# One New Change — basement effects on St Paul’s groundwater

Case reference year: 2010 | Location: City of London, United Kingdom

Redevelopment beside St Paul’s Cathedral required assessment of groundwater changes in shallow deposits supporting the historic structure. The designer describes conceptual and numerical groundwater modeling followed by construction monitoring.

## Suggested capstone study

An original teaching brief based on the documented project. Study assumptions and student designs are separate from the built project.

Assess whether a new basement diverts shallow groundwater enough to affect a neighboring heritage foundation.

### Inputs to assemble

- Extract the reported aquifer, foundation and basement relationships.
- Identify man-made drainage and historic excavations that may change natural flow paths.

### Deliverables

- Compare preconstruction and basement scenarios with recharge and permeability sensitivities.
- Specify piezometers and structural surveys capable of distinguishing seasonal changes from construction effects.
- A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.
- A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points.

### Review questions

- Can a watertight basement cause damaging groundwater change without active dewatering?
- Which calibration observations are needed before trusting a model’s small predicted effect?

## Published project information

### Design — partial

Arup explains the groundwater model and observed construction response. The public account does not provide the full calibrated model or authorize unrestricted basement work near the cathedral.

### Cost information — not-found

A project-specific estimate, bid schedule or final account was not found in the reviewed sources.

### Schedule information — not-found

A dated project programme was not found in the reviewed sources; develop a study schedule from the documented method.

### Completion and records — partial

The designer reports groundwater and structural monitoring during construction with negligible observed effect on the cathedral.

## Project image

View from One New Change toward St Paul’s Cathedral. The photograph shows the adjacent development and heritage structure whose groundwater interaction was assessed.

Credit: Txllxt TxllxT
Image source: https://commons.wikimedia.org/wiki/File:London_-_New_Change_-_One_New_Change_2010_by_Jean_Nouvel_-_View_West_on_St_Paul%27s_Cathedral_1697_by_Sir_Christopher_Wren_III.jpg
Image rights: CC BY-SA 4.0 — https://creativecommons.org/licenses/by-sa/4.0

## Sources

- Ground engineering and groundwater protection at One New Change (Arup; date not stated): https://www.arup.com/en-us/projects/one-new-change/
- London - New Change - One New Change 2010 by Jean Nouvel - View West on St Paul's Cathedral 1697 by Sir Christopher Wren III.jpg — image and reuse license (Wikimedia Commons / Txllxt TxllxT; 2011): https://commons.wikimedia.org/wiki/File:London_-_New_Change_-_One_New_Change_2010_by_Jean_Nouvel_-_View_West_on_St_Paul%27s_Cathedral_1697_by_Sir_Christopher_Wren_III.jpg

Sources checked: 2026-11-22. This brief is an original teaching aid. Source rights remain with their respective holders.