTtunnelentrance.JPG","kind":"project-image","fileName":"smart-tunnel.jpg","mimeType":"image/jpeg","bytes":577763,"sha256":"96788f96ef8b17d718aeb536a6282dc215767c1c9217e99d6a7999c55a4d275d","sourceId":"s4","license":"CC BY-SA 4.0","width":1280,"height":960,"credit":"Azreey","sourceUrl":"https://commons.wikimedia.org/wiki/File:KL-SMARTtunnelentrance.JPG","licenseUrl":"https://creativecommons.org/licenses/by-sa/4.0","imageDate":"2007-12-27","evidenceFile":"image-provenance/smart-tunnel-commons.json","evidenceSha256":"d6654eb1d691f51c5618edc29c7f59f575cfe4d5c70ce3a39979b2a84f69a950","transformations":"Unmodified publisher-generated display-size file; the original source URL and publisher metadata are retained. No AI-generated replacement or content alteration.","originalUrl":"https://upload.wikimedia.org/wikipedia/commons/2/26/KL-SMARTtunnelentrance.JPG","downloadUrl":"/cases/smart-tunnel/download/project-image","originalSha1":"a5a0765e43e062f683adc413aa657655bbd67c36","originalSha256":"96788f96ef8b17d718aeb536a6282dc215767c1c9217e99d6a7999c55a4d275d","imageDownloadAllowed":true,"rightsBasis":"See the per-image provenance record and linked license; source hosting alone is not the rights basis."},{"id":"capstone-brief","title":"Capstone brief (Markdown)","kind":"brief","fileName":"smart-tunnel-capstone.md","mimeType":"text/markdown","bytes":3195,"sha256":"41d78160bf08853a679ec43e844ed00eefd919e2d2cb15461408fd68297d66db","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/smart-tunnel/download/capstone-brief"}],"figure":{"assetId":"project-image","kind":"photograph","alt":"The northbound entrance to Kuala Lumpur’s SMART Tunnel.","caption":"The northbound entrance to Kuala Lumpur’s SMART Tunnel. This is the actual dual-purpose tunnel; its karst treatment works are underground.","credit":"Azreey","sourceUrl":"https://commons.wikimedia.org/wiki/File:KL-SMARTtunnelentrance.JPG","license":"CC BY-SA 4.0","licenseUrl":"https://creativecommons.org/licenses/by-sa/4.0","width":1280,"height":960,"imageDate":"2007-12-27","imageDownloadAllowed":true},"figureCaption":"The northbound entrance to Kuala Lumpur’s SMART Tunnel. This is the actual dual-purpose tunnel; its karst treatment works are underground.","qualityNotes":[],"checked":"2026-11-22","addedIn":"r13","curatedOrder":83,"referenceValues":[],"teachingFigureCaption":"Conceptual study schematic; not an as-built project drawing.","imageEvidence":{"status":"acquired","identityVerified":true,"evidenceFile":"image-provenance/smart-tunnel-commons.json","evidenceSha256":"d6654eb1d691f51c5618edc29c7f59f575cfe4d5c70ce3a39979b2a84f69a950","visualReview":"Viewed the complete publisher photograph in the final contact sheets or individually and compared it with the source identity, date, and caption. The caption distinguishes project context from the particular underground treatment or construction stage.","checked":"2026-11-22"},"localReportCount":0,"downloadBytes":582083,"sourceCount":4,"url":"/cases/smart-tunnel"},{"id":"vajont-landslide","title":"Vajont reservoir — rockslide, groundwater and observational decisions","summary":"The reservoir disaster involved a large pre-existing rockslide and rapid displacement of reservoir water. Geological researchers emphasize the complex shear zone and the influence of groundwater and reservoir operations.","topics":["slopes","rock","dams-levees","seepage","monitoring"],"country":"Italy","region":"Vajont Valley","owner":"Historic reservoir project / Italian public investigation","year":1963,"yearLabel":"Case reference year","projectType":"Failure investigation and lessons","methods":["Rockslide back-analysis","Reservoir drawdown","Shear-zone strength"],"documentationLevel":"forensic-study","design":{"availability":"partial","summary":"This is a forensic case, not a completed slope-remediation design. Competing geological interpretations remain relevant when selecting assumptions for back-analysis.","sourceIds":["s1","s2"]},"cost":{"availability":"not-found","summary":"A project-specific estimate, bid schedule or final account was not found in the reviewed sources.","sourceIds":[]},"schedule":{"availability":"not-found","summary":"A dated project programme was not found in the reviewed sources; develop a study schedule from the documented method.","sourceIds":[]},"records":{"availability":"not-found","summary":"Complete as-built drawings and acceptance records were not found in the reviewed sources.","sourceIds":[]},"capstone":{"label":"Suggested capstone study","scope":"An original teaching brief based on the documented project. Study assumptions and student designs are separate from the built project.","brief":"Reconstruct how alternative geological models change slope-stability decisions during reservoir filling.","inputs":["Compare published interpretations of the old slide mass and basal shear zone.","Compile a source-based sequence of reservoir levels, observations and movement."],"deliverables":["Perform coupled seepage/stability sensitivity studies for the competing models.","Write an observational decision plan with limits on reservoir operations and explicitly conservative triggers.","A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.","A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points."],"questions":["Why can a good fit to one displacement episode fail to validate a unique failure mechanism?","What monitoring evidence would justify stopping filling before a deterministic factor of safety reaches one?"],"output":"Design report, calculation workbook, concept drawings, quantity schedule and construction programme."},"sources":[{"id":"s1","title":"Vajont geological heritage and research context","url":"https://iugs-geoheritage.org/geoheritage_sites/vajont-landslide/","publisher":"International Union of Geological Sciences / case scientists","year":null,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s2","title":"Updated geological model of the prehistoric rockslide","url":"https://www.sciencedirect.com/science/article/pii/S0169555X12002048","publisher":"Paronuzzi and Bolla / Geomorphology","year":null,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s3","title":"Vajont Dam landslide.jpg — image and reuse license","url":"https://commons.wikimedia.org/wiki/File:Vajont_Dam_landslide.jpg","publisher":"Wikimedia Commons / US Army","year":1963,"access":"public-link","license":"Public domain","notes":"Project image source. Unmodified publisher-generated display-size file; the original source URL and publisher metadata are retained. No AI-generated replacement or content alteration.","checked":"2026-11-22","localAssetIds":["project-image"]}],"assets":[{"id":"schematic","title":"Conceptual study schematic","kind":"figure","fileName":"vajont-landslide.svg","mimeType":"image/svg+xml","bytes":1029,"sha256":"ccf2f027816a3de86d722599635826d3b3cadcf8867cf69fa1bf6fc1bdf2d3bf","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/vajont-landslide/download/schematic"},{"id":"project-image","title":"Vajont Dam landslide.jpg","kind":"project-image","fileName":"vajont-landslide.jpg","mimeType":"image/jpeg","bytes":115238,"sha256":"101bf55fce288261b9be5350624ada515293ee27254dc4ea441259aa489fcb16","sourceId":"s3","license":"Public domain","width":800,"height":550,"credit":"US Army","sourceUrl":"https://commons.wikimedia.org/wiki/File:Vajont_Dam_landslide.jpg","licenseUrl":"https://commons.wikimedia.org/wiki/File:Vajont_Dam_landslide.jpg#Licensing","imageDate":"1963","evidenceFile":"image-provenance/vajont-landslide-commons.json","evidenceSha256":"5c02ae2fe38b9b323a7f6211233de9232d9a3ef4bd2bf62b925e09b40fcb24d2","transformations":"Unmodified publisher-generated display-size file; the original source URL and publisher metadata are retained. No AI-generated replacement or content alteration.","originalUrl":"https://upload.wikimedia.org/wikipedia/commons/f/f4/Vajont_Dam_landslide.jpg","downloadUrl":"/cases/vajont-landslide/download/project-image","originalSha1":"fdceebd3956b8ae854e0327568b91a20d76834f8","originalSha256":"101bf55fce288261b9be5350624ada515293ee27254dc4ea441259aa489fcb16","imageDownloadAllowed":true,"rightsBasis":"See the per-image provenance record and linked license; source hosting alone is not the rights basis."