# ETH Hönggerberg — seasonal borehole heat storage

Case reference year: 2025 | Location: Zurich, Switzerland

The campus anergy grid balances heating and cooling through buried borehole fields. Its documented HC4 expansion provides a practical study of thermal interference, drilling access and staged commissioning.

## Suggested capstone study

An original teaching brief based on the documented project. Study assumptions and student designs are separate from the built project.

Develop a phased borehole-field expansion for an operating campus and test whether spacing, ground properties and annual heat imbalance control the design.

### Inputs to assemble

- Use the published HC4 depth, spacing and probe counts; assemble an explicitly labelled study load series for heating and cooling.
- Identify borehole logs, groundwater flow, thermal conductivity and borehole-resistance measurements still needed before design.

### Deliverables

- Compare a line-source screening calculation with a multi-borehole response model under balanced and unbalanced annual loads.
- Lay out drilling access, buried services, grouting verification, commissioning tests and long-term temperature monitoring.
- A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.
- A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points.

### Review questions

- How would persistent net heat injection change performance even if the first operating year meets the heating and cooling demand?
- What additional thermal-response or groundwater observations would justify reducing uncertainty at the 5 m borehole spacing?

## Published project information

### Design — partial

ETH documents 160 additional probes at 200 m depth on a 5 m grid, beside an existing field of 126 probes. The published project description supports layout and heat-balance studies; it does not supply a complete thermal-response test dataset.

### Cost information — not-found

A project-specific estimate, bid schedule or final account was not found in the reviewed sources.

### Schedule information — partial

The owner dates HC4 expansion drilling to October 2024–May 2025 and operational handover to July 2025. Later proposed fields are outside this completed expansion.

### Completion and records — partial

The owner confirms connection of the enlarged HC4 field to the campus network; continuous raw operating data and final drilling records were not provided on the reviewed pages.

## Published reference values

Use each value only within its stated scope. Reported costs have not been escalated or adjusted for inflation. These are source facts, not student design assumptions.

| Quantity | Value | Unit | Scope | Source locator |
| --- | ---: | --- | --- | --- |
| Added HC4 probes | 160 | probes | HC4 expansion drilled October 2024–May 2025. | [HC4 expansion description](https://ethz.ch/staffnet/en/news-and-events/internal-news/archive/2025/08/hoenggerberg-campus-becomes-more-sustainable-above-and-below-ground.html) |
| Reported probe depth | 200 | m | New HC4 geothermal probes; do not infer the full site stratigraphy. | [HC4 expansion description](https://ethz.ch/staffnet/en/news-and-events/internal-news/archive/2025/08/hoenggerberg-campus-becomes-more-sustainable-above-and-below-ground.html) |
| Reported grid spacing | 5 | m | Spacing stated for the HC4 expansion. | [HC4 expansion description](https://ethz.ch/staffnet/en/news-and-events/internal-news/archive/2025/08/hoenggerberg-campus-becomes-more-sustainable-above-and-below-ground.html) |
| Existing HC4 probes | 126 | probes | Pre-expansion field, distinct from the 160 additional probes. | [HC4 expansion description](https://ethz.ch/staffnet/en/news-and-events/internal-news/archive/2025/08/hoenggerberg-campus-becomes-more-sustainable-above-and-below-ground.html) |

## Project image

The ETH Hönggerberg campus, where the anergy grid exchanges heat with borehole fields. This site-context photograph does not show the buried HC4 boreholes.

Credit: Balise42 / Wikimedia Commons
Image source: https://commons.wikimedia.org/wiki/File:ETH_H%C3%B6nggerberg_campus,_seen_from_H%C3%B6nggerbergstrasse.jpg
Image rights: CC BY 4.0 — https://creativecommons.org/licenses/by/4.0

## Sources

- HC4 geothermal probe-field expansion and commissioning (ETH Zurich Real Estate Management; date not stated): https://ethz.ch/staffnet/en/news-and-events/internal-news/archive/2025/08/hoenggerberg-campus-becomes-more-sustainable-above-and-below-ground.html
- Energy supply and the campus anergy grid (ETH Zurich; date not stated): https://ethz.ch/en/the-eth-zurich/organisation/departments/engineering-and-systems/energie.html
- ETH Hönggerberg campus, seen from Hönggerbergstrasse.jpg (Balise42; 2023): https://commons.wikimedia.org/wiki/File:ETH_H%C3%B6nggerberg_campus,_seen_from_H%C3%B6nggerbergstrasse.jpg

Sources checked: 2026-11-22. This brief is an original teaching aid. Source rights remain with their respective holders.