# Second Avenue Subway Phase 1 — ground freezing at a TBM launch

Case reference year: 2017 | Location: Manhattan, New York, United States

Unexpected poor ground near the east running-tunnel launch required a revised sequence. The construction manager describes soil freezing while the TBM first advanced through the western alignment.

## Suggested capstone study

An original teaching brief based on the documented project. Study assumptions and student designs are separate from the built project.

Recover a tunnelling programme when a localized launch zone cannot support the planned hard-rock TBM excavation.

### Inputs to assemble

- Extract the reported launch problem and revised east/west drive sequence.
- Define a study freezing geometry and groundwater flow scenario for the local weak zone.

### Deliverables

- Estimate freeze formation time and identify verification boreholes and temperature targets.
- Plan thawing and lining load transfer with utilities and adjacent building monitoring.
- A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.
- A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points.

### Review questions

- Why can closely spaced borings still miss a localized poor-ground pocket?
- How does moving the TBM to a different drive reduce schedule risk without removing ground risk?

## Published project information

### Design — partial

The construction-manager account identifies the actual temporary treatment and sequencing response. It does not imply that the entire subway alignment was frozen.

### Cost information — not-found

A project-specific estimate, bid schedule or final account was not found in the reviewed sources.

### Schedule information — partial

WSP records west and east running-tunnel completion in 2011 and Phase 1 opening in January 2017.

### Completion and records — not-found

Complete as-built drawings and acceptance records were not found in the reviewed sources.

## Project image

Construction of the future 86th Street station in November 2013. MTA photograph from Second Avenue Subway Phase 1; the localized launch-freezing operation occurred elsewhere on the same phase.

Credit: Metropolitan Transportation Authority of the State of New York
Image source: https://commons.wikimedia.org/wiki/File:Second_Avenue_Subway_November_2013_(11344196583)_(2).jpg
Image rights: CC BY 2.0 — https://creativecommons.org/licenses/by/2.0

## Sources

- Opening and construction challenges (WSP, construction manager; date not stated): https://www.wsp.com/en-us/insights/new-york-opens-its-second-avenue-subway
- Phase 1 project methods (WSP; date not stated): https://www.wsp.com/en-gb/projects/second-avenue-subway
- Second Avenue Subway November 2013 (11344196583) (2).jpg — image and reuse license (Wikimedia Commons / Metropolitan Transportation Authority of the State of New York; 2013): https://commons.wikimedia.org/wiki/File:Second_Avenue_Subway_November_2013_(11344196583)_(2).jpg

Sources checked: 2026-11-22. This brief is an original teaching aid. Source rights remain with their respective holders.