# Millennium Tower — perimeter-pile underpinning and monitored load transfer

Case reference year: 2023 | Location: San Francisco, United States

The remedial designer describes transferring part of the building load to new perimeter piles founded in rock. Installation-induced movement required changes to both pile construction and the final pile arrangement.

## Suggested capstone study

An original teaching brief based on the documented project. Study assumptions and student designs are separate from the built project.

Design a monitored perimeter underpinning concept while keeping an occupied building in service.

### Inputs to assemble

- Compare the original proposal and later constructed solution without mixing their quantities.
- Extract the load-transfer concept and identify the pile-installation effects that prompted revision.

### Deliverables

- Balance imposed pile load, existing-foundation capacity and differential movement.
- Prepare installation trials, staged jacking steps and ten-year monitoring objectives.
- A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.
- A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points.

### Review questions

- Why can installing a settlement remedy initially increase settlement?
- How should load-transfer fuses protect the original foundation if future differential movement occurs?

## Published project information

### Design — partial

The designer distinguishes the earlier 52-pile proposal from the implemented 18-pile solution. The city’s earlier environmental sheet is retained as proposal-stage evidence, not the final design.

### Cost information — not-found

A project-specific estimate, bid schedule or final account was not found in the reviewed sources.

### Schedule information — partial

The remedial designer reports completion in September 2023 with occupancy maintained during the work.

### Completion and records — partial

The designer reports initial post-work behavior and a ten-year monitoring requirement; long-term performance is still a monitoring question.

## Project image

Workers adding a pile section during the Millennium Tower foundation upgrade in San Francisco. The photograph shows actual underpinning work.

Credit: ArnoldReinhold
Image source: https://commons.wikimedia.org/wiki/File:Millennium_Tower_adding_pile_section_2.agr.jpg
Image rights: CC BY-SA 4.0 — https://creativecommons.org/licenses/by-sa/4.0

## Sources

- Perimeter-pile upgrade and observed outcome (Simpson Gumpertz & Heger, remedial designer; date not stated): https://www.sgh.com/project-story/millennium-tower/
- 2019 proposed upgrade information sheet (San Francisco Planning; date not stated): https://media.api.sf.gov/documents/301_Mission_Information_Sheet_CEQA_Notice.pdf
- Millennium Tower adding pile section 2.agr.jpg — image and reuse license (Wikimedia Commons / ArnoldReinhold; 2022): https://commons.wikimedia.org/wiki/File:Millennium_Tower_adding_pile_section_2.agr.jpg

Sources checked: 2026-11-22. This brief is an original teaching aid. Source rights remain with their respective holders.