# Wolf Creek Dam — karst-foundation cutoff wall

Case reference year: 2013 | Location: Jamestown, Kentucky, United States

A deep concrete barrier and associated grouting addressed seepage through the dam’s karst foundation. USACE documents completion and project scope.

## Suggested capstone study

An original teaching brief based on the documented project. Study assumptions and student designs are separate from the built project.

Compare a cutoff wall and grouting strategy for an operating dam over soluble rock, including continuity verification and reservoir constraints.

### Inputs to assemble

- Extract the documented barrier dimensions and geological problem.
- Define an explicitly sourced or assumed permeability model for the study seepage calculation.

### Deliverables

- Develop a seepage/uplift comparison and a wall-continuity QA plan.
- Prepare a construction platform section and a reservoir/instrumentation hold-point sequence.
- A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.
- A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points.

### Review questions

- Which site data control the decision, and what additional investigation would reduce uncertainty?
- How would the proposed solution change under the stated sensitivity cases, construction constraints and performance limits?

## Published project information

### Design — partial

The completion account describes approximately 1,197 overlapping piles forming a 4,000-foot barrier. It does not provide a complete issued-for-construction package.

### Cost information — partial

The March 2013 USACE account identifies a $594 million rehabilitation project; this is programme scope, not the wall’s final unit-price account.

### Schedule information — partial

Last pile placement was reported on 6 March 2013, nine months ahead of the then-planned December completion.

### Completion and records — partial

USACE records barrier completion and the subsequent reservoir review.

## Project image

Concrete barrier-wall construction in the Wolf Creek Dam embankment on May 2, 2012. U.S. Army Corps of Engineers photograph by Leon Roberts.

Credit: Leon Roberts / U.S. Army Corps of Engineers
Image source: https://www.dvidshub.net/image/1965076/nashville-district-highlights-its-notable-projects-leading-into-national-dam-safety-awareness-day
Image rights: Public domain — U.S. federal government work — https://www.dvidshub.net/about/copyright

## Sources

- Nashville District completes Wolf Creek Dam barrier wall (USACE / DVIDS; 2013): https://www.dvidshub.net/news/103103/nashville-district-completes-wolf-creek-dam-barrier-wall
- Wolf Creek Dam barrier-wall construction — published image and source (DVIDS / U.S. Army Corps of Engineers; 2012): https://www.dvidshub.net/image/1965076/nashville-district-highlights-its-notable-projects-leading-into-national-dam-safety-awareness-day

Sources checked: 2026-11-22. This brief is an original teaching aid. Source rights remain with their respective holders.