Frances Badelow and Harry G. Poulos / Japanese Geotechnical Society
public-link · Publisher-hosted; redistribution permission not established · Checked 2026-11-22Burj Khalifa — piled-raft settlement design
The tower uses a piled raft in weak sedimentary rock. The foundation designer publishes an analysis process linking ground characterization, trial pile testing and settlement predictions for super-tall towers.
Project evidence
Design & engineering
Partial recordThe designer paper provides a foundation-design case and discusses piled-raft interaction. Access to a publication does not establish availability of the complete issued-for-construction package.
Cost & estimating
Not located in cited sourcesA project-specific estimate, bid schedule or final account was not found in the reviewed sources.
Schedule & construction
Not located in cited sourcesA dated project programme was not found in the reviewed sources; develop a study schedule from the documented method.
Completion & performance
Not located in cited sourcesComplete as-built drawings and acceptance records were not found in the reviewed sources.
Engineering methods
Suggested teaching exercise
Capstone project brief
Compare a conventional pile-group design with a settlement-led piled-raft concept for a heavily loaded tower on weak rock.
Starting information & inputs
- Extract the published stratigraphy, raft geometry and pile test interpretation.
- Set an explicit study loading envelope instead of inferring column loads from building height.
Suggested deliverables
- Assess pile–raft load sharing and differential settlement under gravity and overturning actions.
- Prepare a trial-pile programme and a monitoring layout that can distinguish group interaction from single-pile behavior.
- A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.
- A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points.
Design questions
- When does an acceptable single-pile capacity still produce unacceptable raft settlement?
- How sensitive is load sharing to the stiffness assigned to weathered rock?
Sources & original records
Multiplex
public-link · Publisher-hosted; redistribution permission not established · Checked 2026-11-22Wikimedia Commons / Laika ac · 2015
Project image source. Unmodified publisher-generated display-size file; the original source URL and publisher metadata are retained. No AI-generated replacement or content alteration.
public-link · CC BY-SA 2.0 · Checked 2026-11-22