},{"id":"capstone-brief","title":"Capstone brief (Markdown)","kind":"brief","fileName":"vajont-landslide-capstone.md","mimeType":"text/markdown","bytes":3153,"sha256":"def386340f1865b5b949a68cec0b779fa5789e9497ca974f589aa46aeb58ad98","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/vajont-landslide/download/capstone-brief"}],"figure":{"assetId":"project-image","kind":"photograph","alt":"The Vajont landslide in 1963.","caption":"The Vajont landslide in 1963. Historical US Army photograph showing the actual landslide and reservoir-dam setting.","credit":"US Army","sourceUrl":"https://commons.wikimedia.org/wiki/File:Vajont_Dam_landslide.jpg","license":"Public domain","licenseUrl":"https://commons.wikimedia.org/wiki/File:Vajont_Dam_landslide.jpg#Licensing","width":800,"height":550,"imageDate":"1963","preserveWholeImage":true,"imageDownloadAllowed":true},"figureCaption":"The Vajont landslide in 1963. Historical US Army photograph showing the actual landslide and reservoir-dam setting.","qualityNotes":[],"checked":"2026-11-22","addedIn":"r13","curatedOrder":87,"referenceValues":[],"teachingFigureCaption":"Conceptual study schematic; not an as-built project drawing.","imageEvidence":{"status":"acquired","identityVerified":true,"evidenceFile":"image-provenance/vajont-landslide-commons.json","evidenceSha256":"5c02ae2fe38b9b323a7f6211233de9232d9a3ef4bd2bf62b925e09b40fcb24d2","visualReview":"Viewed the complete publisher photograph in the final contact sheets or individually and compared it with the source identity, date, and caption. The caption distinguishes project context from the particular underground treatment or construction stage.","checked":"2026-11-22"},"localReportCount":0,"downloadBytes":119420,"sourceCount":3,"url":"/cases/vajont-landslide"},{"id":"malpasset-dam","title":"Malpasset Dam — abutment wedge failure and uplift","summary":"The arch dam failed after instability developed in its rock foundation. The French dam committee and government accident record describe the role of discontinuity geometry, uplift and stress-dependent drainage.","topics":["rock","dams-levees","seepage","site-investigation"],"country":"France","region":"Fréjus","owner":"Historic Malpasset water-supply project","year":1959,"yearLabel":"Case reference year","projectType":"Failure investigation and lessons","methods":["Rock-wedge stability","Uplift pressure","Stress-dependent permeability"],"documentationLevel":"forensic-study","design":{"availability":"partial","summary":"The English technical material supports a forensic rock-wedge study. It is not an as-built remediation proposal for the ruined dam.","sourceIds":["s1","s2"]},"cost":{"availability":"not-found","summary":"A project-specific estimate, bid schedule or final account was not found in the reviewed sources.","sourceIds":[]},"schedule":{"availability":"not-found","summary":"A dated project programme was not found in the reviewed sources; develop a study schedule from the documented method.","sourceIds":[]},"records":{"availability":"not-found","summary":"Complete as-built drawings and acceptance records were not found in the reviewed sources.","sourceIds":[]},"capstone":{"label":"Suggested capstone study","scope":"An original teaching brief based on the documented project. Study assumptions and student designs are separate from the built project.","brief":"Evaluate an arch-dam abutment where intersecting discontinuities create a potentially unstable rock wedge.","inputs":["Extract the reported fault, foliation and abutment-force relationships.","Separate known observations from later interpretations of permeability changes."],"deliverables":["Calculate wedge stability for several groundwater-pressure distributions.","Specify investigation and drainage verification that could discriminate between the competing assumptions.","A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.","A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points."],"questions":["How can increased compressive stress reduce drainage yet raise destabilizing uplift?","Why may strong intact rock still provide an inadequate dam abutment?"],"output":"Design report, calculation workbook, concept drawings, quantity schedule and construction programme."},"sources":[{"id":"s1","title":"Government accident review","url":"https://www.aria.developpement-durable.gouv.fr/fiche_detaillee/29490_en/?lang=en","publisher":"French Ministry environmental accident database","year":null,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s2","title":"Arch-dam guidance and Malpasset foundation case","url":"https://www.barrages-cfbr.eu/IMG/pdf/gtvoute_vienne2018.pdf","publisher":"French Committee on Dams and Reservoirs","year":null,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s3","title":"Barrage Malpasset 2007.jpg — image and reuse license","url":"https://commons.wikimedia.org/wiki/File:Barrage_Malpasset_2007.jpg","publisher":"Wikimedia Commons / Bonho1962","year":2007,"access":"public-link","license":"Public domain","notes":"Project image source. Unmodified publisher-generated display-size file; the original source URL and publisher metadata are retained. No AI-generated replacement or content alteration.","checked":"2026-11-22","localAssetIds":["project-image"]}],"assets":[{"id":"schematic","title":"Conceptual study schematic","kind":"figure","fileName":"malpasset-dam.svg","mimeType":"image/svg+xml","bytes":1017,"sha256":"ab086e9b878d71ca75443d4083022bf013c864b1ad5c4bbfbedf783b1ffc7360","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/malpasset-dam/download/schematic"},{"id":"project-image","title":"Barrage Malpasset 2007.jpg","kind":"project-image","fileName":"malpasset-dam.jpg","mimeType":"image/jpeg","bytes":168986,"sha256":"039a3c531fb72c3b49904ea6e1f9da2bea8acdddbc138a8643e5ba023bab74e5","sourceId":"s3","license":"Public domain","width":1280,"height":453,"credit":"Bonho1962","sourceUrl":"https://commons.wikimedia.org/wiki/File:Barrage_Malpasset_2007.jpg","licenseUrl":"https://commons.wikimedia.org/wiki/File:Barrage_Malpasset_2007.jpg#Licensing","imageDate":"2007-06-08","evidenceFile":"image-provenance/malpasset-dam-commons.json","evidenceSha256":"04369b2ef16501c643e1aea885269ffa0c83d1f6cd2aae2c207a48b564d30a04","transformations":"Unmodified publisher-generated display-size file; the original source URL and publisher metadata are retained. No AI-generated replacement or content alteration.","originalUrl":"https://upload.wikimedia.org/wikipedia/commons/6/64/Barrage_Malpasset_2007.jpg","downloadUrl":"/cases/malpasset-dam/download/project-image","originalSha1":"30bd87cf637b57e5f5502beeba47afb24b14f92f","imageDownloadAllowed":true,"rightsBasis":"See the per-image provenance record and linked license; source hosting alone is not the rights basis."