# Inuvik–Tuktoyaktuk Highway — embankment over permafrost

Case reference year: 2017 | Location: Northwest Territories, Canada

The highway used fill placement and separation geotextile to protect permafrost, with much construction undertaken in winter.

## Suggested capstone study

An original teaching brief based on the documented project. Study assumptions and student designs are separate from the built project.

Develop an embankment concept for ice-rich permafrost and compare seasonal construction and thaw-settlement risk.

### Inputs to assemble

- Extract the owner’s construction constraints and select a monitored ground-temperature location.
- Record how ground-ice and soil-property information differ along the alignment.

### Deliverables

- Prepare a thermal/thaw-settlement screening model and sensitivity to warming and drainage.
- Plan borrow, winter hauling, geotextile placement and long-term temperature monitoring.
- A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.
- A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points.

### Review questions

- Which site data control the decision, and what additional investigation would reduce uncertainty?
- How would the proposed solution change under the stated sensitivity cases, construction constraints and performance limits?

## Published project information

### Design — partial

The owner describes the construction strategy; a Canadian geological report documents regional ground temperatures before and after construction.

### Cost information — not-found

A project-specific estimate, bid schedule or final account was not found in the reviewed sources.

### Schedule information — partial

The owner project page documents opening and winter construction strategy; use source milestones rather than an assumed year-round programme.

### Completion and records — partial

The owner page and regional ground-temperature report support performance review.

## Project image

The Inuvik–Tuktoyaktuk Highway through the Caribou Hills north of Inuvik. Photograph of the actual permafrost-road project corridor.

Credit: Samuell
Image source: https://commons.wikimedia.org/wiki/File:ITH_Caribou_Hills.jpg
Image rights: CC BY 4.0 — https://creativecommons.org/licenses/by/4.0

## Sources

- Inuvik Tuktoyaktuk Highway project (Government of the Northwest Territories; 2017): https://www.inf.gov.nt.ca/en/ITH
- Permafrost ground-temperature synthesis 2013–2019, GSC OF 8656 (Geological Survey of Canada / NWT Geological Survey; 2020): https://publications.gc.ca/collections/collection_2021/rncan-nrcan/m183-2/M183-2-8656-eng.pdf
- ITH Caribou Hills.jpg — image and reuse license (Wikimedia Commons / Samuell; 2021): https://commons.wikimedia.org/wiki/File:ITH_Caribou_Hills.jpg

Sources checked: 2026-11-22. This brief is an original teaching aid. Source rights remain with their respective holders.