# Folsom auxiliary spillway — rock excavation and foundation preparation

Case reference year: 2017 | Location: Folsom, California, United States

The auxiliary spillway required major rock excavation and preparation of the control-structure foundation before concrete placement.

## Suggested capstone study

An original teaching brief based on the documented project. Study assumptions and student designs are separate from the built project.

Plan a rock-foundation excavation and acceptance programme beside an operating dam and public transport route.

### Inputs to assemble

- Extract published construction stages and final structure dimensions.
- Establish study discontinuity, groundwater and blast-vibration parameters explicitly.

### Deliverables

- Prepare a temporary rock-slope/bench concept and foundation mapping checklist.
- Design sequencing between blasting, cleaning, drainage, acceptance and concrete placement.
- A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.
- A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points.

### Review questions

- Which site data control the decision, and what additional investigation would reduce uncertainty?
- How would the proposed solution change under the stated sensitivity cases, construction constraints and performance limits?

## Published project information

### Design — partial

USACE construction accounts describe blasting completion, foundation cleaning and the subsequent control structure and chute.

### Cost information — partial

USACE describes a $900 million cooperative effort, a programme total rather than a rock-excavation unit-rate schedule.

### Schedule information — partial

The source records initial excavation in 2008, final concrete stages in 2016 and the October 2017 completion ceremony.

### Completion and records — partial

The owner’s completion release identifies the constructed auxiliary spillway.

## Project image

Rock excavation for the Folsom Dam auxiliary spillway, April 2012. U.S. Army Corps of Engineers construction photograph.

Credit: U.S. Army Corps of Engineers Sacramento District
Image source: https://commons.wikimedia.org/wiki/File:Corps_completes_final_rock_blasting_for_Folsom_Dam_spillway_(7074960195).jpg
Image rights: Public domain — https://commons.wikimedia.org/wiki/File:Corps_completes_final_rock_blasting_for_Folsom_Dam_spillway_(7074960195).jpg#Licensing

## Sources

- Corps completes blasting for Folsom Dam spillway (USACE; 2012): https://www.spk.usace.army.mil/Media/News-Stories/Article/479150/corps-completes-blasting-for-folsom-dam-spillway/
- Folsom auxiliary spillway completion ceremony (USACE; 2017): https://www.spk.usace.army.mil/Media/News-Releases/Article/1347967/folsom-auxiliary-spillway-completion-ceremony-marks-conclusion-of-historic-proj/
- Corps completes final rock blasting for Folsom Dam spillway (7074960195).jpg — image and reuse license (Wikimedia Commons / U.S. Army Corps of Engineers Sacramento District; 2012): https://commons.wikimedia.org/wiki/File:Corps_completes_final_rock_blasting_for_Folsom_Dam_spillway_(7074960195).jpg

Sources checked: 2026-11-22. This brief is an original teaching aid. Source rights remain with their respective holders.