},{"id":"capstone-brief","title":"Capstone brief (Markdown)","kind":"brief","fileName":"malpasset-dam-capstone.md","mimeType":"text/markdown","bytes":3016,"sha256":"ed57709c549dd09a23398800a53df70f4909ccb6252c938df716172917eaf451","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/malpasset-dam/download/capstone-brief"}],"figure":{"assetId":"project-image","kind":"photograph","alt":"Ruins of Malpasset Dam photographed in 2007.","caption":"Ruins of Malpasset Dam photographed in 2007. The remaining concrete and rock setting belong to the actual 1959 failure site.","credit":"Bonho1962","sourceUrl":"https://commons.wikimedia.org/wiki/File:Barrage_Malpasset_2007.jpg","license":"Public domain","licenseUrl":"https://commons.wikimedia.org/wiki/File:Barrage_Malpasset_2007.jpg#Licensing","width":1280,"height":453,"imageDate":"2007-06-08","imageDownloadAllowed":true},"figureCaption":"Ruins of Malpasset Dam photographed in 2007. The remaining concrete and rock setting belong to the actual 1959 failure site.","qualityNotes":[],"checked":"2026-11-22","addedIn":"r13","curatedOrder":88,"referenceValues":[],"teachingFigureCaption":"Conceptual study schematic; not an as-built project drawing.","imageEvidence":{"status":"acquired","identityVerified":true,"evidenceFile":"image-provenance/malpasset-dam-commons.json","evidenceSha256":"04369b2ef16501c643e1aea885269ffa0c83d1f6cd2aae2c207a48b564d30a04","visualReview":"Viewed the complete publisher photograph in the final contact sheets or individually and compared it with the source identity, date, and caption. The caption distinguishes project context from the particular underground treatment or construction stage.","checked":"2026-11-22"},"localReportCount":0,"downloadBytes":173019,"sourceCount":3,"url":"/cases/malpasset-dam"},{"id":"st-francis-dam","title":"St. Francis Dam — investigation evidence and foundation reassessment","summary":"The 1928 collapse prompted an official investigation and later reassessments of geology and foundation behavior. The records make a useful exercise in distinguishing contemporary findings from subsequent hypotheses.","topics":["rock","dams-levees","problem-soils","site-investigation"],"country":"United States","region":"San Francisquito Canyon, California","owner":"Historic Los Angeles water-supply project","year":1928,"yearLabel":"Case reference year","projectType":"Failure investigation and lessons","methods":["Forensic ground model","Foundation saturation","Abutment stability"],"documentationLevel":"forensic-study","design":{"availability":"partial","summary":"The commission report and later research represent different stages of interpretation. No single disputed mechanism is presented as conclusively established by this catalog.","sourceIds":["s1","s2","s3"]},"cost":{"availability":"not-found","summary":"A project-specific estimate, bid schedule or final account was not found in the reviewed sources.","sourceIds":[]},"schedule":{"availability":"not-found","summary":"A dated project programme was not found in the reviewed sources; develop a study schedule from the documented method.","sourceIds":[]},"records":{"availability":"not-found","summary":"Complete as-built drawings and acceptance records were not found in the reviewed sources.","sourceIds":[]},"capstone":{"label":"Suggested capstone study","scope":"An original teaching brief based on the documented project. Study assumptions and student designs are separate from the built project.","brief":"Compare competing foundation-failure explanations and propose the investigation that would best distinguish them.","inputs":["Extract evidence from the original commission report separately from later interpretations.","Map the contrasting abutment materials and identify changes associated with reservoir filling."],"deliverables":["Prepare sensitivity checks for sliding, uplift and material degradation.","Build an evidence matrix showing which observations support or contradict each mechanism.","A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.","A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points."],"questions":["Which conclusion depends most strongly on an assumed pre-failure groundwater condition?","How would modern investigation reduce uncertainty without claiming hindsight makes the outcome inevitable?"],"output":"Design report, calculation workbook, concept drawings, quantity schedule and construction programme."},"sources":[{"id":"s1","title":"Original commission report record","url":"https://damsafety.org/content/causes-leading-failure-saint-francis-dam","publisher":"California investigation commission / ASDSO archive","year":null,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s2","title":"Later foundation reassessment","url":"https://damsafety.org/content/reassessment-st-francis-dam-failure-0","publisher":"J. David Rogers and David McMahon / ASDSO","year":null,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s3","title":"USGS historical overview","url":"https://www.usgs.gov/media/images/st-francis-dam-disaster","publisher":"US Geological Survey","year":null,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s4","title":"Saint Francis Dam Site 2012.jpg — image and reuse license","url":"https://commons.wikimedia.org/wiki/File:Saint_Francis_Dam_Site_2012.jpg","publisher":"Wikimedia Commons / Chevy111","year":2012,"access":"public-link","license":"CC BY-SA 4.0","notes":"Project image source. Unmodified publisher-generated display-size file; the original source URL and publisher metadata are retained. No AI-generated replacement or content alteration.","checked":"2026-11-22","localAssetIds":["project-image"]}],"assets":[{"id":"schematic","title":"Conceptual study schematic","kind":"figure","fileName":"st-francis-dam.svg","mimeType":"image/svg+xml","bytes":1017,"sha256":"ab086e9b878d71ca75443d4083022bf013c864b1ad5c4bbfbedf783b1ffc7360","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/st-francis-dam/download/schematic"},{"id":"project-image","title":"Saint Francis Dam Site 2012.jpg","kind":"project-image","fileName":"st-francis-dam.jpg","mimeType":"image/jpeg","bytes":410499,"sha256":"615231c05357069092a774fa146cb08b7be245e4ef4479873474fa16986d23f3","sourceId":"s4","license":"CC BY-SA 4.0","width":1280,"height":960,"credit":"Chevy111","sourceUrl":"https://commons.wikimedia.org/wiki/File:Saint_Francis_Dam_Site_2012.jpg","licenseUrl":"https://creativecommons.org/licenses/by-sa/4.0","imageDate":"2012-08-05 09:47:38","evidenceFile":"image-provenance/st-francis-dam-commons.json","evidenceSha256":"53a2c42e8c9d7963c83e036424e0cf8fc84572d726d0e567074b0648702bb588","transformations":"Unmodified publisher-generated display-size file; the original source URL and publisher metadata are retained. No AI-generated replacement or content alteration.","originalUrl":"https://upload.wikimedia.org/wikipedia/commons/a/a3/Saint_Francis_Dam_Site_2012.jpg","downloadUrl":"/cases/st-francis-dam/download/project-image","originalSha1":"9f6c998731ed25f57bb2d83749f0b6043c7ec96b","imageDownloadAllowed":true,"rightsBasis":"See the per-image provenance record and linked license; source hosting alone is not the rights basis."