# New Jersey Turnpike bridges — micropile underpinning

Case reference year: 2008 | Location: New Jersey, United States

Four bridge retrofits used hollow-core bar micropiles under limited headroom after deterioration of exposed precast piles. The submitted case includes proof and verification tests.

## Suggested capstone study

An original teaching brief based on the documented project. Study assumptions and student designs are separate from the built project.

Plan underpinning of an operating bridge with limited access and a temporary cofferdam.

### Inputs to assemble

- Select one of the four bridges and retain its soil profile, bond length and grout diameter.
- Extract verification and production proof-test criteria.

### Deliverables

- Check grout-ground bond, steel capacity and corrosion/scour exposure.
- Prepare a load-transfer sequence and a test-and-acceptance schedule.
- A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.
- A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points.

### Review questions

- Which site data control the decision, and what additional investigation would reduce uncertainty?
- How would the proposed solution change under the stated sensitivity cases, construction constraints and performance limits?

## Published project information

### Design — partial

The case reports an 80-kip design load per micropile, cased exposure to scour level and different bond lengths at the four bridges.

### Cost information — not-found

A project-specific estimate, bid schedule or final account was not found in the reviewed sources.

### Schedule information — not-found

A dated project programme was not found in the reviewed sources; develop a study schedule from the documented method.

### Completion and records — partial

The case reports production proof tests and sacrificial verification tests.

## Project image

Production micropiles installed under limited headroom at one of the New Jersey Turnpike bridge retrofits. Original Figure 3 from the project authors’ 2008 paper.

Credit: Jesús E. Gómez, Carlos J. Rodriguez, Helen D. Robinson, Johanna Mikitka and Larry Keough (2008)
Image source: https://scholarsmine.mst.edu/icchge/6icchge/session08c/3/
Image rights: CC BY-NC-ND 4.0 — noncommercial, unchanged reproduction — https://creativecommons.org/licenses/by-nc-nd/4.0/

## Sources

- Existing bridge retrofits, Turnpike, New Jersey (ASCE Geo-Institute / named case-history author; 2012): https://www.geoinstitute.org/node/8358
- Bond Strength of Hollow-Core Bar Micropiles (Project authors / Missouri S&T Scholars’ Mine; 2008): https://scholarsmine.mst.edu/icchge/6icchge/session08c/3/

Sources checked: 2026-11-22. This brief is an original teaching aid. Source rights remain with their respective holders.