Cases / Project case study

Dalton Highway MP 209–222 — air-convection embankment trial

Twelve embankment test sections compared air-convection shoulder geometry and rock classes over thaw-unstable permafrost near milepost 219.

Permafrost and cold regionsEarthworks and pavement subgradesMonitoring and observational designEstimating, sequencing and project delivery
Placement of the coarse rock shoulder for the Dalton Highway air-convection embankment experiment. Original Figure 2 in the final report.
Placement of the coarse rock shoulder for the Dalton Highway air-convection embankment experiment. Original Figure 2 in the final report.Alaska DOT&PF; report by Matt Billings and Michael Berggren (2022) · Image source · No open reuse license verified; original copyright retained

Project evidence

Design & engineering

Partial record

The final report documents sections installed in 2017–2018 and three years of monitoring; it evaluates thermal performance rather than a complete climate-life prediction.

Sources: s1

Cost & estimating

Not located in cited sources

A project-specific estimate, bid schedule or final account was not found in the reviewed sources.

Schedule & construction

Partial record

Test sections were installed in 2017–2018 and monitored for three years.

Sources: s1

Completion & performance

Partial record

The 2022 final report presents the trial performance evaluation.

Sources: s1

Engineering methods

Air-convection embankmentInsulationThermal monitoring

Suggested teaching exercise

Capstone project brief

Select an embankment shoulder treatment using measured thermal response and construction quantity comparisons.

Starting information & inputs

  • Extract section dimensions, rock class and ground-temperature records.
  • Separate effects of embankment height, rock size and shoulder width.

Suggested deliverables

  • Compare thermal performance and rock quantities for the test configurations.
  • Specify monitoring and maintenance needed to retain open pore spaces and drainage.
  • A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.
  • A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points.

Design questions

  • Which site data control the decision, and what additional investigation would reduce uncertainty?
  • How would the proposed solution change under the stated sensitivity cases, construction constraints and performance limits?

The brief is a proposed educational exercise based on the cited project, not the original designer's instruction or a complete construction document set.

Sources & original records