},{"id":"capstone-brief","title":"Capstone brief (Markdown)","kind":"brief","fileName":"st-francis-dam-capstone.md","mimeType":"text/markdown","bytes":3301,"sha256":"5af44503b48f4b65d84af1c900f2f16e6943ff68d5b7e370826792c2a549f618","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/st-francis-dam/download/capstone-brief"}],"figure":{"assetId":"project-image","kind":"photograph","alt":"Concrete ruins at the St.","caption":"Concrete ruins at the St. Francis Dam site in San Francisquito Canyon, photographed in 2012. The image shows the actual historic failure site.","credit":"Chevy111","sourceUrl":"https://commons.wikimedia.org/wiki/File:Saint_Francis_Dam_Site_2012.jpg","license":"CC BY-SA 4.0","licenseUrl":"https://creativecommons.org/licenses/by-sa/4.0","width":1280,"height":960,"imageDate":"2012-08-05 09:47:38","imageDownloadAllowed":true},"figureCaption":"Concrete ruins at the St. Francis Dam site in San Francisquito Canyon, photographed in 2012. The image shows the actual historic failure site.","qualityNotes":[],"checked":"2026-11-22","addedIn":"r13","curatedOrder":89,"referenceValues":[],"teachingFigureCaption":"Conceptual study schematic; not an as-built project drawing.","imageEvidence":{"status":"acquired","identityVerified":true,"evidenceFile":"image-provenance/st-francis-dam-commons.json","evidenceSha256":"53a2c42e8c9d7963c83e036424e0cf8fc84572d726d0e567074b0648702bb588","visualReview":"Viewed the complete publisher photograph in the final contact sheets or individually and compared it with the source identity, date, and caption. The caption distinguishes project context from the particular underground treatment or construction stage.","checked":"2026-11-22"},"localReportCount":0,"downloadBytes":414817,"sourceCount":4,"url":"/cases/st-francis-dam"},{"id":"heerlen-minewater","title":"Heerlen — heat recovery and storage in flooded mines","summary":"Flooded coal-mine workings provide thermal resources and storage for a district network. Published project accounts explain the transition from extracting mine heat to exchanging and regenerating it through building clusters.","topics":["geothermal","rock","dewatering","geoenvironmental","monitoring"],"country":"Netherlands","region":"Heerlen, Limburg","owner":"Mijnwater / Municipality of Heerlen","year":2014,"yearLabel":"Case reference year","projectType":"Design, construction and performance","methods":["Mine-water heat recovery","Coupled groundwater and heat transport","Thermal regeneration","Mine-void risk assessment"],"documentationLevel":"technical-case","design":{"availability":"partial","summary":"The project paper describes Minewater 2.0 and the STORM demonstrator documents hot, cold and reinjection wells. Mine connectivity, well condition, water chemistry and pressure limits remain site-specific inputs for any new scheme.","sourceIds":["s1","s2"]},"cost":{"availability":"not-found","summary":"A project-specific estimate, bid schedule or final account was not found in the reviewed sources.","sourceIds":[]},"schedule":{"availability":"partial","summary":"The project paper identifies pilot operation from October 2008 and the first Minewater 2.0 phase from June 2013.","sourceIds":["s1","s2"]},"records":{"availability":"partial","summary":"The STORM project records staged controller deployment and monitoring at the Heerlen demonstration site; it is not a complete mine-closure or well-acceptance dossier.","sourceIds":["s1","s2"]},"capstone":{"label":"Suggested capstone study","scope":"An original teaching brief based on the documented project. Study assumptions and student designs are separate from the built project.","brief":"Develop a hydrothermal operating concept for a flooded-mine network, with explicit mine-stability, water-quality and seasonal heat-recovery constraints.","inputs":["Trace the reported hot/cold-well arrangement and distinguish the original pilot from the later cluster network.","Assemble mine plans, hydraulic connections, pumping response and chemistry data; document gaps instead of assuming a uniform porous aquifer."],"deliverables":["Construct a reduced network water/heat balance and test thermal short-circuiting and seasonal regeneration scenarios.","Prepare well-integrity, mine-stability and water-quality monitoring plans with operating limits and contingency actions.","A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.","A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points."],"questions":["Why can a system that initially supplies heat become unsustainable if recharge and heat exchange are ignored?","How would a poorly mapped mine connection alter pumping response, thermal breakthrough and the choice of observation wells?"],"output":"Design report, calculation workbook, concept drawings, quantity schedule and construction programme."},"sources":[{"id":"s1","title":"Minewater 2.0 — project authors’ account","url":"https://www.sciencedirect.com/science/article/pii/S187661021400174X","publisher":"Verhoeven et al. / Energy Procedia","year":null,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s2","title":"Heerlen demonstration site and well/network configuration","url":"https://storm-dhc.eu/en/mijnwater-bv-site","publisher":"STORM project / VITO","year":null,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s3","title":"Heerlerheide Schacht ONIII (1).jpg","url":"https://commons.wikimedia.org/wiki/File:Heerlerheide_Schacht_ONIII_(1).jpg","publisher":"Hans Erren","year":2012,"access":"public-link","license":"CC BY-SA 3.0","notes":"Project image source. Provider-generated width-limited JPEG preview; no local crop, retouching, added text or recolouring.","checked":"2026-11-22","localAssetIds":["project-image"]}],"assets":[{"id":"schematic","title":"Conceptual study schematic","kind":"figure","fileName":"heerlen-minewater.svg","mimeType":"image/svg+xml","bytes":1057,"sha256":"6c0f3672578d66652bd772c30449ad7f24ff1dacdf6823a19f097a49f226c6ec","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/heerlen-minewater/download/schematic"},{"id":"reference-values","title":"Published reference values (CSV)","kind":"table","fileName":"heerlen-minewater-reference-values.csv","mimeType":"text/csv","bytes":532,"sha256":"a2efc312f0bbcd2b120f9231b984aff1643b05c6e92016837cfe49dfb2cbceb2","sourceId":null,"license":"Factual values transcribed with source attribution; original selection and descriptions by Foundation Design","downloadUrl":"/cases/heerlen-minewater/download/reference-values"},{"id":"project-image","title":"Heerlerheide — former Oranje-Nassau III mine shaft","kind":"project-image","fileName":"heerlen-minewater.jpg","mimeType":"image/jpeg","bytes":333440,"sha256":"baa063d001e8d1878b3fcb4bc810e00f26ce5b5768ff10ffafb48b0cde985468","sourceId":"s3","license":"CC BY-SA 3.0","width":1280,"height":648,"credit":"Hans Erren / Wikimedia Commons","sourceUrl":"https://commons.wikimedia.org/wiki/File:Heerlerheide_Schacht_ONIII_(1).jpg","licenseUrl":"https://creativecommons.org/licenses/by-sa/3.0","imageDate":"2012-08-01 18:48:42","evidenceFile":"image-provenance/heerlen-minewater-r14-source.json","evidenceSha256":"ead9774990be9695ae89799195ff0a7032b9f83c5146cdf65c8ff6331c92f048","transformations":"Provider-generated width-limited JPEG preview; no local crop, retouching, added text or recolouring.","originalUrl":"https://upload.wikimedia.org/wikipedia/commons/5/58/Heerlerheide_Schacht_ONIII_%281%29.jpg?utm_source=commons.wikimedia.org&utm_campaign=imageinfo&utm_content=original","downloadUrl":"/cases/heerlen-minewater/download/project-image","imageDownloadAllowed":true,"rightsStatus":"open-license","rightsBasis":"See the per-image provenance record and linked license; source hosting alone is not the rights basis."