# Seattle SR 99 tunnel — soft-ground tunnelling and settlement

Case reference year: 2019 | Location: Seattle, Washington, United States

The bored-tunnel replacement passed beneath downtown Seattle. Owner material includes geology/soils assessment, procurement information and completion history.

## Suggested capstone study

An original teaching brief based on the documented project. Study assumptions and student designs are separate from the built project.

Develop a settlement-risk and monitoring plan for an urban bored tunnel, including shaft construction and dewatering interactions.

### Inputs to assemble

- Extract route geology, groundwater and protected assets from Appendix P.
- Separate environmental alternatives from the subsequently selected design-build solution.

### Deliverables

- Estimate surface settlement for documented or explicitly assumed loss scenarios.
- Prepare shaft/uplift checks and a response plan for unexpected settlement.
- A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.
- A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points.

### Review questions

- Which site data control the decision, and what additional investigation would reduce uncertainty?
- How would the proposed solution change under the stated sensitivity cases, construction constraints and performance limits?

## Published project information

### Design — partial

The environmental geology/soils appendix and design-build procurement records establish ground risks and contract context, not a complete as-built tunnel design.

### Cost information — not-found

A project-specific estimate, bid schedule or final account was not found in the reviewed sources.

### Schedule information — partial

WSDOT identifies February 2019 completion; procurement and construction milestones are available on the owner pages.

### Completion and records — partial

The owner’s completed-project page records the outcome and links supporting material.

## Project image

The SR 99 tunnel project’s Bertha retrieval and repair site in Seattle, July 2015. The photograph shows the actual construction setting after the machine’s front section had been lifted for repairs.

Credit: SounderBruce from Seattle, United States
Image source: https://commons.wikimedia.org/wiki/File:Bertha_TBM_retrieval_site.jpg
Image rights: CC BY-SA 2.0 — https://creativecommons.org/licenses/by-sa/2.0

## Sources

- SR 99 tunnel — completed February 2019 (WSDOT; 2019): https://apps.wsdot.wa.gov/construction-planning/search-projects/sr-99-tunnel
- Alaskan Way Viaduct FEIS Appendix P — geology and soils (WSDOT; 2011): https://data.wsdot.wa.gov/publications/Viaduct/AWVFEIS-AppendixP.pdf
- SR 99 bored tunnel design-build procurement (WSDOT; 2010): https://wsdot.wa.gov/business-wsdot/contracting-opportunities/sr-99-alaskan-way-viaduct-sr-99-bored-tunnel-design-build-project
- Bertha TBM retrieval site.jpg — image and reuse license (Wikimedia Commons / SounderBruce from Seattle, United States; 2015): https://commons.wikimedia.org/wiki/File:Bertha_TBM_retrieval_site.jpg

Sources checked: 2026-11-22. This brief is an original teaching aid. Source rights remain with their respective holders.