FHWA / Iowa DOT · 2023
public-link · US federal agency case study; original credits retained · Checked 2026-11-22US 34, Iowa — flood-resistant embankment matting
After the 2019 flood damaged the road embankment, Iowa DOT selected anchored concrete-block matting and evaluated recurring-damage economics.
Project evidence
Design & engineering
Partial recordThe FHWA case documents flexible matting, economic assumptions and the treated extent; full construction drawings are not attached.
Cost & estimating
Partial recordThe case separates $6.8 million emergency restoration from $2.3 million resilience improvements and reports a benefit-cost ratio of 1.07.
Schedule & construction
Partial recordEmergency restoration was completed in May 2019; the matting installation followed approval in 2021.
Completion & performance
Partial recordThe case describes installed protection along 2.25 miles and the economic review.
Engineering methods
Published quantities & cost references
These values retain the scope and date basis of their cited source. Estimates, alternatives and partial packages are identified individually.
| Item | Reported value | Scope & source |
|---|---|---|
| Emergency restoration cost | 6,800,000 USD | Emergency restoration following the 2019 event.As reported; no escalation or inflation adjustment.Source s1 · Page 1, emergency restoration |
| Resilience-improvement cost | 2,300,000 USD | Concrete-block matting resilience treatment.As reported; no escalation or inflation adjustment.Source s1 · Page 1, Project Snapshot |
| Treatment extent | 2.25 mile | Reported embankment protection extent.Reported project length.Source s1 · Resilience Features |
| Reported benefit-cost ratio | 1.07 dimensionless | Source economic evaluation; reproduce its assumptions before comparison.Source calculation result.Source s1 · Resilience Features |
Suggested teaching exercise
Capstone project brief
Design a flood-resistant embankment protection scheme that explicitly includes residual damage in its economic assessment.
Starting information & inputs
- Extract the damaged/treatment extents and recurrence assumptions.
- Identify geotechnical filter, anchorage and subgrade conditions needed beyond the case summary.
Suggested deliverables
- Prepare a typical treatment section and interface/filter checks.
- Reproduce the benefit-cost calculation and vary residual repair costs and flood frequency.
- A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.
- A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points.
Design questions
- Which site data control the decision, and what additional investigation would reduce uncertainty?
- How would the proposed solution change under the stated sensitivity cases, construction constraints and performance limits?