# Changi East reclamation — instrumented vertical-drain design

Case reference year: 2005 | Location: Eastern Singapore, Singapore

The reclamation programme used prefabricated vertical drains to accelerate consolidation of marine clay. Its investigators publish pilot trials, specialized testing and interpretation of settlement and pore-pressure records.

## Suggested capstone study

An original teaching brief based on the documented project. Study assumptions and student designs are separate from the built project.

Select drain spacing and surcharge duration for a reclamation cell using both settlement and pore-pressure acceptance measures.

### Inputs to assemble

- Extract a single pilot-cell stratigraphy, drain spacing and loading history from the papers.
- Identify horizontal consolidation coefficients and laboratory versus field scale differences.

### Deliverables

- Calculate consolidation time with drain smear and well resistance sensitivities.
- Create a surcharge-removal decision that reconciles settlement and piezometer observations.
- A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.
- A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points.

### Review questions

- Why can settlement-based and pore-pressure-based degrees of consolidation disagree?
- What evidence would justify changing drain spacing after a pilot trial?

## Published project information

### Design — partial

The papers provide field and laboratory characterization and consolidation-monitoring methods for the historic reclamation phases. They should not be mistaken for current Terminal 5 construction records.

### Cost information — not-found

A project-specific estimate, bid schedule or final account was not found in the reviewed sources.

### Schedule information — partial

The research account covers the historic reclamation phases completed by 2005, not the schedule of present airport expansion.

### Completion and records — not-found

Complete as-built drawings and acceptance records were not found in the reviewed sources.

## Project image

The Changi East slurry pond before reclamation, reproduced from Figure 2 of the original 2009 engineering paper. This is the historic reclamation programme, not current airport expansion work.

Credit: J. Chu, M. W. Bo and A. Arulrajah / ICE Geotechnical Engineering (2009), Figure 2
Image source: https://doi.org/10.1680/geng.2009.162.1.13
Image rights: No open reuse license verified; original copyright retained — https://doi.org/10.1680/geng.2009.162.1.13

## Sources

- Soil improvement works for an offshore land reclamation (Project investigators / ICE Geotechnical Engineering; date not stated): https://doi.org/10.1680/geng.2009.162.1.21
- Research-oriented ground investigation at Changi (Project investigators / ICE Geotechnical Research; date not stated): https://www.sciencedirect.com/org/science/article/pii/S205261561700014X
- Reclamation of a slurry pond in Singapore (Institution of Civil Engineers; date not stated): https://doi.org/10.1680/geng.2009.162.1.13

Sources checked: 2026-11-22. This brief is an original teaching aid. Source rights remain with their respective holders.