# Clearwater Dam — karst pretreatment and a hanging cutoff

Case reference year: 2011 | Location: Wayne and Reynolds counties, Missouri, United States

A sinkhole prompted foundation exploration and grouting before construction of a deep seepage cutoff. The owner explains why treating solution-enlarged fractures was necessary for slurry-supported excavation.

## Suggested capstone study

An original teaching brief based on the documented project. Study assumptions and student designs are separate from the built project.

Design a pretreatment and cutoff-wall sequence for a dam with connected karst features.

### Inputs to assemble

- Extract the reported seepage problem and the relationship between pretreatment and panel excavation.
- Define a study range for rock permeability and connected-void sizes.

### Deliverables

- Compare seepage paths around a hanging cutoff and through a locally defective panel.
- Specify staged grouting, slurry-loss response and test-panel acceptance requirements.
- A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.
- A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points.

### Review questions

- Why can grouting be necessary even when a cutoff wall is the main permanent barrier?
- How should treatment change when drilling loses circulation in a solution feature?

## Published project information

### Design — partial

USACE’s rehabilitation account describes the grouting sequence, epikarst treatment and cutoff construction. Its forecast of later completion is retained as a forecast rather than a final-account statement.

### Cost information — partial

The owner page forecast approximately $240 million for the overall rehabilitation. It is not presented here as a verified final account.

### Schedule information — partial

USACE records placement of the final cutoff panel on 6 December 2011; the page’s remaining-work milestones were forecasts.

### Completion and records — not-found

Complete as-built drawings and acceptance records were not found in the reviewed sources.

## Project image

Aerial view of Clearwater Lake Dam in Missouri during the rehabilitation works, from Keller’s project account. The photograph shows construction along the dam crest.

Credit: Keller / Keller Management Services, LLC
Image source: https://www.keller-na.com/projects/clearwater-lake-dam
Image rights: No open reuse license verified; original copyright retained — https://www.keller-na.com/projects/clearwater-lake-dam

## Sources

- Clearwater major rehabilitation (USACE Little Rock District; date not stated): https://www.swl.usace.army.mil/Missions/Civil-Works/Program-and-Project-Management/Clearwater-Major-Rehab/
- Cutoff-wall construction account (Keller; date not stated): https://www.keller-na.com/projects/clearwater-lake-dam

Sources checked: 2026-11-22. This brief is an original teaching aid. Source rights remain with their respective holders.