# Randle Reef — harbour sediment containment and final capping

Case reference year: 2026 | Location: Hamilton Harbour, Ontario, Canada

Contaminated harbour sediment is managed within a double-walled engineered containment facility. The owner separates wall construction, dredging and the later environmental cap and structural works.

## Suggested capstone study

An original teaching brief based on the documented project. Study assumptions and student designs are separate from the built project.

Design a staged containment-cell concept that can receive dredged sediment and later support a capped working surface.

### Inputs to assemble

- Extract the containment, dredging and cap-stage functions from the owner record.
- Define sediment compressibility, drainage and future surface loads as explicit study inputs.

### Deliverables

- Compare wall stability and fill settlement during successive dredging stages.
- Develop cap tolerances, consolidation monitoring and handover criteria for long-term operation.
- A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.
- A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points.

### Review questions

- How does sediment settlement affect cap grading and surface drainage?
- Why is completion of contaminant placement different from completion of the containment facility?

## Published project information

### Design — partial

The official project record identifies the staged remedy. The final cap is not labeled complete: the reviewed owner update schedules that phase for 2027.

### Cost information — not-found

A project-specific estimate, bid schedule or final account was not found in the reviewed sources.

### Schedule information — partial

The reviewed owner update schedules Stage 3 completion for 2027, subject to the additional structural work described there.

### Completion and records — not-found

Complete as-built drawings and acceptance records were not found in the reviewed sources.

## Project image

The Randle Reef containment facility in Hamilton Harbour in July 2024, as shown in the project’s dated milestone gallery. This construction-stage image does not establish completion of the final cap.

Credit: Randle Reef project gallery / Bay Area Restoration Council; project-partner photo credits are recorded in the source evidence
Image source: https://randlereef.ca/
Image rights: No open reuse license verified; original copyright retained — https://randlereef.ca/

## Sources

- Randle Reef remediation stages and status (Canada Water Agency; date not stated): https://www.canada.ca/en/canada-water-agency/freshwater-ecosystem-initiatives/great-lakes/great-lakes-protection/areas-concern/hamilton-harbour/randle-reef.html
- Randle Reef — project milestones and photographs (Randle Reef project / Bay Area Restoration Council; 2024): https://randlereef.ca/

Sources checked: 2026-11-22. This brief is an original teaching aid. Source rights remain with their respective holders.