},{"id":"capstone-brief","title":"Capstone brief (Markdown)","kind":"brief","fileName":"heerlen-minewater-capstone.md","mimeType":"text/markdown","bytes":4155,"sha256":"3757cab5372b656f41e48fd4cc3e273c7a8e68bc26af1ec2053b87ecd31e0fde","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/heerlen-minewater/download/capstone-brief"}],"figure":{"assetId":"project-image","kind":"photograph","alt":"The marked former Oranje-Nassau III shaft in Heerlerheide, part of the mining legacy underlying the Heerlen minewater project. This is a historic mine-site feature, not a photograph of an operational heat-extraction well.","caption":"The marked former Oranje-Nassau III shaft in Heerlerheide, part of the mining legacy underlying the Heerlen minewater project. This is a historic mine-site feature, not a photograph of an operational heat-extraction well.","credit":"Hans Erren / Wikimedia Commons","sourceUrl":"https://commons.wikimedia.org/wiki/File:Heerlerheide_Schacht_ONIII_(1).jpg","license":"CC BY-SA 3.0","licenseUrl":"https://creativecommons.org/licenses/by-sa/3.0","width":1280,"height":648,"imageDate":"2012-08-01 18:48:42","preserveWholeImage":true,"imageDownloadAllowed":true,"rightsStatus":"open-license"},"figureCaption":"The marked former Oranje-Nassau III shaft in Heerlerheide, part of the mining legacy underlying the Heerlen minewater project. This is a historic mine-site feature, not a photograph of an operational heat-extraction well.","qualityNotes":[],"checked":"2026-11-22","addedIn":"r14","curatedOrder":105,"referenceValues":[{"label":"Hot-well temperature","value":28,"unit":"°C","scope":"Two hot wells in the documented STORM demonstration configuration.","sourceId":"s2","locator":"Site description","basis":"As reported by the cited project source; not a universal design input."},{"label":"Cold-well temperature","value":16,"unit":"°C","scope":"Two cold wells in the documented STORM demonstration configuration.","sourceId":"s2","locator":"Site description","basis":"As reported by the cited project source; not a universal design input."}],"teachingFigureCaption":"Conceptual study schematic; not an as-built project drawing.","imageEvidence":{"status":"acquired","identityVerified":true,"evidenceFile":"image-provenance/heerlen-minewater-r14-source.json","evidenceSha256":"ead9774990be9695ae89799195ff0a7032b9f83c5146cdf65c8ff6331c92f048","visualReview":"Reviewed the actual photograph at publication size against the file description and project identity. The caption states when the image is a site-context or historic-stage view; no diagram or substitute project image is used.","checked":"2026-11-22"},"localReportCount":0,"downloadBytes":339184,"sourceCount":3,"url":"/cases/heerlen-minewater"},{"id":"svalbard-seed-vault","title":"Svalbard Seed Vault — tunnel waterproofing and frozen ground","summary":"The Seed Vault upgrade replaced its access tunnel with a watertight concrete structure and moved heat-producing services. The construction account includes artificial ground freezing to support the replacement works.","topics":["cold-regions","tunnels","ground-improvement","seepage","rock","delivery"],"country":"Norway","region":"Longyearbyen, Svalbard","owner":"Norwegian Ministry of Agriculture and Food / Statsbygg","year":2019,"yearLabel":"Case reference year","projectType":"Design, construction and performance","methods":["Artificial ground freezing","Tunnel waterproofing","Thermal disturbance","Groundwater exclusion"],"documentationLevel":"technical-case","design":{"availability":"partial","summary":"Owner sources describe the 2016–2019 upgrade and freezing used during tunnel construction. The seed-storage chambers and the entrance tunnel have different thermal and groundwater functions; do not treat the entire facility as one homogeneous frozen-ground boundary.","sourceIds":["s1","s2","s3"]},"cost":{"availability":"not-found","summary":"A project-specific estimate, bid schedule or final account was not found in the reviewed sources.","sourceIds":[]},"schedule":{"availability":"partial","summary":"The owner identifies the main upgrade period as 2016–2019; the 2018 construction update describes the work while it was in progress.","sourceIds":["s1","s2","s3"]},"records":{"availability":"partial","summary":"The owner reports a waterproofed entrance tunnel and upgraded cooling. Published descriptions do not provide the full freeze-pipe commissioning records or as-built waterproofing details.","sourceIds":["s1","s2","s3"]},"capstone":{"label":"Suggested capstone study","scope":"An original teaching brief based on the documented project. Study assumptions and student designs are separate from the built project.","brief":"Plan a watertight tunnel replacement in warming permafrost, combining temporary frozen-ground support with a permanent drainage, waterproofing and thermal strategy.","inputs":["Map the access tunnel, rock chambers, service heat sources and surface-water pathways from the owner descriptions.","Define study values for unfrozen permeability, ice content, thermal properties and freezing-system temperature, flagging them as assumptions."],"deliverables":["Estimate freeze-wall development and thaw sensitivity around the excavation, then assess leakage and uplift for the permanent tunnel.","Prepare freezing verification holes, temperature monitoring, excavation hold points and a seasonal surface-water diversion plan.","A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.","A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points."],"questions":["Why does removing internal heat generation help even when the final tunnel lining is designed to be watertight?","What measurements would establish adequate frozen-ground continuity before excavation without confusing cold air with frozen soil?"],"output":"Design report, calculation workbook, concept drawings, quantity schedule and construction programme."