# Leaning Tower of Pisa — controlled underexcavation

Case reference year: 2008 | Location: Pisa, Italy

A heritage foundation was stabilized by carefully removing soil beneath its north side. Published post-intervention observations connect rotation, settlement and groundwater control.

## Suggested capstone study

An original teaching brief based on the documented project. Study assumptions and student designs are separate from the built project.

Plan a staged underexcavation trial for an eccentric masonry-tower footing, using Pisa to define observations and stop criteria.

### Inputs to assemble

- Extract the foundation geometry, rotation history and monitored groundwater response from the author paper.
- Distinguish the temporary stabilization operations from the permanent soil-removal and drainage measures.

### Deliverables

- Calculate the direction and sensitivity of foundation rotation for small asymmetric volume removals.
- Specify incremental excavation stages, survey precision, trigger values and contingency actions.
- A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.
- A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points.

### Review questions

- Why can removing support on the higher side improve stability without simply increasing bearing resistance?
- How would a seasonal groundwater rise change the interpretation of the measured tilt?

## Published project information

### Design — partial

The project authors describe the stabilization mechanism and subsequent instrument readings. The case supports an observational-method study rather than copying a universal underpinning detail.

### Cost information — not-found

A project-specific estimate, bid schedule or final account was not found in the reviewed sources.

### Schedule information — not-found

A dated project programme was not found in the reviewed sources; develop a study schedule from the documented method.

### Completion and records — partial

The author paper reports post-stabilization monitoring; it is not a current inspection certificate.

## Project image

The Leaning Tower of Pisa after the stabilization works. The photograph identifies the actual monument; the soil-removal operations are documented in the linked engineering accounts.

Credit: PaestumPaestum
Image source: https://commons.wikimedia.org/wiki/File:Exterior_of_the_Leaning_Tower_(Pisa)_in_April_2024.1.jpg
Image rights: CC BY 4.0 — https://creativecommons.org/licenses/by/4.0

## Sources

- Behaviour after stabilization operations (Burland, Jamiolkowski and Viggiani / International Journal of Geoengineering Case Histories; date not stated): https://www.geocasehistoriesjournal.org/issues/volume-1-3/leaning-tower-of-pisa-behaviour-after-stabilization-operations
- Restoration works contractor account (Trevi; date not stated): https://trevispa.com/en/progetti/the-restoration-of-the-leaning-tower-of-pisa/
- Exterior of the Leaning Tower (Pisa) in April 2024.1.jpg — image and reuse license (Wikimedia Commons / PaestumPaestum; 2023): https://commons.wikimedia.org/wiki/File:Exterior_of_the_Leaning_Tower_(Pisa)_in_April_2024.1.jpg

Sources checked: 2026-11-22. This brief is an original teaching aid. Source rights remain with their respective holders.