{"id":"millau-viaduct","title":"Millau Viaduct — rock foundations and observational control","summary":"Very tall bridge piers transfer load through large shaft-and-raft foundations in limestone and marl. The geotechnical authors report measured foundation movement and the observational design strategy.","topics":["rock","deep-foundations","settlement","monitoring"],"country":"France","region":"Tarn Valley","owner":"Compagnie Eiffage du Viaduc de Millau","year":2004,"yearLabel":"Case reference year","projectType":"Design, construction and performance","methods":["Rock sockets","Foundation rotation","Observational method"],"documentationLevel":"technical-case","design":{"availability":"partial","summary":"An open research paper describes investigation, foundation geometry and monitoring. The consultant account distinguishes pier geology and a local abutment adaptation.","sourceIds":["s1","s2","s3"]},"cost":{"availability":"not-found","summary":"A project-specific estimate, bid schedule or final account was not found in the reviewed sources.","sourceIds":[]},"schedule":{"availability":"partial","summary":"Eiffage records construction during 2001–2004 and inauguration in December 2004; this is a milestone history, not the full contractor programme.","sourceIds":["s1","s2","s3"]},"records":{"availability":"partial","summary":"The geotechnical paper reports the monitored foundation behavior after construction.","sourceIds":["s1","s2","s3"]},"capstone":{"label":"Suggested capstone study","scope":"An original teaching brief based on the documented project. Study assumptions and student designs are separate from the built project.","brief":"Check a tall-pier foundation on contrasting rock units, with rotation limits governing the design.","inputs":["Extract published shaft, raft and rock-unit descriptions for one selected pier.","Separate measured translations from rotations and identify the construction stages."],"deliverables":["Compare bearing, sliding and rotational stiffness for limestone and marl assumptions.","Draft an instrumentation plan and pre-agreed foundation intervention sequence.","A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.","A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points."],"questions":["Why can small differential movements matter more than total bearing capacity for this bridge?","How should an unexpected weak zone change the verification and contingency plan?"],"output":"Design report, calculation workbook, concept drawings, quantity schedule and construction programme."},"sources":[{"id":"s1","title":"Millau viaduct geotechnical studies and foundations","url":"https://www.sciencedirect.com/science/article/pii/S167477551300036X","publisher":"Geotechnical project authors / Journal of Rock Mechanics and Geotechnical Engineering","year":null,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s2","title":"Foundation engineering project account","url":"https://www.terrasol.fr/wp-content/uploads/2017/12/oa07_845_millau_viaduct_eng.pdf","publisher":"Terrasol","year":null,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s3","title":"Construction milestones","url":"https://www.eiffagegeniecivil.com/milau-viaduct","publisher":"Eiffage Génie Civil","year":null,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s4","title":"Viaduc millau 1.JPG — image and reuse license","url":"https://commons.wikimedia.org/wiki/File:Viaduc_millau_1.JPG","publisher":"Wikimedia Commons / Emeraude","year":2004,"access":"public-link","license":"Public domain","notes":"Project image source. Unmodified publisher-generated display-size file; the original source URL and publisher metadata are retained. No AI-generated replacement or content alteration.","checked":"2026-11-22","localAssetIds":["project-image"]}],"assets":[{"id":"schematic","title":"Conceptual study schematic","kind":"figure","fileName":"millau-viaduct.svg","mimeType":"image/svg+xml","bytes":1017,"sha256":"ab086e9b878d71ca75443d4083022bf013c864b1ad5c4bbfbedf783b1ffc7360","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/millau-viaduct/download/schematic"},{"id":"project-image","title":"Viaduc millau 1.JPG","kind":"project-image","fileName":"millau-viaduct.jpg","mimeType":"image/jpeg","bytes":51310,"sha256":"9467ba872ccc50d998b9cc2bfb5188db5146d84c983f005b7d3b9847e693a6b9","sourceId":"s4","license":"Public domain","width":480,"height":640,"credit":"Emeraude","sourceUrl":"https://commons.wikimedia.org/wiki/File:Viaduc_millau_1.JPG","licenseUrl":"https://commons.wikimedia.org/wiki/File:Viaduc_millau_1.JPG#Licensing","imageDate":"2004-03-14","evidenceFile":"image-provenance/millau-viaduct-commons.json","evidenceSha256":"e7a265ad5c20e75ffa310179ed68178f1fb3cf4910a87d8e54fabfba3627795e","transformations":"Unmodified publisher-generated display-size file; the original source URL and publisher metadata are retained. No AI-generated replacement or content alteration.","originalUrl":"https://upload.wikimedia.org/wikipedia/commons/9/9c/Viaduc_millau_1.JPG","downloadUrl":"/cases/millau-viaduct/download/project-image","originalSha1":"cfe891bbedddcb693b57292d9abae9380c489b21","originalSha256":"9467ba872ccc50d998b9cc2bfb5188db5146d84c983f005b7d3b9847e693a6b9","imageDownloadAllowed":true,"rightsBasis":"See the per-image provenance record and linked license; source hosting alone is not the rights basis."},{"id":"capstone-brief","title":"Capstone brief (Markdown)","kind":"brief","fileName":"millau-viaduct-capstone.md","mimeType":"text/markdown","bytes":3222,"sha256":"694e38240fd87fccdac897252bff729b43efe470995f39c65b3c150cb2d6baca","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/millau-viaduct/download/capstone-brief"}],"figure":{"assetId":"project-image","kind":"photograph","alt":"The Millau Viaduct during construction.","caption":"The Millau Viaduct during construction. The tall piers and valley setting provide context for the published rock-foundation and monitoring case.","credit":"Emeraude","sourceUrl":"https://commons.wikimedia.org/wiki/File:Viaduc_millau_1.JPG","license":"Public domain","licenseUrl":"https://commons.wikimedia.org/wiki/File:Viaduc_millau_1.JPG#Licensing","width":480,"height":640,"imageDate":"2004-03-14","preserveWholeImage":true,"imageDownloadAllowed":true},"figureCaption":"The Millau Viaduct during construction. The tall piers and valley setting provide context for the published rock-foundation and monitoring case.","qualityNotes":[],"checked":"2026-11-22","addedIn":"r13","curatedOrder":52,"referenceValues":[],"teachingFigureCaption":"Conceptual study schematic; not an as-built project drawing.","imageEvidence":{"status":"acquired","identityVerified":true,"evidenceFile":"image-provenance/millau-viaduct-commons.json","evidenceSha256":"e7a265ad5c20e75ffa310179ed68178f1fb3cf4910a87d8e54fabfba3627795e","visualReview":"Viewed the complete publisher photograph in the final contact sheets or individually and compared it with the source identity, date, and caption. The caption distinguishes project context from the particular underground treatment or construction stage.","checked":"2026-11-22"},"localReportCount":0,"downloadBytes":55549,"sourceCount":4,"url":"/cases/millau-viaduct"}