# Hywind Scotland — suction anchors for floating wind

Case reference year: 2017 | Location: Buchan Deep, offshore Peterhead, United Kingdom

Five floating turbines use mooring systems connected to seabed suction anchors. Project and decommissioning material support an integrated study of anchor capacity, installation, inspection and eventual removal.

## Suggested capstone study

An original teaching brief based on the documented project. Study assumptions and student designs are separate from the built project.

Prepare a suction-anchor concept and inspection strategy for one mooring line, including cyclic demand and removal feasibility.

### Inputs to assemble

- Trace the three-point mooring arrangement and identify the anchor information actually supplied by the project.
- Develop explicit study soil profiles and load envelopes when borehole/CPT data or proprietary design loads are unavailable.

### Deliverables

- Compare installation suction, holding capacity and cyclic degradation scenarios, retaining the distinction between drained and undrained assumptions.
- Prepare an ROV inspection plan, cable/mooring interaction review and a decommissioning sequence with geotechnical risks.
- A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.
- A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points.

### Review questions

- Why can an anchor meet a monotonic holding-capacity check yet remain unsuitable under repeated inclined mooring loads?
- How would the preferred removal method change if the as-installed suction anchor has tilted or developed significant internal soil plugging?

## Published project information

### Design — partial

Project sources describe the spar, mooring lines and suction anchors; the 2022 decommissioning programme gives asset-specific arrangements. Distinguish the floating turbine substructure from its seabed anchor foundation and do not transfer onshore monopile checks directly.

### Cost information — not-found

A project-specific estimate, bid schedule or final account was not found in the reviewed sources.

### Schedule information — partial

The operator records commissioning in 2017. The 2022 decommissioning document is a programme, not evidence that removal has occurred.

### Completion and records — partial

The published field study reports subsea observations from 2018 and 2020. These observations show asset inspection opportunities and are not a complete geotechnical acceptance certificate.

## Project image

Hywind Scotland photographed from the sea on 22 June 2022. The turbine spars are visible above the water; the suction anchors and mooring arrangements are described in the linked project records.

Credit: Mike Pennington / Wikimedia Commons
Image source: https://commons.wikimedia.org/wiki/File:Hywind_Wind_Farm,_off_Peterhead_-_geograph.org.uk_-_7226685.jpg
Image rights: CC BY-SA 2.0 — https://creativecommons.org/licenses/by-sa/2.0

## Sources

- Hywind Scotland — operator project information (Equinor; date not stated): https://www.equinor.com/energy/hywind-scotland
- Pilot Park decommissioning programme, May 2022 (Equinor; date not stated): https://cdn.equinor.com/files/h61q9gi9/global/1b585f93025b2cf77ece1bb597520ff325454abc.pdf?hywind-scotland-pilot-park-decommissioning-programme-submission-may-2022-equinor.pdf=
- Artificial hard-substrate colonisation — field inspection of structures, moorings and anchors (Karlsson et al. / Wind Energy Science; date not stated): https://wes.copernicus.org/articles/7/801/2022/
- Hywind Wind Farm, off Peterhead - geograph.org.uk - 7226685.jpg (Mike Pennington; 2022): https://commons.wikimedia.org/wiki/File:Hywind_Wind_Farm,_off_Peterhead_-_geograph.org.uk_-_7226685.jpg

Sources checked: 2026-11-22. This brief is an original teaching aid. Source rights remain with their respective holders.