# Marina Bay Sands — deep foundations on reclaimed ground

Case reference year: 2010 | Location: Marina Bay, Singapore, Singapore

The integrated resort was constructed on reclaimed waterfront land. The foundation contractors describe bored piling and advance removal of a buried seawall within a tightly constrained site.

## Suggested capstone study

An original teaching brief based on the documented project. Study assumptions and student designs are separate from the built project.

Plan a bored-pile and basement construction sequence across reclaimed fill containing a former seawall.

### Inputs to assemble

- Map the reported obstruction and the interfaces between enabling work, piling and excavation.
- Specify a supplemental investigation for fill variability, groundwater and founding strata.

### Deliverables

- Compare pile installation risks with alternative obstruction-removal sequences.
- Prepare a support-of-excavation concept and hold points for pile integrity and base cleanliness.
- A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.
- A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points.

### Review questions

- How can a buried seawall affect both pile verticality and groundwater flow?
- Which enabling work must precede production piling to avoid repeated access conflicts?

## Published project information

### Design — partial

Contractor accounts identify foundation and enabling works; complete ground parameters and structural reactions are not supplied. Those require explicit study assumptions or additional records.

### Cost information — not-found

A project-specific estimate, bid schedule or final account was not found in the reviewed sources.

### Schedule information — not-found

A dated project programme was not found in the reviewed sources; develop a study schedule from the documented method.

### Completion and records — not-found

Complete as-built drawings and acceptance records were not found in the reviewed sources.

## Project image

Construction of the Marina Bay Sands resort in Singapore. The source identifies the actual development discussed in the foundation contractors’ accounts.

Credit: Andy Mitchell from Glasgow, UK
Image source: https://commons.wikimedia.org/wiki/File:Marina_Bay_Sands_Casino_construction_site_(3366800416).jpg
Image rights: CC BY-SA 2.0 — https://creativecommons.org/licenses/by-sa/2.0

## Sources

- Integrated Marina Bay Sands foundation works (Bachy Soletanche Singapore; date not stated): https://bachy-soletanche.com.sg/offer-portfolio/intergrated-marina-bay-sands/
- Marina Bay Sands piling account (Foundation Alliance; date not stated): https://www.foundation-alliance.com/offer-portfolio/marina-bay-sands-integrated-resort/
- Integrated resort project description (Safdie Architects; date not stated): https://www.safdiearchitects.com/projects/marina-bay-sands-integrated-resort
- Marina Bay Sands Casino construction site (3366800416).jpg — image and reuse license (Wikimedia Commons / Andy Mitchell from Glasgow, UK; 2009): https://commons.wikimedia.org/wiki/File:Marina_Bay_Sands_Casino_construction_site_(3366800416).jpg

Sources checked: 2026-11-22. This brief is an original teaching aid. Source rights remain with their respective holders.