17th Street Canal — floodwall failure and reevaluation

Post-Katrina investigations and reevaluation examine the canal floodwall/levee system, including the soil profile and interaction between the wall and foundation.

Dams and leveesSeepage and internal erosionRetaining walls and anchorsLaboratory testing and parametersSite investigation
Aerial view of the 17th Street Canal breach and surrounding flooding after Hurricane Katrina.
Aerial view of the 17th Street Canal breach and surrounding flooding after Hurricane Katrina in August 2005. NOAA photograph.NOAA · Image source · Public domain

Project evidence

Design & engineering

Partial record

USACE publishes reevaluation material and later remediation decisions. The record distinguishes the original I-wall problem from subsequent protection measures.

Sources: s1 · s2

Cost & estimating

Not located in cited sources

A project-specific estimate, bid schedule or final account was not found in the reviewed sources.

Schedule & construction

Not located in cited sources

A dated project programme was not found in the reviewed sources; develop a study schedule from the documented method.

Completion & performance

Partial record

The reevaluation and remediation decisions are linked; complete as-built records for all later works are not included.

Sources: s1 · s2

Engineering methods

Floodwall stabilityUndrained strengthWater-filled gapSeepage

Suggested teaching exercise

Capstone project brief

Reconcile competing ground-model and wall-loading assumptions, then propose a monitored remediation concept.

Starting information & inputs

  • Extract a published cross section and the laboratory/field-test evidence for foundation strength.
  • Identify canal water levels, wall embedment and alternative assumptions for a water-filled gap.

Suggested deliverables

  • Compare effective-stress/undrained equilibrium cases and sensitivity to weak layers.
  • Develop a remediation alternatives assessment and a verification investigation.
  • A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.
  • A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points.

Design questions

  • Which site data control the decision, and what additional investigation would reduce uncertainty?
  • How would the proposed solution change under the stated sensitivity cases, construction constraints and performance limits?

The brief is a proposed educational exercise based on the cited project, not the original designer's instruction or a complete construction document set.

Sources & original records