{"id":"lee-tunnel","title":"Lee Tunnel — diaphragm-wall shafts in water-bearing chalk","summary":"Deep circular shafts and a slurry-driven tunnel connected Abbey Mills and Beckton. The foundation contractor describes diaphragm-wall design, fractured chalk and flint bands encountered during shaft construction.","topics":["tunnels","excavation","dewatering","retaining-walls"],"country":"United Kingdom","region":"East London","owner":"Thames Water","year":2017,"yearLabel":"Case reference year","projectType":"Design, construction and performance","methods":["Diaphragm-wall shafts","Hoop action","Curtain grouting","Slurry TBM"],"documentationLevel":"technical-case","design":{"availability":"partial","summary":"The contractor account describes geology and shaft systems; the contract case supplies delivery context. Its later Tideway forecasts are historical and are not treated as current milestones.","sourceIds":["s1","s2"]},"cost":{"availability":"partial","summary":"The contract case describes a £675 million overall project. It is not a shaft-only cost or an independently audited final account.","sourceIds":["s1","s2"]},"schedule":{"availability":"partial","summary":"The contract case reports operation beginning in 2016 and overall completion in 2017.","sourceIds":["s1","s2"]},"records":{"availability":"not-found","summary":"Complete as-built drawings and acceptance records were not found in the reviewed sources.","sourceIds":[]},"capstone":{"label":"Suggested capstone study","scope":"An original teaching brief based on the documented project. Study assumptions and student designs are separate from the built project.","brief":"Design a circular access shaft with large openings through mixed superficial deposits and chalk.","inputs":["Extract the reported shaft geometry range and rock description.","Identify openings and non-axisymmetric actions that violate a simple uniform hoop model."],"deliverables":["Check wall forces, basal water pressure and the staged excavation sequence.","Specify verticality, panel-joint and grouting acceptance checks before deep excavation.","A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.","A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points."],"questions":["How do large shaft openings alter the advantages of circular wall action?","Which checks become most sensitive when chalk fractures connect to overlying sands?"],"output":"Design report, calculation workbook, concept drawings, quantity schedule and construction programme."},"sources":[{"id":"s1","title":"Lee Tunnel foundations and shafts","url":"https://www.bacsol.co.uk/project/lee-tunnel-london","publisher":"Bachy Soletanche","year":null,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22","localAssetIds":["project-image"]},{"id":"s2","title":"Lee Tunnel delivery case","url":"https://www.neccontract.com/projects/lee-sewage-tunnel-uk","publisher":"NEC Contracts / project participants","year":null,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"}],"assets":[{"id":"schematic","title":"Conceptual study schematic","kind":"figure","fileName":"lee-tunnel.svg","mimeType":"image/svg+xml","bytes":1125,"sha256":"6e6bc7d568720504ae2ac68b2111e026e4bb56fc1979d2a2854bd49ec8c3b1db","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/lee-tunnel/download/schematic"},{"id":"project-image","title":"Lee Tunnel — diaphragm-wall shaft","kind":"project-image","fileName":"lee-tunnel-r13.jpg","mimeType":"image/jpeg","bytes":228064,"sha256":"fc396c5f49b66dd83e44ab6a653056fe8d94c89b90f8994e87f69391358eef32","sourceId":"s1","license":"No open reuse license verified; original copyright retained","width":600,"height":400,"credit":"Bachy Soletanche","sourceUrl":"https://www.bacsol.co.uk/project/lee-tunnel-london","licenseUrl":"https://www.bacsol.co.uk/project/lee-tunnel-london","imageDate":null,"evidenceFile":"image-provenance/lee-tunnel-r13-source.json","evidenceSha256":"5cc7371182aedd09643f171ed244c2357082c4601da5804250e5e0010cf8673a","transformations":"Copied the publisher’s 600 × 400 JPEG derivative unchanged; no additional crop, resizing, added labels, or retouching.","originalUrl":"https://www.bacsol.co.uk/wp-content/uploads/2020/08/Retaining-Wall-Solution-Lee-Tunnel-Diaphragm-Wall-Shaft-7-600x400.jpg","originalSha256":"fc396c5f49b66dd83e44ab6a653056fe8d94c89b90f8994e87f69391358eef32","imageDownloadAllowed":false,"rightsStatus":"editorial-reference","permissionStatus":"No open reuse permission verified","rightsNote":"Source-linked editorial reference; copyright remains with the original owner. The site does not offer this image as a reusable download.","imageUsage":"project-photograph","rightsBasis":"See the per-image provenance record and linked license; source hosting alone is not the rights basis.","previewUrl":"/cases/lee-tunnel/figure"},{"id":"capstone-brief","title":"Capstone brief (Markdown)","kind":"brief","fileName":"lee-tunnel-capstone.md","mimeType":"text/markdown","bytes":2910,"sha256":"a2d8ea7378ad7a5316b4aff6b33df06977e908282baab4aa1e0a4f0859b388cc","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/lee-tunnel/download/capstone-brief"}],"figure":{"assetId":"project-image","kind":"photograph","alt":"Construction photograph looking down into a circular Lee Tunnel diaphragm-wall shaft.","caption":"Looking into a deep Lee Tunnel diaphragm-wall shaft during construction, from the foundation contractor’s project gallery. The source does not identify this image as one particular named shaft.","credit":"Bachy Soletanche","sourceUrl":"https://www.bacsol.co.uk/project/lee-tunnel-london","license":"No open reuse license verified; original copyright retained","licenseUrl":"https://www.bacsol.co.uk/project/lee-tunnel-london","width":600,"height":400,"imageDate":null,"preserveWholeImage":true,"imageDownloadAllowed":false,"rightsStatus":"editorial-reference","permissionStatus":"No open reuse permission verified","rightsNote":"Source-linked editorial reference; copyright remains with the original owner. The site does not offer this image as a reusable download.","imageUsage":"project-photograph"},"figureCaption":"Looking into a deep Lee Tunnel diaphragm-wall shaft during construction, from the foundation contractor’s project gallery. The source does not identify this image as one particular named shaft.","qualityNotes":[],"checked":"2026-11-22","addedIn":"r13","curatedOrder":79,"referenceValues":[],"teachingFigureCaption":"Conceptual study schematic; not an as-built project drawing.","imageEvidence":{"status":"acquired","identityVerified":true,"evidenceFile":"image-provenance/lee-tunnel-r13-source.json","evidenceSha256":"5cc7371182aedd09643f171ed244c2357082c4601da5804250e5e0010cf8673a","visualReview":"Inspected the entire published 600 × 400 photograph. It shows the full visible circular shaft lining, suspended construction lines and equipment below. No generative or unrelated replacement was used.","checked":"2026-11-22"},"localReportCount":0,"downloadBytes":4035,"sourceCount":2,"url":"/cases/lee-tunnel"}