# Oroville spillway recovery — erosion-resistant foundation reconstruction

Case reference year: 2018 | Location: Oroville, California, United States

Recovery rebuilt the main spillway and added a secant pile wall, splashpad and buttress at the emergency spillway after the 2017 incident.

## Suggested capstone study

An original teaching brief based on the documented project. Study assumptions and student designs are separate from the built project.

Develop an emergency-to-permanent reconstruction plan that addresses erosion, uplift and uncertain rock quality.

### Inputs to assemble

- Review the forensic findings and identify the selected failure mechanisms.
- Extract the repair cross sections and distinguish temporary from permanent work.

### Deliverables

- Prepare a foundation-drainage and erosion-protection concept with construction hold points.
- Reconcile changing estimate scopes and show how geological uncertainty enters contingency.
- A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.
- A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points.

### Review questions

- Which site data control the decision, and what additional investigation would reduce uncertainty?
- How would the proposed solution change under the stated sensitivity cases, construction constraints and performance limits?

## Published project information

### Design — partial

DWR’s recovery page links investigations and describes the final-design reconstruction; the project update distinguishes initial mobilization from the completed design.

### Cost information — partial

The September 2018 update estimated $940 million recovery through 2019, plus $160 million emergency response; these are dated estimates, not a final account.

### Schedule information — partial

Temporary main-spillway readiness was targeted for November 2017; final-design reconstruction was completed in 2018.

### Completion and records — partial

DWR links consultant, inspection and forensic records from the recovery page.

## Project image

Oroville Dam’s emergency spillway and the erosion below its weir during the February 2017 spillway incident. California Department of Water Resources project photograph.

Credit: California Department of Water Resources
Image source: https://commons.wikimedia.org/wiki/File:Oroville_Dam_weir_and_emergency_spillway_erosion.jpg
Image rights: Public domain — https://commons.wikimedia.org/wiki/File:Oroville_Dam_weir_and_emergency_spillway_erosion.jpg#Licensing

## Sources

- Oroville Spillways Recovery (California DWR; 2018): https://water.ca.gov/Programs/State-Water-Project/SWP-Facilities/Oroville/Oroville-Spillways
- September 2018 construction and cost estimate update (California DWR; 2018): https://water.ca.gov/News/News-Releases/2018/Sept-18/Oroville-Spillways-Construction-and-Cost-Estimate-Update
- Oroville Dam weir and emergency spillway erosion.jpg — image and reuse license (Wikimedia Commons / California Department of Water Resources; 2017): https://commons.wikimedia.org/wiki/File:Oroville_Dam_weir_and_emergency_spillway_erosion.jpg

Sources checked: 2026-11-22. This brief is an original teaching aid. Source rights remain with their respective holders.