# Virginia Route 288 — drilled-shaft quality evaluation

Case reference year: 2004 | Location: Richmond region, Virginia, United States

This design-build highway case documents drilled-shaft assessment using crosshole sonic logging and pile-integrity tests, including construction anomalies.

## Suggested capstone study

An original teaching brief based on the documented project. Study assumptions and student designs are separate from the built project.

Develop an inspection and acceptance plan for drilled shafts, including how to investigate an anomalous test result before deciding on remediation.

### Inputs to assemble

- Identify the shaft construction method, test types and reported anomalies.
- Separate an instrument anomaly from an independently confirmed physical defect.

### Deliverables

- Prepare a shaft inspection checklist and evidence-based test decision tree.
- Design a supplemental investigation and a repair-verification programme for a selected anomaly.
- A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.
- A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points.

### Review questions

- Which site data control the decision, and what additional investigation would reduce uncertainty?
- How would the proposed solution change under the stated sensitivity cases, construction constraints and performance limits?

## Published project information

### Design — partial

The technical paper addresses foundation evaluation and test interpretation; it is not the complete bridge design package.

### Cost information — not-found

A project-specific estimate, bid schedule or final account was not found in the reviewed sources.

### Schedule information — not-found

A dated project programme was not found in the reviewed sources; develop a study schedule from the documented method.

### Completion and records — partial

Published test and anomaly discussions support a quality-control exercise; the complete acceptance register is not included.

## Project image

Microcamera photograph of defective concrete inside a Route 288 drilled shaft, from the project evaluation paper’s Figure 9. This is the actual shaft inspection, rather than an exterior bridge view.

Credit: Emad Farouz, Paul Landers and Scott Webster (2004)
Image source: https://scholarsmine.mst.edu/icchge/5icchge/session09/5/
Image rights: CC BY-NC-ND 4.0 — noncommercial, unchanged reproduction — https://creativecommons.org/licenses/by-nc-nd/4.0/

## Sources

- Case history: Foundation evaluation for the Virginia Highway 288 project (Project authors / Missouri S&T Scholars’ Mine; 2004): https://scholarsmine.mst.edu/icchge/5icchge/session09/5/

Sources checked: 2026-11-22. This brief is an original teaching aid. Source rights remain with their respective holders.