Project case author / ASCE Geo-Institute
public-link · Publisher-hosted; redistribution permission not established · Checked 2026-11-22East Side Access — frozen support beneath Northern Boulevard
A short mined connection beneath active transport infrastructure used a frozen soil arch for temporary support and groundwater cutoff. The project sources distinguish local freezing from the wider East Side Access tunnel programme.
Project evidence
Design & engineering
Partial recordThe contractor case and design-team account describe the Northern Boulevard crossing and movement control. Photographs of the wider project are identified as context unless the crossing itself is shown.
Cost & estimating
Not located in cited sourcesA project-specific estimate, bid schedule or final account was not found in the reviewed sources.
Schedule & construction
Not located in cited sourcesA dated project programme was not found in the reviewed sources; develop a study schedule from the documented method.
Completion & performance
Not located in cited sourcesComplete as-built drawings and acceptance records were not found in the reviewed sources.
Engineering methods
Suggested teaching exercise
Capstone project brief
Design a short mined crossing beneath an operating subway box where drawdown and ground movement are tightly constrained.
Starting information & inputs
- Extract the access-shaft arrangement, groundwater setting and supported transport structures.
- Distinguish freeze-induced heave from excavation-induced settlement in the monitoring plan.
Suggested deliverables
- Develop staged thermal and stability checks for a frozen arch.
- Coordinate compensation grouting, lining installation and controlled thaw with operating railway limits.
- A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.
- A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points.
Design questions
- Which monitoring trends would indicate that freezing is protecting the face but damaging the asset above?
- Why must the temporary frozen ground remain effective until lining load transfer is complete?
Sources & original records
Mott MacDonald
public-link · Publisher-hosted; redistribution permission not established · Checked 2026-11-22Wikimedia Commons / Metropolitan Transportation Authority of the State of New York · 2012