},"sources":[{"id":"s1","title":"Construction improvements and temporary ground freezing","url":"https://www.seedvault.no/2018/09/04/seed-vault-construction-improvements-proceed-as-planned/","publisher":"Svalbard Global Seed Vault / Norwegian Ministry of Agriculture and Food","year":null,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s2","title":"Purpose, operations and 2016–2019 upgrade","url":"https://www.seedvault.no/about/purpose-operations-and-organisation/","publisher":"Svalbard Global Seed Vault","year":null,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s3","title":"Facility operation and tunnel arrangement","url":"https://www.nordgen.org/our-work/svalbard-global-seed-vault/frequently-asked-questions/","publisher":"NordGen","year":null,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s4","title":"Svalbard Global Seed Vault Exterior 2020.jpg","url":"https://commons.wikimedia.org/wiki/File:Svalbard_Global_Seed_Vault_Exterior_2020.jpg","publisher":"Cierra Martin for Crop Trust","year":2020,"access":"public-link","license":"CC BY-SA 2.0","notes":"Project image source. Provider-generated width-limited JPEG preview; no local crop, retouching, added text or recolouring.","checked":"2026-11-22","localAssetIds":["project-image"]}],"assets":[{"id":"schematic","title":"Conceptual study schematic","kind":"figure","fileName":"svalbard-seed-vault.svg","mimeType":"image/svg+xml","bytes":968,"sha256":"90bd9d5f0e906d8c86b1dbf936087013600fc464568e53625a08db29592daa87","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/svalbard-seed-vault/download/schematic"},{"id":"project-image","title":"Svalbard Global Seed Vault — exterior in 2020","kind":"project-image","fileName":"svalbard-seed-vault.jpg","mimeType":"image/jpeg","bytes":345849,"sha256":"3514d4606ff689bef0b68899a77237a3b3cf4225b33b29b32b01f7ab01657dc8","sourceId":"s4","license":"CC BY-SA 2.0","width":1280,"height":913,"credit":"Cierra Martin for Crop Trust / Wikimedia Commons","sourceUrl":"https://commons.wikimedia.org/wiki/File:Svalbard_Global_Seed_Vault_Exterior_2020.jpg","licenseUrl":"https://creativecommons.org/licenses/by-sa/2.0","imageDate":"2020-02-25","evidenceFile":"image-provenance/svalbard-seed-vault-r14-source.json","evidenceSha256":"a74e8e13c3cc9218a920f57b5674c8c671e2a53fa45916765d7eb1b5f9620ccb","transformations":"Provider-generated width-limited JPEG preview; no local crop, retouching, added text or recolouring.","originalUrl":"https://upload.wikimedia.org/wikipedia/commons/e/e3/Svalbard_Global_Seed_Vault_Exterior_2020.jpg?utm_source=commons.wikimedia.org&utm_campaign=imageinfo&utm_content=original","downloadUrl":"/cases/svalbard-seed-vault/download/project-image","imageDownloadAllowed":true,"rightsStatus":"open-license","rightsBasis":"See the per-image provenance record and linked license; source hosting alone is not the rights basis."},{"id":"capstone-brief","title":"Capstone brief (Markdown)","kind":"brief","fileName":"svalbard-seed-vault-capstone.md","mimeType":"text/markdown","bytes":3964,"sha256":"7be9dac2dda47c60c428fcb9c412c0a4663488f05b6fa991da6346122ad9c1cb","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/svalbard-seed-vault/download/capstone-brief"}],"figure":{"assetId":"project-image","kind":"photograph","alt":"The entrance to the Svalbard Global Seed Vault in February 2020, after the 2016–2019 upgrade period. The photograph shows the actual facility; buried tunnel details are documented by the linked owner sources.","caption":"The entrance to the Svalbard Global Seed Vault in February 2020, after the 2016–2019 upgrade period. The photograph shows the actual facility; buried tunnel details are documented by the linked owner sources.","credit":"Cierra Martin for Crop Trust / Wikimedia Commons","sourceUrl":"https://commons.wikimedia.org/wiki/File:Svalbard_Global_Seed_Vault_Exterior_2020.jpg","license":"CC BY-SA 2.0","licenseUrl":"https://creativecommons.org/licenses/by-sa/2.0","width":1280,"height":913,"imageDate":"2020-02-25","preserveWholeImage":true,"imageDownloadAllowed":true,"rightsStatus":"open-license"},"figureCaption":"The entrance to the Svalbard Global Seed Vault in February 2020, after the 2016–2019 upgrade period. The photograph shows the actual facility; buried tunnel details are documented by the linked owner sources.","qualityNotes":[],"checked":"2026-11-22","addedIn":"r14","curatedOrder":106,"referenceValues":[],"teachingFigureCaption":"Conceptual study schematic; not an as-built project drawing.","imageEvidence":{"status":"acquired","identityVerified":true,"evidenceFile":"image-provenance/svalbard-seed-vault-r14-source.json","evidenceSha256":"a74e8e13c3cc9218a920f57b5674c8c671e2a53fa45916765d7eb1b5f9620ccb","visualReview":"Reviewed the actual photograph at publication size against the file description and project identity. The caption states when the image is a site-context or historic-stage view; no diagram or substitute project image is used.","checked":"2026-11-22"},"localReportCount":0,"downloadBytes":350781,"sourceCount":4,"url":"/cases/svalbard-seed-vault"},{"id":"berkeley-pit","title":"Berkeley Pit — mine flooding and hydraulic containment","summary":"The flooded open pit and connected underground mine workings require water-level management and treatment. Public monitoring records link hydraulic containment with an ongoing remediation operation.","topics":["geoenvironmental","dewatering","rock","seepage","monitoring"],"country":"United States","region":"Butte, Montana","owner":"EPA oversight / responsible mining parties","year":2025,"yearLabel":"Case reference year","projectType":"Design, construction and performance","methods":["Mine-water balance","Hydraulic containment","Pumping and treatment","Monitoring interpretation"],"documentationLevel":"technical-report","design":{"availability":"partial","summary":"EPA identifies the Butte Mine Flooding operable unit and continuing treatment. The official monitoring archive provides dated discharge reports; pit water, connected mine water and surrounding aquifers must be represented as a connected system.","sourceIds":["s1","s2","s3"]},"cost":{"availability":"not-found","summary":"A project-specific estimate, bid schedule or final account was not found in the reviewed sources.","sourceIds":[]},"schedule":{"availability":"not-found","summary":"A dated project programme was not found in the reviewed sources; develop a study schedule from the documented method.","sourceIds":[]},"records":{"availability":"partial","summary":"Public discharge reports and EPA status material document continuing treatment and monitoring. They are dated operational records, not evidence that treatment can be discontinued.","sourceIds":["s1","s2","s3"]},"capstone":{"label":"Suggested capstone study","scope":"An original teaching brief based on the documented project. Study assumptions and student designs are separate from the built project.","brief":"Develop a water-balance and containment assessment for the flooded mine, with sensitivity to uncertain inflow and temporary treatment interruption.","inputs":["Use a dated monthly monitoring report for observed discharge and compliance data.","Identify pit and mine-water levels, the relevant control elevation and its datum, and unmeasured groundwater exchanges."],"deliverables":["Build a time-dependent storage/pumping model that distinguishes observations, calibrated flows and conservative assumptions.","Develop outage scenarios, monitoring triggers and a recovery pumping strategy with treatment-capacity constraints.","A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.","A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points."],"questions":["How would a stable pit level conceal a change in groundwater capture or treatment demand?","What evidence is needed before comparing a reported control elevation with survey data recorded in a different vertical datum?"],"output":"Design report, calculation workbook, concept drawings, quantity schedule and construction programme."