# I-70 Grizzly Creek — post-fire rockfall risk and betterment

Case reference year: 2021 | Location: Glenwood Canyon, Colorado, United States

After the 2020 fire, CDOT compared rockfall mitigation using risk and benefit-cost analysis. Subsequent debris flows exceeded some installed protection capacities.

## Suggested capstone study

An original teaching brief based on the documented project. Study assumptions and student designs are separate from the built project.

Select a rockfall-protection strategy under changing post-fire hazard and explicitly describe the residual risk from events beyond its capacity.

### Inputs to assemble

- Extract the source cost table, hazard categories and analysis periods.
- Verify energy units and fence specifications against design documents before using them; the summary’s unit labels require confirmation.

### Deliverables

- Recalculate the published benefit-cost comparison with transparent assumptions.
- Develop a fence layout concept, inspection triggers and a response to debris-flow exceedance.
- A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.
- A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points.

### Review questions

- Which site data control the decision, and what additional investigation would reduce uncertainty?
- How would the proposed solution change under the stated sensitivity cases, construction constraints and performance limits?

## Published project information

### Design — partial

The FHWA case documents selected fence treatments, cost assumptions and the importance of distinguishing routine rockfall from larger debris-flow events.

### Cost information — partial

The report lists a $2.692 million fence estimate and benefit-cost ratios for one- and five-year periods; other summary totals have different scopes.

### Schedule information — partial

Fences were installed in spring 2021; intense rainfall caused damaging debris flows in July 2021.

### Completion and records — partial

The case records both reduced minor-rockfall disruption and damage during larger subsequent events.

## Project image

Burn scars from the Grizzly Creek fire above I-70 in Glenwood Canyon, Colorado. FHWA photograph from its rockfall and debris-flow mitigation case study.

Credit: Federal Highway Administration (FHWA)
Image source: https://www.fhwa.dot.gov/programadmin/er/er_case_colorado_grizzlycreek.pdf
Image rights: Public domain — U.S. federal government work — https://www.fhwa.dot.gov/publications/research/general/15058/024.cfm