# Hong Kong International Airport — foundations across rock and reclamation

Case reference year: 1998 | Location: Chek Lap Kok, China

The original airport terminal crosses former island rock and newly reclaimed ground. The designer describes a range of foundation types adapted to these contrasting conditions; a contemporaneous paper documents vibrocompaction of marine sand fill.

## Suggested capstone study

An original teaching brief based on the documented project. Study assumptions and student designs are separate from the built project.

Design the transition between a shallow foundation on rock and a piled concourse on reclaimed deposits.

### Inputs to assemble

- Distinguish original rock, weathered zones and reclaimed sand in a project ground model.
- Extract the reported investigation and density-verification approach from the vibrocompaction paper.

### Deliverables

- Compare settlement and construction risk for two terminal foundation zones.
- Define CPT acceptance criteria and an interface detail for differential movement.
- A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.
- A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points.

### Review questions

- Which discontinuity is more important: the former shoreline or the top of competent rock?
- How can improvement verification avoid hiding local loose pockets behind an average density?

## Published project information

### Design — partial

The sources describe actual foundation choices and field characterization. They do not provide a single uniform soil profile for the whole airport.

### Cost information — not-found

A project-specific estimate, bid schedule or final account was not found in the reviewed sources.

### Schedule information — not-found

A dated project programme was not found in the reviewed sources; develop a study schedule from the documented method.

### Completion and records — not-found

Complete as-built drawings and acceptance records were not found in the reviewed sources.

## Project image

Hong Kong International Airport at Chek Lap Kok viewed from the air. The photograph shows the actual airport platform; ground improvement and terminal foundation zones are documented separately.

Credit: PSnyan
Image source: https://commons.wikimedia.org/wiki/File:Hong_Kong_Internatinal_Airport_from_Air(Chek_Lap_Kok,%E9%A6%99%E6%B8%AF%E5%9C%8B%E9%9A%9B%E7%A9%BA%E6%B8%AF)_-_panoramio.jpg
Image rights: CC BY-SA 3.0 — https://creativecommons.org/licenses/by-sa/3.0

## Sources

- Airport design and construction history (Mott MacDonald; date not stated): https://www.mottmac.com/en/projects/hong-kong-international-the-airport-that-changed-the-world/
- Review of vibrocompaction at Hong Kong’s new airport (Petra Berner, Airport Authority / HKIE Transactions; date not stated): https://www.tandfonline.com/doi/abs/10.1080/1023697X.1998.10667731
- Hong Kong Internatinal Airport from Air(Chek Lap Kok,香港國際空港) - panoramio.jpg — image and reuse license (Wikimedia Commons / PSnyan; date not stated): https://commons.wikimedia.org/wiki/File:Hong_Kong_Internatinal_Airport_from_Air(Chek_Lap_Kok,%E9%A6%99%E6%B8%AF%E5%9C%8B%E9%9A%9B%E7%A9%BA%E6%B8%AF)_-_panoramio.jpg

Sources checked: 2026-11-22. This brief is an original teaching aid. Source rights remain with their respective holders.