# Teton Dam — internal erosion and first-filling investigation

Case reference year: 1976 | Location: Eastern Idaho, United States

The first-filling failure is documented through the Bureau of Reclamation’s history and the independent investigation report.

## Suggested capstone study

An original teaching brief based on the documented project. Study assumptions and student designs are separate from the built project.

Evaluate alternative core/filter and foundation-treatment concepts using the investigation as a forensic reference, without treating a classroom redesign as an approved remedy.

### Inputs to assemble

- Extract foundation geology, core/filter arrangement and reservoir-filling observations.
- Separate contemporary records from later interpretations of the failure mechanism.

### Deliverables

- Prepare a potential-failure-mode analysis and a filtered-contact concept.
- Design a first-filling monitoring and escalation plan.
- A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.
- A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points.

### Review questions

- Which site data control the decision, and what additional investigation would reduce uncertainty?
- How would the proposed solution change under the stated sensitivity cases, construction constraints and performance limits?

## Published project information

### Design — partial

The official archive provides the original design/foundation investigation context and the 1976 failure report; the dam was not rebuilt.

### Cost information — not-found

A project-specific estimate, bid schedule or final account was not found in the reviewed sources.

### Schedule information — partial

Failure occurred on 5 June 1976; the independent panel report was submitted in December 1976.

### Completion and records — partial

The official archive links the investigation and contemporary photographs; there is no completed replacement-dam record.

## Project image

The breach of Teton Dam, June 5, 1976. Historical project photograph from the U.S. Bureau of Reclamation collection.

Credit: U.S. Bureau of Reclamation / U.S. National Archives at Denver
Image source: https://commons.wikimedia.org/wiki/File:Breach_of_Teton_Dam_-_DPLA_-_657b673aa7b01ea982116a68bef069b4.jpg
Image rights: Public domain — https://commons.wikimedia.org/wiki/File:Breach_of_Teton_Dam_-_DPLA_-_657b673aa7b01ea982116a68bef069b4.jpg#Licensing

## Sources

- Teton Dam history and investigation archive (Bureau of Reclamation; 1976): https://www.usbr.gov/pn/snakeriver/dams/uppersnake/teton/
- Breach of Teton Dam - DPLA - 657b673aa7b01ea982116a68bef069b4.jpg — image and reuse license (Wikimedia Commons / Department of the Interior. Bureau of Reclamation. Denver Office. 3/4/1988; 1976): https://commons.wikimedia.org/wiki/File:Breach_of_Teton_Dam_-_DPLA_-_657b673aa7b01ea982116a68bef069b4.jpg

Sources checked: 2026-11-22. This brief is an original teaching aid. Source rights remain with their respective holders.