# Palm Jumeirah — densification of reclaimed sand

Case reference year: 2006 | Location: Dubai, United Arab Emirates

The artificial island’s reclaimed sand was treated by vibrocompaction before infrastructure construction. The project’s visitor centre explains the working sequence and its role in controlling settlement and liquefaction susceptibility.

## Suggested capstone study

An original teaching brief based on the documented project. Study assumptions and student designs are separate from the built project.

Plan a field trial and acceptance programme for vibrocompaction of a reclaimed waterfront building plot.

### Inputs to assemble

- Use the source to define the treatment sequence and imported/backfill material interfaces.
- Specify a study sand profile and groundwater level, then identify tests required before adopting design parameters.

### Deliverables

- Compare trial-grid spacings using settlement and CPT-based acceptance criteria.
- Develop treatment quantities, verification coverage and a response to refusal or poor improvement.
- A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.
- A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points.

### Review questions

- Why should vibratory power records be supplemented with independent ground testing?
- How do fines content and drainage affect the suitability of vibrocompaction?

## Published project information

### Design — partial

The owner-associated account describes the compaction process and construction sequence. Site-specific CPT data and the complete foundation design package are not provided.

### Cost information — not-found

A project-specific estimate, bid schedule or final account was not found in the reviewed sources.

### Schedule information — not-found

A dated project programme was not found in the reviewed sources; develop a study schedule from the documented method.

### Completion and records — not-found

Complete as-built drawings and acceptance records were not found in the reviewed sources.

## Project image

Palm Jumeirah viewed from a helicopter in May 2008. The actual reclaimed island is shown after the principal ground-treatment period.

Credit: Imre Solt
Image source: https://commons.wikimedia.org/wiki/File:Palm_Jumeirah_on_8_May_2008_Pict_1.jpg
Image rights: CC BY-SA 3.0 — https://creativecommons.org/licenses/by-sa/3.0/

## Sources

- Vibro-compaction at Palm Jumeirah (The View at The Palm / project exhibition; date not stated): https://www.theviewpalm.ae/en/museum/vibro-compaction
- Palm Jumeirah on 8 May 2008 Pict 1.jpg — image and reuse license (Wikimedia Commons / Imre Solt; 2008): https://commons.wikimedia.org/wiki/File:Palm_Jumeirah_on_8_May_2008_Pict_1.jpg

Sources checked: 2026-11-22. This brief is an original teaching aid. Source rights remain with their respective holders.