Glen Canyon Dam — sandstone abutments and controlled seepage

The high concrete dam required canyon-wall stabilization, river diversion and excavation to sandstone bedrock. Reclamation describes rock bolts, seepage measurement and the geological basis of the site selection.

Rock slopes and foundationsDams and leveesSeepage and internal erosionDewatering and groundwaterSite investigation
Glen Canyon Dam under construction in 1962.
Glen Canyon Dam under construction in 1962. The historical photograph shows the actual dam and sandstone canyon abutments.U.S. Bureau of Reclamation · Image source · Public domain

Project evidence

Design & engineering

Partial record

The owner history explains the construction systems; the USGS regional map supports geological context. Regional mapping does not replace discontinuity surveys at individual abutments.

Sources: s1 · s2

Cost & estimating

Not located in cited sources

A project-specific estimate, bid schedule or final account was not found in the reviewed sources.

Schedule & construction

Partial record

Reclamation records major construction milestones and dedication in 1966; detailed daily excavation records are not included.

Sources: s1 · s2

Completion & performance

Not located in cited sources

Complete as-built drawings and acceptance records were not found in the reviewed sources.

Engineering methods

Rock boltingAbutment stabilitySeepage measurementRiver diversion

Suggested teaching exercise

Capstone project brief

Develop rock-abutment support and seepage-monitoring concepts for a dam in fractured sandstone.

Starting information & inputs

  • Use the regional map and owner account to distinguish formation-scale geology from local joints.
  • Identify the temporary diversion and excavation stages that precede concrete placement.

Suggested deliverables

  • Perform a study wedge-stability check with bolt and groundwater sensitivities.
  • Design a drainage and weir-monitoring layout that distinguishes changing seepage paths from reservoir-level effects.
  • A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.
  • A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points.

Design questions

  • Why is measurable seepage not by itself evidence of dam failure?
  • What site mapping is required before using a regional joint orientation in a support design?

The brief is a proposed educational exercise based on the cited project, not the original designer's instruction or a complete construction document set.

Sources & original records

Glen Canyon Dam 1962.jpg — image and reuse license ↗

Wikimedia Commons / U.S. Bureau of Reclamation · 1962

Project image source. Unmodified publisher-generated display-size file; the original source URL and publisher metadata are retained. No AI-generated replacement or content alteration.

public-link · Public domain · Checked 2026-11-22