},"sources":[{"id":"s1","title":"Current site status — Butte Mine Flooding OU3","url":"https://www.epa.gov/butte/current-site-status","publisher":"U.S. Environmental Protection Agency","year":null,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s2","title":"January 2025 monthly discharge monitoring report","url":"https://digitalcommons.mtech.edu/superfund_silverbowbutte/1282/","publisher":"Thompson and Griffis / Montana Technological University archive","year":null,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s3","title":"Berkeley Pit water-treatment explanation","url":"https://pitwatch.org/learn/water-treatment/","publisher":"PitWatch / Butte Mine Flooding information programme","year":null,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s4","title":"2013 Berkeley Pit, Butte, Montana (1).jpg","url":"https://commons.wikimedia.org/wiki/File:2013_Berkeley_Pit,_Butte,_Montana_(1).jpg","publisher":"Chris06","year":2013,"access":"public-link","license":"CC BY-SA 4.0","notes":"Project image source. Provider-generated width-limited JPEG preview; no local crop, retouching, added text or recolouring.","checked":"2026-11-22","localAssetIds":["project-image"]}],"assets":[{"id":"schematic","title":"Conceptual study schematic","kind":"figure","fileName":"berkeley-pit.svg","mimeType":"image/svg+xml","bytes":991,"sha256":"26222485f74844ee89b3f605791d3913e3b1100909062100b32642ad290c3b48","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/berkeley-pit/download/schematic"},{"id":"project-image","title":"Berkeley Pit — flooded mine excavation","kind":"project-image","fileName":"berkeley-pit.jpg","mimeType":"image/jpeg","bytes":297779,"sha256":"27b5d65db09c4b1d2ba719119c2740d3cb439ae5250b4e5c9ace6f2032d4f473","sourceId":"s4","license":"CC BY-SA 4.0","width":1280,"height":903,"credit":"Chris06 / Wikimedia Commons","sourceUrl":"https://commons.wikimedia.org/wiki/File:2013_Berkeley_Pit,_Butte,_Montana_(1).jpg","licenseUrl":"https://creativecommons.org/licenses/by-sa/4.0","imageDate":"2013-08-03","evidenceFile":"image-provenance/berkeley-pit-r14-source.json","evidenceSha256":"8258faad4b0bffb33e50f379f8fc7e4acf937b5946609c3dc163c7733f9ca2b8","transformations":"Provider-generated width-limited JPEG preview; no local crop, retouching, added text or recolouring.","originalUrl":"https://upload.wikimedia.org/wikipedia/commons/a/a8/2013_Berkeley_Pit%2C_Butte%2C_Montana_%281%29.jpg?utm_source=commons.wikimedia.org&utm_campaign=imageinfo&utm_content=original","downloadUrl":"/cases/berkeley-pit/download/project-image","imageDownloadAllowed":true,"rightsStatus":"open-license","rightsBasis":"See the per-image provenance record and linked license; source hosting alone is not the rights basis."},{"id":"capstone-brief","title":"Capstone brief (Markdown)","kind":"brief","fileName":"berkeley-pit-capstone.md","mimeType":"text/markdown","bytes":3653,"sha256":"a8e1cd9696e424949050088262199d4660028a778e7daa8a242dd143c1df072d","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/berkeley-pit/download/capstone-brief"}],"figure":{"assetId":"project-image","kind":"photograph","alt":"The Berkeley Pit in Butte, Montana, photographed in 2013. The image shows the actual flooded pit; water-level controls and treatment performance should be read from the dated monitoring records.","caption":"The Berkeley Pit in Butte, Montana, photographed in 2013. The image shows the actual flooded pit; water-level controls and treatment performance should be read from the dated monitoring records.","credit":"Chris06 / Wikimedia Commons","sourceUrl":"https://commons.wikimedia.org/wiki/File:2013_Berkeley_Pit,_Butte,_Montana_(1).jpg","license":"CC BY-SA 4.0","licenseUrl":"https://creativecommons.org/licenses/by-sa/4.0","width":1280,"height":903,"imageDate":"2013-08-03","preserveWholeImage":true,"imageDownloadAllowed":true,"rightsStatus":"open-license"},"figureCaption":"The Berkeley Pit in Butte, Montana, photographed in 2013. The image shows the actual flooded pit; water-level controls and treatment performance should be read from the dated monitoring records.","qualityNotes":[],"checked":"2026-11-22","addedIn":"r14","curatedOrder":111,"referenceValues":[],"teachingFigureCaption":"Conceptual study schematic; not an as-built project drawing.","imageEvidence":{"status":"acquired","identityVerified":true,"evidenceFile":"image-provenance/berkeley-pit-r14-source.json","evidenceSha256":"8258faad4b0bffb33e50f379f8fc7e4acf937b5946609c3dc163c7733f9ca2b8","visualReview":"Reviewed the actual photograph at publication size against the file description and project identity. The caption states when the image is a site-context or historic-stage view; no diagram or substitute project image is used.","checked":"2026-11-22"},"localReportCount":0,"downloadBytes":302423,"sourceCount":4,"url":"/cases/berkeley-pit"},{"id":"yeager-airport","title":"Yeager Airport — reinforced-slope failure and degraded rock","summary":"The reinforced slope supporting a runway extension failed in 2015. Published investigations examine the fill–rock interface, material strength selection and global failure mechanisms, offering a strong forensic capstone.","topics":["reinforced-soil","slopes","rock","laboratory-testing","site-investigation","monitoring"],"country":"United States","region":"Charleston, West Virginia","owner":"Central West Virginia Regional Airport Authority","year":2015,"yearLabel":"Case reference year","projectType":"Failure investigation and lessons","methods":["Reinforced-slope stability","Fully softened and residual strength","Degraded sedimentary rock","Inverse analysis"],"documentationLevel":"forensic-study","design":{"availability":"partial","summary":"The author studies discuss construction, performance and post-failure testing. The reinforced-slope height is reported differently across papers; retain the geometry and datum of the particular section being analysed instead of merging those values.","sourceIds":["s1","s2","s3"]},"cost":{"availability":"not-found","summary":"A project-specific estimate, bid schedule or final account was not found in the reviewed sources.","sourceIds":[]},"schedule":{"availability":"partial","summary":"The failure occurred on 12 March 2015 after several years of service. The published papers separately describe construction and the observed pre-failure movements.","sourceIds":["s1","s2","s3"]},"records":{"availability":"partial","summary":"Post-failure investigation and analyses are documented; these sources are not a complete record of the later repair and acceptance programme.","sourceIds":["s1","s2","s3"]},"capstone":{"label":"Suggested capstone study","scope":"An original teaching brief based on the documented project. Study assumptions and student designs are separate from the built project.","brief":"Reconstruct a documented failure section and compare competing strength and groundwater assumptions against the observed failure geometry.","inputs":["Extract one internally consistent cross-section, foundation preparation detail and chronology from the selected author paper.","Separate coarse reinforced-fill test results from softened or residual strengths at the fill–rock interface, recording drainage and sample scale."],"deliverables":["Compare internal, compound and global mechanisms with sensitivity to interface strength and pore pressure.","Prepare an improved investigation, construction-observation and movement-trigger plan, clearly distinguished from the actual historical design.","A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.","A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points."],"questions":["Why can strong geogrid and competent reinforced fill fail to prevent a mechanism controlled by the underlying weathered-rock interface?","What would make a back-calculated strength plausible as a material property, rather than merely compensating for an incorrect geometry or groundwater model?"],"output":"Design report, calculation workbook, concept drawings, quantity schedule and construction programme."