{"id":"west-closure-complex","title":"West Closure Complex — foundations on soft deltaic deposits","summary":"The gate and pumping complex is founded in soft, compressible deltaic deposits. USACE authors describe exploration, laboratory characterization and pile testing used to develop design strength profiles.","topics":["deep-foundations","laboratory-testing","site-investigation","problem-soils","coastal-offshore"],"country":"United States","region":"New Orleans, Louisiana","owner":"US Army Corps of Engineers","year":2011,"yearLabel":"Case reference year","projectType":"Design, construction and performance","methods":["CPT interpretation","Strength profiling","Static and dynamic pile tests"],"documentationLevel":"technical-paper","design":{"availability":"partial","summary":"The technical publication explains the characterization programme and foundation-selection evidence. A complete final calculation set and acceptance database are not supplied by the abstract.","sourceIds":["s1","s2"]},"cost":{"availability":"not-found","summary":"A project-specific estimate, bid schedule or final account was not found in the reviewed sources.","sourceIds":[]},"schedule":{"availability":"not-found","summary":"A dated project programme was not found in the reviewed sources; develop a study schedule from the documented method.","sourceIds":[]},"records":{"availability":"not-found","summary":"Complete as-built drawings and acceptance records were not found in the reviewed sources.","sourceIds":[]},"capstone":{"label":"Suggested capstone study","scope":"An original teaching brief based on the documented project. Study assumptions and student designs are separate from the built project.","brief":"Design an investigation and test-pile programme for a critical coastal pumping structure on organic clay and silt.","inputs":["Identify the published depositional units and component-specific foundation requirements.","Specify the additional parameters needed for axial, lateral and settlement analyses."],"deliverables":["Develop characteristic strength profiles and compare test-pile interpretations.","Prepare component foundation alternatives with construction access and long-term subsidence allowances.","A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.","A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points."],"questions":["Which laboratory sampling problems are most consequential in soft organic deltaic soils?","How can a test-pile programme distinguish drivability constraints from long-term capacity?"],"output":"Design report, calculation workbook, concept drawings, quantity schedule and construction programme."},"sources":[{"id":"s1","title":"Geocharacterization for design and construction of West Closure Complex","url":"https://ascelibrary.org/doi/10.1061/9780784413272.039","publisher":"USACE project authors / ASCE","year":null,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s2","title":"Indexed technical-paper details","url":"https://trid.trb.org/View/1303129","publisher":"Transportation Research Board","year":null,"access":"public-link","license":"Publisher-hosted; redistribution permission not established","notes":"","checked":"2026-11-22"},{"id":"s3","title":"West Closure Complex testing, Louisiana 2023 - 01.jpg — image and reuse license","url":"https://commons.wikimedia.org/wiki/File:West_Closure_Complex_testing,_Louisiana_2023_-_01.jpg","publisher":"Wikimedia Commons / Team New Orleans, US Army Corps of Engineers","year":2023,"access":"public-link","license":"Public domain","notes":"Project image source. Unmodified publisher-generated display-size file; the original source URL and publisher metadata are retained. No AI-generated replacement or content alteration.","checked":"2026-11-22","localAssetIds":["project-image"]}],"assets":[{"id":"schematic","title":"Conceptual study schematic","kind":"figure","fileName":"west-closure-complex.svg","mimeType":"image/svg+xml","bytes":1199,"sha256":"2e6aeebf9456a19bc9da1a7d3b9c13bec3912b8bc79cc219008f227e2613f027","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/west-closure-complex/download/schematic"},{"id":"project-image","title":"West Closure Complex testing, Louisiana 2023 - 01.jpg","kind":"project-image","fileName":"west-closure-complex.jpg","mimeType":"image/jpeg","bytes":151852,"sha256":"24ff3fd3f6dcdabc9dc258256e332c4cd04548f9398b99d6a9568ecf307d5697","sourceId":"s3","license":"Public domain","width":1280,"height":854,"credit":"Team New Orleans, US Army Corps of Engineers","sourceUrl":"https://commons.wikimedia.org/wiki/File:West_Closure_Complex_testing,_Louisiana_2023_-_01.jpg","licenseUrl":"https://commons.wikimedia.org/wiki/File:West_Closure_Complex_testing,_Louisiana_2023_-_01.jpg#Licensing","imageDate":"2023-05-11 10:19:39","evidenceFile":"image-provenance/west-closure-complex-commons.json","evidenceSha256":"8d095d27d0a6bde356c186d31570a687b18cca899f9d4b359ceef56a389fc721","transformations":"Unmodified publisher-generated display-size file; the original source URL and publisher metadata are retained. No AI-generated replacement or content alteration.","originalUrl":"https://upload.wikimedia.org/wikipedia/commons/1/13/West_Closure_Complex_testing%2C_Louisiana_2023_-_01.jpg","downloadUrl":"/cases/west-closure-complex/download/project-image","originalSha1":"13204edda35ce31161453465ac85aa6fac1fe530","imageDownloadAllowed":true,"rightsBasis":"See the per-image provenance record and linked license; source hosting alone is not the rights basis."},{"id":"capstone-brief","title":"Capstone brief (Markdown)","kind":"brief","fileName":"west-closure-complex-capstone.md","mimeType":"text/markdown","bytes":3328,"sha256":"fec13d74d145a189bb0a084cecd6f93a464bf18f7883a87b18e15f167b3f654e","sourceId":null,"license":"Original Foundation Design teaching material","downloadUrl":"/cases/west-closure-complex/download/capstone-brief"}],"figure":{"assetId":"project-image","kind":"photograph","alt":"The West Closure Complex during its 2023 annual operational testing.","caption":"The West Closure Complex during its 2023 annual operational testing. This is the completed gate and pumping project discussed in the foundation-characterization paper.","credit":"Team New Orleans, US Army Corps of Engineers","sourceUrl":"https://commons.wikimedia.org/wiki/File:West_Closure_Complex_testing,_Louisiana_2023_-_01.jpg","license":"Public domain","licenseUrl":"https://commons.wikimedia.org/wiki/File:West_Closure_Complex_testing,_Louisiana_2023_-_01.jpg#Licensing","width":1280,"height":854,"imageDate":"2023-05-11 10:19:39","imageDownloadAllowed":true},"figureCaption":"The West Closure Complex during its 2023 annual operational testing. This is the completed gate and pumping project discussed in the foundation-characterization paper.","qualityNotes":[],"checked":"2026-11-22","addedIn":"r13","curatedOrder":73,"referenceValues":[],"teachingFigureCaption":"Conceptual study schematic; not an as-built project drawing.","imageEvidence":{"status":"acquired","identityVerified":true,"evidenceFile":"image-provenance/west-closure-complex-commons.json","evidenceSha256":"8d095d27d0a6bde356c186d31570a687b18cca899f9d4b359ceef56a389fc721","visualReview":"Viewed the complete publisher photograph in the final contact sheets or individually and compared it with the source identity, date, and caption. The caption distinguishes project context from the particular underground treatment or construction stage.","checked":"2026-11-22"},"localReportCount":0,"downloadBytes":156379,"sourceCount":3,"url":"/cases/west-closure-complex"}