Cases / Project case study

Block Island Wind Farm — pile foundations and measured stiffness

The five-turbine offshore project has public foundation-installation observations and subsequent structural-monitoring studies.

Coastal and offshore foundationsPiles and drilled shaftsLateral foundations and interactionMonitoring and observational designEarthquakes and liquefaction
Installation of Block Island Wind Farm jacket foundations in Rhode Island waters in 2015.
Installation of Block Island Wind Farm jacket foundations in Rhode Island waters in 2015. The jackets were built in Louisiana and transported to the offshore site.BOEM-OPA · Image source · CC BY-SA 2.0

Project evidence

Design & engineering

Partial record

The original geotechnical consultant describes interpreted profiles and pile-capacity work. BSEE publishes a foundation-stiffness study for one turbine.

Sources: s1 · s2 · s3

Cost & estimating

Partial record

The BSEE page lists a $608,722 monitoring-research award; this is not the wind-farm construction cost.

Sources: s1 · s2 · s3

Schedule & construction

Partial record

The Rhode Island owner/regulator record identifies commercial operation in December 2016.

Sources: s3

Completion & performance

Partial record

The regulator records and BSEE technical attachments support construction/performance review.

Sources: s1 · s2 · s3

Engineering methods

Jacket pilesFoundation stiffnessStructural health monitoring

Suggested teaching exercise

Capstone project brief

Compare predicted and observed foundation stiffness for an offshore wind support, including how uncertain soil springs affect structural response.

Starting information & inputs

  • Extract pile/structure information from published monitoring and technical reports.
  • Distinguish one instrumented turbine from the full wind farm and retain marine ground-condition differences.

Suggested deliverables

  • Prepare an axial/lateral soil-spring sensitivity model and identify validation data.
  • Develop an installation and monitoring plan with offshore access and scour considerations.
  • A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.
  • A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points.

Design questions

  • Which site data control the decision, and what additional investigation would reduce uncertainty?
  • How would the proposed solution change under the stated sensitivity cases, construction constraints and performance limits?

The brief is a proposed educational exercise based on the cited project, not the original designer's instruction or a complete construction document set.

Sources & original records