# Herbert Hoover Dike — seepage barriers and structure replacement

Case reference year: 2023 | Location: Lake Okeechobee, Florida, United States

The rehabilitation combined cutoff walls, culvert replacements and embankment armoring around Lake Okeechobee. USACE provides a completion summary and project update.

## Suggested capstone study

An original teaching brief based on the documented project. Study assumptions and student designs are separate from the built project.

Develop a reach-prioritization and treatment plan for a long embankment system with penetrations and heterogeneous seepage risk.

### Inputs to assemble

- Extract the completed work types and distinguish dike length from treated cutoff length.
- Select one study reach and record what local borings, heads and structure details remain necessary.

### Deliverables

- Compare seepage-control alternatives at a typical reach and at a culvert penetration.
- Build a work-package schedule and QA plan for interfaces between walls and structures.
- A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.
- A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points.

### Review questions

- Which site data control the decision, and what additional investigation would reduce uncertainty?
- How would the proposed solution change under the stated sensitivity cases, construction constraints and performance limits?

## Published project information

### Design — partial

USACE documents more than 56 miles of cutoff wall and replacement of 28 water-control structures, alongside other risk-reduction work.

### Cost information — partial

The January 2023 announcement reports $1.5 billion invested; the later Fall 2023 update reports over $1.6 billion since 2001. Preserve the different dates and scopes.

### Schedule information — partial

USACE celebrated construction completion in January 2023 after a programme begun in 2005.

### Completion and records — partial

The completion release and later update describe completed risk-reduction features.

## Published reference values

Use each value only within its stated scope. Reported costs have not been escalated or adjusted for inflation. These are source facts, not student design assumptions.

| Quantity | Value | Unit | Scope | Source locator |
| --- | ---: | --- | --- | --- |
| Completed cutoff-wall length | 56.2 | mile | Partial-penetration wall described in the Fall 2023 update. | [Embankment cutoff wall](https://usace.contentdm.oclc.org/digital/api/collection/p16021coll11/id/6735/download) |
| Replaced water-control structures | 28 | count | Replacement work within the rehabilitation programme. | [Water control structures](https://usace.contentdm.oclc.org/digital/api/collection/p16021coll11/id/6735/download) |
| Removed or abandoned structures | 4 | count | Structures no longer required. | [Water control structures](https://usace.contentdm.oclc.org/digital/api/collection/p16021coll11/id/6735/download) |

## Project image

Construction equipment working along the Herbert Hoover Dike at Lake Okeechobee. Original USACE photograph from the Fall 2023 project update.

Credit: U.S. Army Corps of Engineers, Jacksonville District
Image source: https://usace.contentdm.oclc.org/digital/api/collection/p16021coll11/id/6735/download
Image rights: Public domain — U.S. federal government work — https://www.usace.army.mil/Privacy-and-Security/

## Sources

- Herbert Hoover Dike rehabilitation completion (USACE; 2023): https://www.saj.usace.army.mil/Media/News-Releases/Article/3276863/usace-marks-herbert-hoover-dike-rehabilitation-project-completion-with-ribbon-c/
- Herbert Hoover Dike — Fall 2023 project update (USACE; 2023): https://usace.contentdm.oclc.org/digital/api/collection/p16021coll11/id/6735/download

Sources checked: 2026-11-22. This brief is an original teaching aid. Source rights remain with their respective holders.