# Eurasia Tunnel — high-pressure mixed-ground TBM crossing

Case reference year: 2016 | Location: Bosphorus, Istanbul, Türkiye

The road tunnel passes through rock and marine sediments at high water pressure. The designers describe slurry-shield excavation, specialized lining details and seismic joints near changes in ground stiffness.

## Suggested capstone study

An original teaching brief based on the documented project. Study assumptions and student designs are separate from the built project.

Define a TBM operating envelope and segmental-lining checks for a deep water-bearing rock-to-soil transition.

### Inputs to assemble

- Map the reported stiffness transitions and separate water pressure from effective ground stress.
- Identify the design-stage and construction-stage dates in the engineering accounts.

### Deliverables

- Compare face-pressure limits for blowout, inflow and ground loss.
- Prepare a lining/joint load summary and contingency measures for interventions under pressure.
- A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.
- A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points.

### Review questions

- Why should seismic joints be linked to ground stiffness rather than regular spacing alone?
- Which ground investigation would most reduce uncertainty at a mixed-face transition?

## Published project information

### Design — partial

The design consultant and supervising engineer describe ground conditions, machine selection and the installed systems. They do not supply a complete downloadable design calculation set.

### Cost information — not-found

A project-specific estimate, bid schedule or final account was not found in the reviewed sources.

### Schedule information — partial

Italferr records TBM excavation during 2014–2015, opening to traffic in December 2016 and final acceptance in February 2017.

### Completion and records — not-found

Complete as-built drawings and acceptance records were not found in the reviewed sources.

## Project image

The Asian entrance of the Eurasia Tunnel in Istanbul. The photograph shows the completed road-tunnel project; the deep mixed-ground crossing is below the strait.

Credit: Alessandro57
Image source: https://commons.wikimedia.org/wiki/File:Eurasia_tunnel_Asia_entrance_01.jpg
Image rights: CC BY-SA 4.0 — https://creativecommons.org/licenses/by-sa/4.0

## Sources

- Eurasia Tunnel design account (WSP; date not stated): https://www.wsp.com/en-us/projects/eurasia-tunnel-istanbul-strait-road-tube-crossing
- Supervision and technical summary (Italferr; date not stated): https://www.italferr.it/content/dam/italferr_nd/inglese/document/SCHEDA%20TECNICA%20EURASYA%20TUNNEL%20ENG1.pdf
- Eurasia tunnel Asia entrance 01.jpg — image and reuse license (Wikimedia Commons / Alessandro57; 2026): https://commons.wikimedia.org/wiki/File:Eurasia_tunnel_Asia_entrance_01.jpg

Sources checked: 2026-11-22. This brief is an original teaching aid. Source rights remain with their respective holders.