# Center Hill Dam — grouting, cutoff wall and stabilizing berm

Case reference year: 2020 | Location: DeKalb County, Tennessee, United States

A staged rehabilitation treated foundation seepage and auxiliary-dam risks using grouting, a deep cutoff wall and a roller-compacted-concrete berm.

## Suggested capstone study

An original teaching brief based on the documented project. Study assumptions and student designs are separate from the built project.

Develop a risk-based sequence of dam repairs in which initial grouting also informs the later cutoff design.

### Inputs to assemble

- Extract phase scope, wall depth and published contract-period information.
- Identify the piezometric and geological evidence needed to assess each repaired failure mode.

### Deliverables

- Prepare a seepage/stability failure-mode map and an investigation-to-construction decision process.
- Compare a single-stage programme with the documented phased strategy.
- A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.
- A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points.

### Review questions

- Which site data control the decision, and what additional investigation would reduce uncertainty?
- How would the proposed solution change under the stated sensitivity cases, construction constraints and performance limits?

## Published project information

### Design — partial

USACE describes three major repair phases and their completed components; detailed construction plans are not attached to the completion release.

### Cost information — partial

The completion release reports $353 million overall, with $107 million grouting, $122 million cutoff and $50 million berm contracts; scopes differ from the programme total.

### Schedule information — partial

Reported phases were grouting in 2008–2010, cutoff in 2012–2015 and final berm completion celebrated in July 2020.

### Completion and records — partial

The USACE release documents the final repair phase and constructed features.

## Project image

The roller-compacted-concrete berm at the Center Hill auxiliary dam, shown in the USACE project-completion image collection published in July 2020.

Credit: Leon Roberts / U.S. Army Corps of Engineers
Image source: https://www.dvidshub.net/image/6260111/berm-construction-completes-last-repair-phase-dam-rehabilitation
Image rights: Public domain — U.S. federal government work — https://www.dvidshub.net/about/copyright

## Sources

- Berm construction completes last repair phase for dam rehabilitation (USACE; 2020): https://www.usace.army.mil/Media/News-Releases/News-Release-Article-View/Article/2261687/berm-construction-completes-last-repair-phase-for-dam-rehabilitation/
- Center Hill auxiliary-dam RCC berm — published image and source (DVIDS / U.S. Army Corps of Engineers; 2020): https://www.dvidshub.net/image/6260111/berm-construction-completes-last-repair-phase-dam-rehabilitation

Sources checked: 2026-11-22. This brief is an original teaching aid. Source rights remain with their respective holders.