# US 231, Lacey Springs — bridging a moving landslide

Case reference year: 2020 | Location: Lacey Springs, Alabama, United States

After a rainfall-triggered slide, ALDOT selected two bridges across the unstable area rather than reconstructing the road on the moving embankment.

## Suggested capstone study

An original teaching brief based on the documented project. Study assumptions and student designs are separate from the built project.

Compare slope stabilization with a bridge solution that transfers loads through unstable ground while preserving the road alignment.

### Inputs to assemble

- Extract the evaluated alternatives, slope geometry constraints and monitored quantities.
- Identify the shear surface and pile-soil relative movement needed for a study shaft design.

### Deliverables

- Prepare an alternatives decision matrix and a lateral soil-loading sensitivity study.
- Develop an instrument layout with action levels and an accelerated procurement schedule.
- A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.
- A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points.

### Review questions

- Which site data control the decision, and what additional investigation would reduce uncertainty?
- How would the proposed solution change under the stated sensitivity cases, construction constraints and performance limits?

## Published project information

### Design — partial

FHWA documents alternative selection, drilled-shaft monitoring and construction delivery. It does not supply the full bridge/shaft design set.

### Cost information — partial

The source reports $27.4 million for the repair/betterment and describes comparison with more expensive alternatives.

### Schedule information — partial

The bridges opened on 28 September 2020; the case describes incentives and advance purchase of casings and girders.

### Completion and records — partial

The case discusses post-opening performance and ongoing instrumentation.

## Published reference values

Use each value only within its stated scope. Reported costs have not been escalated or adjusted for inflation. These are source facts, not student design assumptions.

| Quantity | Value | Unit | Scope | Source locator |
| --- | ---: | --- | --- | --- |
| Repair/betterment cost | 27,400,000 | USD | Two-bridge resilience solution; FHWA-reported package. | [Project Snapshot and page 2](https://www.fhwa.dot.gov/programadmin/er/er_case_alabama_us231.pdf) |
| Contract opening incentive | 2,490,000 | USD | Incentive described for opening by 2 November 2020; not an extra cost assumed to have been paid. | [Challenges and Lessons Learned](https://www.fhwa.dot.gov/programadmin/er/er_case_alabama_us231.pdf) |

## Project image

The completed US 231 bridges at Lacey Springs span the unstable slope, shown in the FHWA case study’s Figure 3.

Credit: Alabama Department of Transportation (ALDOT), published by FHWA
Image source: https://www.fhwa.dot.gov/programadmin/er/er_case_alabama_us231.pdf
Image rights: No open reuse license verified; original copyright retained — https://www.fhwa.dot.gov/programadmin/er/er_case_alabama_us231.pdf

## Sources

- FHWA-HIF-23-028 — US 231 landslide repair (FHWA / ALDOT; 2023): https://www.fhwa.dot.gov/programadmin/er/er_case_alabama_us231.pdf

Sources checked: 2026-11-22. This brief is an original teaching aid. Source rights remain with their respective holders.