# Treasure Island redevelopment — liquefaction, settlement and shoreline stability

Case reference year: 2023 | Location: San Francisco Bay, United States

Redevelopment of the former naval station must address liquefiable fill, compressible bay mud and perimeter stability. City documents connect geotechnical work with groundwater, contaminated-soil management and phased infrastructure delivery.

## Suggested capstone study

An original teaching brief based on the documented project. Study assumptions and student designs are separate from the built project.

Develop a staged redevelopment concept that coordinates ground improvement with contaminated-soil handling and future flood levels.

### Inputs to assemble

- Separate dredged sand, young bay mud and shoreline fills in a study ground model.
- Select one development phase and identify which remediation and infrastructure works precede buildings.

### Deliverables

- Compare densification, drainage and soil mixing for the selected ground risks.
- Prepare a compatible earthworks, groundwater and monitoring plan with defined parcel interfaces.
- A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.
- A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points.

### Review questions

- Could improving liquefaction resistance leave long-term bay-mud settlement unresolved?
- How would an improvement method alter the contaminated-water management needs?

## Published project information

### Design — partial

The city’s management plan identifies ground risks and candidate mitigation measures. It is a programme-level source; a measure mentioned there is not automatically the final design for every parcel.

### Cost information — not-found

A project-specific estimate, bid schedule or final account was not found in the reviewed sources.

### Schedule information — partial

The planning authority describes multiple major phases and phased approvals. Use the selected phase’s current documents for a detailed programme.

### Completion and records — not-found

Complete as-built drawings and acceptance records were not found in the reviewed sources.

## Project image

Reconstruction of the Treasure Island Causeway in August 2021. This is a real redevelopment work area at the island connection, not a diagram of every ground-improvement method.

Credit: Pi.1415926535
Image source: https://commons.wikimedia.org/wiki/File:Treasure_Island_Causeway_reconstruction,_August_2021.jpg
Image rights: CC BY-SA 4.0 — https://creativecommons.org/licenses/by-sa/4.0

## Sources

- Revised soil and groundwater management plan (City and County of San Francisco; date not stated): https://www.sf.gov/sites/default/files/2023-12/SGMP_0004-007-005%20Treasure%20Island_Rev%2003-17-23-compressed.pdf
- Adopted development plans and environmental review (San Francisco Planning; date not stated): https://sfplanning.org/project/treasure-island-yerba-buena-island
- Treasure Island Causeway reconstruction, August 2021.jpg — image and reuse license (Wikimedia Commons / Pi.1415926535; date not stated): https://commons.wikimedia.org/wiki/File:Treasure_Island_Causeway_reconstruction,_August_2021.jpg

Sources checked: 2026-11-22. This brief is an original teaching aid. Source rights remain with their respective holders.