Cases / Project case study

San Vicente Dam raise — rock preparation and RCC interface

The existing concrete dam was raised using roller-compacted concrete. Owner documents connect excavation to competent rock, treatment of localized poor material and seepage control with the enlarged structure.

Rock slopes and foundationsDams and leveesSeepage and internal erosionExcavation supportEstimating, sequencing and project delivery
Aerial view of the raised San Vicente Dam and reservoir in San Diego County.
Aerial view of the raised San Vicente Dam and reservoir in San Diego County. The photograph shows the actual completed dam, not a rendering of the proposed raise.Redideo · Image source · CC BY-SA 4.0

Project evidence

Design & engineering

Partial record

The environmental design commitments describe proposed foundation measures; the completion account establishes the constructed dam raise. Detailed final foundation treatment records are not included.

Sources: s1 · s2

Cost & estimating

Not located in cited sources

A project-specific estimate, bid schedule or final account was not found in the reviewed sources.

Schedule & construction

Partial record

The owner reports foundation preparation beginning in June 2009 and construction ending in June 2014.

Sources: s1 · s2

Completion & performance

Not located in cited sources

Complete as-built drawings and acceptance records were not found in the reviewed sources.

Engineering methods

Rock excavationDental concreteConsolidation groutingRCC

Suggested teaching exercise

Capstone project brief

Plan foundation preparation and construction of an RCC enlargement beside an existing gravity dam.

Starting information & inputs

  • Extract the owner’s foundation-treatment commitments and construction milestones.
  • Identify rock defects, existing-dam support and old/new concrete interfaces needing detailed verification.

Suggested deliverables

  • Prepare excavation acceptance criteria, dental-concrete details and grout/drain layouts.
  • Check a representative enlarged section for sliding and uplift, with treatment effectiveness sensitivities.
  • A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.
  • A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points.

Design questions

  • How does excavating beside the original dam change temporary stability requirements?
  • Which field observations should decide whether a weak rock pocket is removed or treated?

The brief is a proposed educational exercise based on the cited project, not the original designer's instruction or a complete construction document set.