# US 98, Florida — coastal roadway revetment

Case reference year: 2018 | Location: Florida Panhandle, United States

Following Hurricane Michael, roadway reconstruction incorporated articulated concrete blocks over filter fabric and bedding to reduce recurring embankment erosion.

## Suggested capstone study

An original teaching brief based on the documented project. Study assumptions and student designs are separate from the built project.

Design a roadway-embankment protection concept with particular attention to drains and interfaces where protection can be discontinuous.

### Inputs to assemble

- Extract the published shoulder section and treatment layers.
- Establish wave/current demands and filtration requirements from appropriate site data.

### Deliverables

- Check filter compatibility, toe/interface stability and treatment limits.
- Reproduce the stated cost comparison and test sensitivity to storm recurrence and residual damage.
- A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.
- A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points.

### Review questions

- Which site data control the decision, and what additional investigation would reduce uncertainty?
- How would the proposed solution change under the stated sensitivity cases, construction constraints and performance limits?

## Published project information

### Design — available

The FHWA case includes an as-built shoulder section, construction details and comparison with retaining-wall protection.

### Cost information — partial

The source reports $5.25 million for resilience improvements and a separate 1,000-ft comparison: $490,000 protection versus $724,000 reconstruction.

### Schedule information — partial

The study concerns recovery after the October 2018 hurricane; it also compares performance of protection installed after an earlier storm.

### Completion and records — partial

An as-built shoulder detail and observed performance comparisons appear in the source.

## Published reference values

Use each value only within its stated scope. Reported costs have not been escalated or adjusted for inflation. These are source facts, not student design assumptions.

| Quantity | Value | Unit | Scope | Source locator |
| --- | ---: | --- | --- | --- |
| Resilience-improvement cost | 5,250,000 | USD | Reported project resilience improvements. | [Project Snapshot](https://www.fhwa.dot.gov/programadmin/er/er_case_florida_hurricanemichael.pdf) |
| Protection comparison cost | 490,000 | USD per 1,000 ft | Articulated-concrete-block protection in the stated comparison. | [Page 2, cost comparison](https://www.fhwa.dot.gov/programadmin/er/er_case_florida_hurricanemichael.pdf) |
| Reconstruction comparison cost | 724,000 | USD per 1,000 ft | Road reconstruction without equivalent protection in the stated comparison. | [Page 2, cost comparison](https://www.fhwa.dot.gov/programadmin/er/er_case_florida_hurricanemichael.pdf) |

## Project image

The articulating concrete-block revetment beside US 98 in Florida, shown in Figure 3 of the FHWA case study.

Credit: Federal Highway Administration (FHWA)
Image source: https://www.fhwa.dot.gov/programadmin/er/er_case_florida_hurricanemichael.pdf
Image rights: U.S. government photograph — credited to FHWA in the source — https://www.fhwa.dot.gov/programadmin/er/er_case_florida_hurricanemichael.pdf

## Sources

- FHWA-HIF-23-025 — Hurricane Michael US 98 revetment (FHWA / FDOT; 2023): https://www.fhwa.dot.gov/programadmin/er/er_case_florida_hurricanemichael.pdf

Sources checked: 2026-11-22. This brief is an original teaching aid. Source rights remain with their respective holders.