},"sources":[{"id":"s1","title":"Case history: failure of the reinforced soil slope at Yeager Airport","url":"https://ascelibrary.org/doi/10.1061/%28ASCE%29GT.1943-5606.0002430","publisher":"VandenBerge, Valentine, Brandon and Wright / ASCE","year":null,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s2","title":"Case history on failure of a 67 m tall reinforced soil slope","url":"https://www.sciencedirect.com/science/article/pii/S0266114420300686","publisher":"Collin and coauthors / Geotextiles and Geomembranes","year":null,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s3","title":"Stability and stress-deformation analyses — author-hosted paper","url":"https://www.thecollingroup.com/wp-content/uploads/2021/01/Collin-Yeager-Failure-JGGE-ASCE-GT.1943-5606.0002454.pdf","publisher":"Investigation authors / The Collin Group","year":null,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s4","title":"KCRW airport aerial 20261020.jpg","url":"https://commons.wikimedia.org/wiki/File:KCRW_airport_aerial_20261020.jpg","publisher":"Designism","year":2026,"access":"public-link","license":"CC0","notes":"Project image source. Provider-generated width-limited JPEG preview; no local crop, retouching, added text or recolouring.","checked":"2026-11-22","localAssetIds":["project-image"]}],"assets":[{"id":"schematic","title":"Conceptual study schematic","kind":"figure","fileName":"yeager-airport.svg","mimeType":"image/svg+xml","bytes":1121,"sha256":"0e13d7f91be9a4043d6221c6dd16082f3a79a21a846b2c1d4395e0bb04939f37","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/yeager-airport/download/schematic"},{"id":"reference-values","title":"Published reference values (CSV)","kind":"table","fileName":"yeager-airport-reference-values.csv","mimeType":"text/csv","bytes":794,"sha256":"743239327bd7a5bc43922859fa94090a2465f88f69d96df2d76f0f2ff4fc22f7","sourceId":null,"license":"Factual values transcribed with source attribution; original selection and descriptions by Foundation Design","downloadUrl":"/cases/yeager-airport/download/reference-values"},{"id":"project-image","title":"Yeager Airport — aerial site context in 2026","kind":"project-image","fileName":"yeager-airport.jpg","mimeType":"image/jpeg","bytes":192611,"sha256":"e81b78a1347994e6c2a868aa8ab7749e6e273bdd01e3b9cdf73809b3c388a605","sourceId":"s4","license":"CC0","width":1280,"height":867,"credit":"Designism / Wikimedia Commons","sourceUrl":"https://commons.wikimedia.org/wiki/File:KCRW_airport_aerial_20261020.jpg","licenseUrl":"https://creativecommons.org/publicdomain/zero/1.0/deed.en","imageDate":"2026-10-20 13:24:53","evidenceFile":"image-provenance/yeager-airport-r14-source.json","evidenceSha256":"11ad0740552021430cbcd470ca63fca0b86f43ac87d9d6aba8b379f3dc393172","transformations":"Provider-generated width-limited JPEG preview; no local crop, retouching, added text or recolouring.","originalUrl":"https://upload.wikimedia.org/wikipedia/commons/c/cd/KCRW_airport_aerial_20261020.jpg?utm_source=commons.wikimedia.org&utm_campaign=imageinfo&utm_content=original","downloadUrl":"/cases/yeager-airport/download/project-image","originalSha1":"f179194a5d2d62c05b3a6400727fc85453c6caaf","imageDownloadAllowed":true,"rightsStatus":"open-license","rightsBasis":"See the per-image provenance record and linked license; source hosting alone is not the rights basis."},{"id":"capstone-brief","title":"Capstone brief (Markdown)","kind":"brief","fileName":"yeager-airport-capstone.md","mimeType":"text/markdown","bytes":4809,"sha256":"f2ee34dc662632c6f866232936ea9c60202f43c4e59d54196c0d3d15c610fa5d","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/yeager-airport/download/capstone-brief"}],"figure":{"assetId":"project-image","kind":"photograph","alt":"Yeager Airport photographed on 20 October 2026. This later site view is context for the 2015 reinforced-slope failure; it is not an image of the failure itself or a reconstruction drawing.","caption":"Yeager Airport photographed on 20 October 2026. This later site view is context for the 2015 reinforced-slope failure; it is not an image of the failure itself or a reconstruction drawing.","credit":"Designism / Wikimedia Commons","sourceUrl":"https://commons.wikimedia.org/wiki/File:KCRW_airport_aerial_20261020.jpg","license":"CC0","licenseUrl":"https://creativecommons.org/publicdomain/zero/1.0/deed.en","width":1280,"height":867,"imageDate":"2026-10-20 13:24:53","preserveWholeImage":true,"imageDownloadAllowed":true,"rightsStatus":"open-license"},"figureCaption":"Yeager Airport photographed on 20 October 2026. This later site view is context for the 2015 reinforced-slope failure; it is not an image of the failure itself or a reconstruction drawing.","qualityNotes":["The 2026 aerial photograph is a later view of the actual airport, not a photograph of the 2015 collapse.","Published heights differ by section/definition. The study must cite its selected source geometry."],"checked":"2026-11-22","addedIn":"r14","curatedOrder":117,"referenceValues":[{"label":"Slope height stated by Collin et al.","value":67,"unit":"m","scope":"Reinforced-soil slope height in the Geotextiles and Geomembranes case-history title; retain that paper’s definition.","sourceId":"s2","locator":"Article title and case description","basis":"As reported by the cited project source; not a universal design input."},{"label":"Slope height stated by VandenBerge et al.","value":73,"unit":"m","scope":"Height used in the ASCE case-history description; consult geometry and reference elevations before comparing with 67 m.","sourceId":"s1","locator":"Case-history description","basis":"Source-specific geometry definition. The two published heights are not averaged or silently treated as interchangeable."}],"teachingFigureCaption":"Conceptual study schematic; not an as-built project drawing.","imageEvidence":{"status":"acquired","identityVerified":true,"evidenceFile":"image-provenance/yeager-airport-r14-source.json","evidenceSha256":"11ad0740552021430cbcd470ca63fca0b86f43ac87d9d6aba8b379f3dc393172","visualReview":"Reviewed the actual photograph at publication size against the file description and project identity. The caption states when the image is a site-context or historic-stage view; no diagram or substitute project image is used.","checked":"2026-11-22"},"localReportCount":0,"downloadBytes":199335,"sourceCount":4,"url":"/cases/yeager-airport"}]}