A highway embankment over organic clay used vertical drains, surcharge and staged filling, with remote monitoring of pore pressure and settlement.

## Suggested capstone study

An original teaching brief based on the documented project. Study assumptions and student designs are separate from the built project.

Design a preload programme that meets a highway opening deadline while controlling stability and residual settlement.

### Inputs to assemble

- Extract layer thicknesses, compression parameters and drain layout from the cited papers.
- Use measured settlement and pore-pressure stages to define the observation period.

### Deliverables

- Compare untreated waiting time with vertical/radial drainage and secondary compression.
- Set stage-release criteria and a contingency for slow pore-pressure dissipation.
- A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.
- A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points.

### Review questions

- Which site data control the decision, and what additional investigation would reduce uncertainty?
- How would the proposed solution change under the stated sensitivity cases, construction constraints and performance limits?

## Published project information

### Design — partial

The project authors describe drain spacing, surcharge, staged lifts, waiting periods and primary/post-surcharge secondary settlement.

### Cost information — partial

The source lists estimated alternatives from $0.3 million for surcharge-only to $1.8 million for a land bridge; these are comparison estimates, not audited final costs.

### Schedule information — partial

The documented drain/surcharge design targeted a five-month waiting period after staged filling.

### Completion and records — partial

The submitted case describes automated settlement, piezometric and earth-pressure monitoring.

## Published reference values

Use each value only within its stated scope. Reported costs have not been escalated or adjusted for inflation. These are source facts, not student design assumptions.

| Quantity | Value | Unit | Scope | Source locator |
| --- | ---: | --- | --- | --- |
| Organic-soil thickness | 34 | ft | Reported soft to very soft organic deposit above glacial till. | [Project Summary/Scope](https://www.geoinstitute.org/node/16159) |
| Typical drain spacing | 6 | ft | Triangular drain pattern over 80% of the embankment length. | [Project Summary/Scope](https://www.geoinstitute.org/node/16159) |
| Surcharge-only estimate | 300,000 | USD | Alternative with extended waiting period. | [Estimated Costs of Considered Options](https://www.geoinstitute.org/node/16159) |
| Drains and surcharge estimate | 500,000 | USD | Alternative including extended wait and geotechnical monitoring. | [Estimated Costs of Considered Options](https://www.geoinstitute.org/node/16159) |
| Geofoam estimate | 800,000 | USD | Lightweight-fill alternative. | [Estimated Costs of Considered Options](https://www.geoinstitute.org/node/16159) |
| Column-supported estimate | 1,200,000 | USD | Column-supported embankment alternative. | [Estimated Costs of Considered Options](https://www.geoinstitute.org/node/16159) |
| Land-bridge estimate | 1,800,000 | USD | Land-bridge alternative. | [Estimated Costs of Considered Options](https://www.geoinstitute.org/node/16159) |

## Project image

Vertical-drain construction on the US 14 embankment project near Nicollet, Minnesota.

Credit: Project photograph published by ASCE Geo-Institute; case submitted by Liang Chern Chow and Rich Lamb
Image source: https://www.geoinstitute.org/node/16159
Image rights: No open reuse license verified; original copyright retained — https://www.geoinstitute.org/node/16159

## Sources

- PVD and fill preloading — US Highway 14 (ASCE Geo-Institute / named case-history author; 2024): https://www.geoinstitute.org/node/16159

Sources checked: 2026-11-22. This brief is an original teaching aid. Source rights remain with their respective holders.