Design & engineering
Partial recordThe published case describes battered micropiles, anchor layout, soil-rock sliding interface and instrumentation.
Sources: s1
Cost & estimating
Not located in cited sourcesA project-specific estimate, bid schedule or final account was not found in the reviewed sources.
Schedule & construction
Partial recordConstruction ran from April to September 1997; monitoring continued through June 1998.
Sources: s1
Completion & performance
Partial recordInclinometers, piezometers, strain gauges, load cells and survey measurements are described.