# I-15 reconstruction — soft-ground embankments and geofoam

Case reference year: 2001 | Location: Salt Lake City, Utah, United States

Rapid highway reconstruction over soft lacustrine soils used geofoam, lime-cement columns, vertical drains, surcharge and staged MSE construction. UDOT reports ten-year performance.

## Suggested capstone study

An original teaching brief based on the documented project. Study assumptions and student designs are separate from the built project.

Choose an embankment solution above sensitive buried utilities and soft clay, then reconcile the design prediction with the long-term monitoring record.

### Inputs to assemble

- Extract stratigraphy, groundwater and construction loading from the selected instrumented section.
- Digitize a clearly identified settlement series with units and dates.

### Deliverables

- Compare earth fill, preload/drains and geofoam for settlement, time and buoyancy.
- Prepare a staged-load calculation, utility protection detail and monitoring acceptance criteria.
- A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.
- A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points.

### Review questions

- Which site data control the decision, and what additional investigation would reduce uncertainty?
- How would the proposed solution change under the stated sensitivity cases, construction constraints and performance limits?

## Published project information

### Design — available

The reports document alternative embankment systems and monitored geofoam sections, including the 100 South crossing.

### Cost information — not-found

A project-specific estimate, bid schedule or final account was not found in the reviewed sources.

### Schedule information — partial

The monitoring reports cover reconstruction and the following decade; extract dates for the chosen section rather than using a corridor-wide programme.

### Completion and records — partial

Long-term settlement and numerical-model comparisons are available in the research reports.

## Project image

The 100 South utility corridor during the Salt Lake City I-15 reconstruction, shown in the project authors’ Figure 2.

Credit: Steven Bartlett, Dawit Negussey, Mark Kimble and Michael Sheeley; published by Syracuse Geofoam Research Center
Image source: https://geofoam.syr.edu/utah.html
Image rights: No open reuse license verified; original copyright retained — https://geofoam.syr.edu/utah.html

## Sources

- I-15 reconstruction long-term embankment monitoring study (UDOT / University of Utah; 2012): https://rosap.ntl.bts.gov/view/dot/31963
- Design and evaluation of EPS geofoam embankments (UDOT / University of Utah; 2012): https://rosap.ntl.bts.gov/view/dot/31962
- Use of Geofoam for I-15 Reconstruction in Salt Lake City, UT (Syracuse University Geofoam Research Center; date not stated): https://geofoam.syr.edu/utah.html

Sources checked: 2026-11-22. This brief is an original teaching aid. Source rights remain with their respective holders.