# West Closure Complex — foundations on soft deltaic deposits

Case reference year: 2011 | Location: New Orleans, Louisiana, United States

The gate and pumping complex is founded in soft, compressible deltaic deposits. USACE authors describe exploration, laboratory characterization and pile testing used to develop design strength profiles.

## Suggested capstone study

An original teaching brief based on the documented project. Study assumptions and student designs are separate from the built project.

Design an investigation and test-pile programme for a critical coastal pumping structure on organic clay and silt.

### Inputs to assemble

- Identify the published depositional units and component-specific foundation requirements.
- Specify the additional parameters needed for axial, lateral and settlement analyses.

### Deliverables

- Develop characteristic strength profiles and compare test-pile interpretations.
- Prepare component foundation alternatives with construction access and long-term subsidence allowances.
- A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.
- A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points.

### Review questions

- Which laboratory sampling problems are most consequential in soft organic deltaic soils?
- How can a test-pile programme distinguish drivability constraints from long-term capacity?

## Published project information

### Design — partial

The technical publication explains the characterization programme and foundation-selection evidence. A complete final calculation set and acceptance database are not supplied by the abstract.

### Cost information — not-found

A project-specific estimate, bid schedule or final account was not found in the reviewed sources.

### Schedule information — not-found

A dated project programme was not found in the reviewed sources; develop a study schedule from the documented method.

### Completion and records — not-found

Complete as-built drawings and acceptance records were not found in the reviewed sources.

## Project image

The West Closure Complex during its 2023 annual operational testing. This is the completed gate and pumping project discussed in the foundation-characterization paper.

Credit: Team New Orleans, US Army Corps of Engineers
Image source: https://commons.wikimedia.org/wiki/File:West_Closure_Complex_testing,_Louisiana_2023_-_01.jpg
Image rights: Public domain — https://commons.wikimedia.org/wiki/File:West_Closure_Complex_testing,_Louisiana_2023_-_01.jpg#Licensing

## Sources

- Geocharacterization for design and construction of West Closure Complex (USACE project authors / ASCE; date not stated): https://ascelibrary.org/doi/10.1061/9780784413272.039
- Indexed technical-paper details (Transportation Research Board; date not stated): https://trid.trb.org/View/1303129
- West Closure Complex testing, Louisiana 2023 - 01.jpg — image and reuse license (Wikimedia Commons / Team New Orleans, US Army Corps of Engineers; 2023): https://commons.wikimedia.org/wiki/File:West_Closure_Complex_testing,_Louisiana_2023_-_01.jpg

Sources checked: 2026-11-22. This brief is an original teaching aid. Source rights remain with their respective holders.