# Lee Tunnel — diaphragm-wall shafts in water-bearing chalk

Case reference year: 2017 | Location: East London, United Kingdom

Deep circular shafts and a slurry-driven tunnel connected Abbey Mills and Beckton. The foundation contractor describes diaphragm-wall design, fractured chalk and flint bands encountered during shaft construction.

## Suggested capstone study

An original teaching brief based on the documented project. Study assumptions and student designs are separate from the built project.

Design a circular access shaft with large openings through mixed superficial deposits and chalk.

### Inputs to assemble

- Extract the reported shaft geometry range and rock description.
- Identify openings and non-axisymmetric actions that violate a simple uniform hoop model.

### Deliverables

- Check wall forces, basal water pressure and the staged excavation sequence.
- Specify verticality, panel-joint and grouting acceptance checks before deep excavation.
- A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.
- A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points.

### Review questions

- How do large shaft openings alter the advantages of circular wall action?
- Which checks become most sensitive when chalk fractures connect to overlying sands?

## Published project information

### Design — partial

The contractor account describes geology and shaft systems; the contract case supplies delivery context. Its later Tideway forecasts are historical and are not treated as current milestones.

### Cost information — partial

The contract case describes a £675 million overall project. It is not a shaft-only cost or an independently audited final account.

### Schedule information — partial

The contract case reports operation beginning in 2016 and overall completion in 2017.

### Completion and records — not-found

Complete as-built drawings and acceptance records were not found in the reviewed sources.

## Project image

Looking into a deep Lee Tunnel diaphragm-wall shaft during construction, from the foundation contractor’s project gallery. The source does not identify this image as one particular named shaft.

Credit: Bachy Soletanche
Image source: https://www.bacsol.co.uk/project/lee-tunnel-london
Image rights: No open reuse license verified; original copyright retained — https://www.bacsol.co.uk/project/lee-tunnel-london

## Sources

- Lee Tunnel foundations and shafts (Bachy Soletanche; date not stated): https://www.bacsol.co.uk/project/lee-tunnel-london
- Lee Tunnel delivery case (NEC Contracts / project participants; date not stated): https://www.neccontract.com/projects/lee-sewage-tunnel-uk

Sources checked: 2026-11-22. This brief is an original teaching aid. Source rights remain with their respective holders.